HomeMy WebLinkAboutMINUTES - 12062011 - C.03RECOMMENDATION(S):
ADOPT Resolution No. 2011/473 accepting as complete the contracted work performed by
Thomas D. Eychner Co., Inc., for demolition of a structure for the SR4 (E) Widening:
Somersville to SR160 Project, as recommended by the Public Works Director, Antioch area.
FISCAL IMPACT:
The cost of this demolition is $78,560.00 and is funded 100% by the Contra Costa
Transportation Authority (CCTA).
BACKGROUND:
The Public Works Director reports that said work has been inspected and complies with the
special provisions and standard specifications and recommends its acceptance as complete
as of October 20, 2011, for Assessor’s Parcel No. 067-341-032 in Antioch.
CONSEQUENCE OF NEGATIVE ACTION:
Thomas D. Eychner Co., Inc. will not be paid and acceptance notification will not be
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On: 12/06/2011 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:John Gioia, District I
Supervisor
Gayle B. Uilkema, District II
Supervisor
Mary N. Piepho, District III
Supervisor
Karen Mitchoff, District IV
Supervisor
Federal D. Glover, District V
Supervisor
Contact: Angela Bell; (925)
313-2337
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board
of Supervisors on the date shown.
ATTESTED: December 6, 2011
David Twa, County Administrator and Clerk of the Board of Supervisors
By: STACEY M. BOYD, Deputy
cc: Real Property Division; Fina Prak
C. 3
To:Board of Supervisors
From:Julia R. Bueren, Public Works Director/Chief Engineer
Date:December 6, 2011
Contra
Costa
County
Subject:Accepting and Giving Notice of Completion of Contract for Demolition of property, Antioch area. Project
No. 4660-6X4168
recorded.
CHILDREN'S IMPACT STATEMENT:
Not applicable.
ATTACHMENTS
Resolution No. 2011/473