HomeMy WebLinkAboutMINUTES - 12062011 - C.04RECOMMENDATION(S):
ADOPT Resolution No. 2011/471 accepting as complete the contracted work performed by
Maggiora & Ghilotti, Inc., for the Alhambra Valley Road Safety and Bicycle Facility
Improvements project, Project No. 0662-6R4095, as recommended by the Public Works
Director.
FISCAL IMPACT:
The project construction was funded by 56% Proposition 1B funds, 40% Federal High Risk
Rural Road funds, and 4% Local Road Funds.
BACKGROUND:
The Public Works Director reports that said work has been inspected and complies with the
approved plans, special provisions and standard specifications and recommends its
acceptance as complete as of October 25, 2011.
CONSEQUENCE OF NEGATIVE ACTION:
The contractor will not be paid and acceptance notification will not be recorded.
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On: 12/06/2011 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:John Gioia, District I Supervisor
Gayle B. Uilkema, District II
Supervisor
Mary N. Piepho, District III
Supervisor
Karen Mitchoff, District IV
Supervisor
Federal D. Glover, District V
Supervisor
Contact: Kevin Emigh, (925)
313-2233
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board
of Supervisors on the date shown.
ATTESTED: December 6, 2011
David Twa, County Administrator and Clerk of the Board of Supervisors
By: STACEY M. BOYD, Deputy
cc: Kevin Emigh, Janet Dowling, Paulette Denison, Maggiora & Ghilotti, Inc., Kathy Guruwaya
C. 4
To:Board of Supervisors
From:Julia R. Bueren, Public Works Director/Chief Engineer
Date:December 6, 2011
Contra
Costa
County
Subject:ACCEPTANCE & Giving Notice of Completion of Contract for Alhambra Valley Road Safety and Bicycle
Facility Improvements, Project No. 0662-6R4095
CHILDREN'S IMPACT STATEMENT:
Not Applicable.
ATTACHMENTS
Resolution No.
2011/471