HomeMy WebLinkAboutMINUTES - 12091986 - T.4 f _,
TO: BOARD OF SUPERVISORS
Contra
FROM: Phil Batchelor S}
County Administrator Costa
DATE: December 9, 1986 County
SUBJECT: Approval of Schematic Phase Design
West County Justice Center Project
SPECIFIC REQUEST(S) OR RECOMMENDATION(S) & BACKGROUND AND JUSTIFICATION
RECOMMENDATIONS:
1 . ACCEPT Report from the County Administrator on design and construction
cost issues relating to the West County Justice Center Project .
2 . APPROVE The Schematic Phase of Design .
REASONS FOR RECOMMENDATIONS/BACKGROUND:
A. HISTORY OF PROJECT DEVELOPMENT
As a result of overcrowding at the County' s adult detention facilities
in Mari.inez , Richmond and Clayton, the County made application for a
$36 , 570 , 521 grant to the California Board of Corrections on November 17 ,
1983 . This grant was approved for the development of a 560-bed minimum-
medium correctional facility in accordance with the County Jail Capital
t
Expenditure Bond Act .
From the creation of the Correctional Facility Planning Task Force in
December 1982 until December 1985 , the County conducted a comprehensive
site selection process in which 29 sites were seriously studied prior
to the selection of the preferred location for the West County Justice
Cente-l- ('WCJC ) . In November 1984 , the architectural/planning firm of
Design Partnership began predesign programming studies .
The selection of the project Architect began on January 4 , 1935 , followed
by the Board ' s selecting the joint venture firm of Dworsky/Design
Partnership on April- 9 , 1985 . The contract was awarded December 17 ,
1985 .
The Project/Construction Management selection process began on
Seotarnber 10 , 1985 . The Board selected O' Brien-Kreitzberg and Associates
on March 3 , 1986' and awarded a. contract for management services three
months late__.
The Architect ' s Notice to Proceed was issued on July 7 , 1986 , thus begin-
ning the three months Schematic Phase of design. On July 8 , the Board
approved the Architectural Predesign Program. During Schematic Design
phase , the Architect conducted four design workshops for County project
team members representing the Sheriff-Coroner, County Administrator and
General Services Department .
CONTINUED ON ATTACHMENT:X YES SIGNATURE:
RECOMMENDATION OF COUNTY ADMINISTRATOR RECOM ENDATIO F BOAR COMMITTEE
APPROVE OTHER
SIGNATURE(S)
.2 ACTION OF BOARD ON D2CeIClbeT 9, 1986 APPROVED AS RECOMMENDED X OTHER
VOTE OF SUPERVISORS
i
_X UNANIMOUS (ABSENT ) I HEREBY CERTIFY THAT THIS IS A TRUE
AYES: NOES: AND CORRECT COPY OF AN ACTION TAKEN
ABSENT: ABSTAIN: AND ENTERED ON THE MINUTES OF THE BOARD
OF SUPERVISORS ON THE DATE SHOWN,
CC: CAO-Justice System Programs ATTESTED
Sheriff-Coroner nil UWhelor, eFk of the Watd
Members , WCJC Advisory Group &Ip6Mm adCollatyAdminl*dv
M382/7-83
8Y DEPUTY
Approval of Schematic Phase Design December 9 , 1986
West CountylJustice Center Page Two
On October 15 , the County received the Architect ' s formal . Schematic
Design submittal, which included drawings , a project description and
outline specification, an integrated security plan , and a control and
communications systems plan. The construction cost estimate was
received on October 27 . A set of the submittal documents was delivered
to the Board. of Corrections on October 21 for their review and comment .
B. DESIGN CONCEPTS
The project design developed in response to a well defined security
concept . The integrated security plan calls for a secure perimeter
consisting of a landscaped buffer zone, a perimeter patrol road, a
double security fence with two independent electronic detection systems ,
and an open buffer zone separating the fences from the buildings and
recreation areas . This strong perimeter security system will allow
for buildings of more conventional construction, and controlled but
independent movement of inmates within the compound. Access to and
from this area will be through a tunnel going under the patrol road
and perimeter fences into a secure building located outside the fence
line. This outside building will contain the public lobby, administra-
tive and staff areas , operations , and services including kitchen and
laundry facilities .
The area within the fenced compound is divided into three areas :
housing, inmate services and recreation. There are four two-story
general population housing buildings , each. with 128 beds . In addition,
there is a 48 bed housing module for unclassified inmates . The intake
housing building is part of a complex of buildings situated around
a quadrangle that house central visiting, an outpatient client , library,
classrooms , religious offices , staff dining, commissary/clothing
exchange, and space for multi-purpose activities . This compound is
designed for future expansion without change to the perimeter security
system.
The project is a departure from standard county jail design as it per-
tains to the general population housing buildings . Given a well devel-
oped inmate classification system in combination with the maximum secu-
rity facilities at the Martinez Detention Facility, the County developed
a medium security housing concept using dry inmate rooms and centralized
toilets . This concept precludes long term lockdown within the indivi-
dual rooms ; however, the housing buildings themselves can be locked
down for an extended period if necessary. This concept is not consis-
tent with Title 15 of the California Administrative Code and will
require a variance from the Board of Corrections . This approval would
eliminate a toilet and sink in 480 rooms resulting in a significant
cost savings ( see next section for planned action ) .
C. DESIGN REVIEW
Throughout the three month Schematic Design period, the Architect parti-
cipated in several County and public design workshops . The County' s
project team participated in four workshops and a number of informal
review meetings . In addition, the Architect participated in eight
WCJC Advisory Group Design Committee meetings . The meeting topics
included program requirements , security concept , design aesthetics ,
functional layouts , future expansion and mitigation of potentially
adverse impacts .
The Advisory Group Design Committee ' s major concerns during this first
phase of design generally pertained to the project ' s impact on the
surrounding area, i.e . , Point Pinole Regional Shoreline Park, Parchester
Village , Richmond Country Club, Pinole Point Properties and the Chevron
Hilltop development . These concerns focused on site design. The Com-
mittee was primarily concerned with landscaping, perimeter security,
proximity of the buildings to the park entrance, building height and
design, parking and traffic, noise , and night lighting. Given the
Approval of Schematic Phase Design December 9 , 1986
West County Justice Center Page,. 'Three
project ' s close proximity to the Regional Shoreline Park entrance ,
the Design Committee is supporting the Park District ' s interest in
establishing a new park entry at a more central point . Access to this
new entry would be along the north edge of the site.
Representatives from the County and the Architect met with the Board
of Corrections ' staff on November 26 to present the project design
revisions and discuss their review comments . The project is generally
consistent with corrections and fire safety standards ; however, the
general population housing buildings are non-conforming and will require
a variance from the Board . of Corrections . On December 10 , the Board
of Corrections will be asked to grant this facility status as a pilot
project which would allow a departure of the building regulations for
the purposes of experimenting with a new design concept . This pilot
project will develop these housing buildings without toilets and sinks
in most inmate rooms and with non-confirming glazed openings . The
remaining 3oard comments will be addressed during the next phase of
design . Any Richmond Fire Marshal' s concerns , resulting from the
December 4 meeting, will also be responded to in this next design phase.
D. BUDGET
The project has a total budget of $48 , 760 , 085 . The target construction
contract award is $33 , 152 , 220 . The Schematic Design Phase cost estimate
totaled several million dollars above the project budget , thus resulting
in major architectural and . engineering changes during the design review
period. Since receipt of the submittal on October 15 , the County staff
and Architects have met four times in scope and budget reducing work-
shops . As a result of this value engineering effort , the project ' s
construction estimate is within budget . The value engineering effort
has kept the predesign program intact . The majority of the cost reduc-
tions was the result of design changes , including simplified designs ,
more 'efficient layout of space , and changes in building materials .
The revised cost estimate includes a loo design contingency, thus main-
taining a reserve fund for cost changes during the future design phases .
The target construction contract remains $33 , 152 , 000 . Adding a 5%
bidding contingency to this amount , the Fixed Limit of Initial Construc-
tion Contract Cost ( FLICCC ) is $34 , 810 , 000.
E. DESIGN DEVELOPMENT PHASE
Approval of the project ' s Schematic Design submittal, as revised, ini-
tiates the four month Design Development Phase of design. Design during
this phase will continue to develop and refine the schematic designs ,
reflecting the County' s design review comments and mitigation measures
described in the environmental impact report . These comments include
the questions and concerns of the State and Richmond Fire Marshals ,
County operating personnel, the Project Manager and the WCJC Advisory
Group.
During Design Development , the Architect will continue to conduct design
workshops for the County' s Project Team. The emphasis for this phase
will include the refinement of the various building systems , including
structural, mechanical, electrical ( including security) , exterior wall
and roof. The Architect and his consultants will evaluate environmental
control and energy conservation systems , methods of construction, faci-
lity staffing and operations , and building maintenance . Alternative
system solutions will be evaluated using life-cycle cost analysis
models . Working together, the County' s Project Team will continue
to refine the design, including layout modifications , selection of
finish materials and evaluation of construction methods .
Currently the project is on schedule for construction contract award
in May 1988 . The Design Development Phase submission will be due
April 10 , 1987 and will be presented next to the Board for their action
in May.
TO: BOARD OF SUPERVISORS
Contra
FROM: Phil Batchelor
County Administrator Costa
DATE: December 9, 1986 `"rity
SUBJECT: Report Submitted by West County Justice
Center Advisory Group
SPECIFIC REQUEST(S) OR,RECOMMENDATION(S) & BACKGROUND AND JUSTIFICATION
RECOMMENDED ACTION:
1 . ACCEPT Report from the West County Justice Center Advisory Group and
REFER Recommendations to the County Administrator for a report back to
the Board by February 15 , 1987 .
2 . DIRECT The County Administrator to cooperate with the City of Richmond
as they develop the Richmond Shoreline Strategy for the Point Pinole
area.
BACKGROUND:
The West County Justice Center Advisory Group was established by the Board
of Supervisors on April 1 , 1986 , to provide advice to the Board regarding
the design and construction of the new Justice Center. The Advisory Group
has been meeting regularly and discussing the community issues related to
the planning and operation of the Justice Center. The Advisory Group is
submitting three recommendations for the Board' s consideration at this
stage of the process :
1 . Develop a Minority and Women ,Business Enterprise Program Policy.
2 . Explore with the West County Justice Center Architect and
Project Management Contractor the hiring of local MBE/WBE
subconsultants during the project ' s design phase.
3. Accept the design resolution asking for the public endorsement
of a new northern entrance to the Point Pinole Regional Shoreline
and related design and site issues .
CONTINUED ON ATTACHMENT: YES SIGNATURE:
RECOMMENDATION OF COUNTY ADMINISTRATOR RECOMMENDA,7 OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURES)
ACTION OF,BOARD ON December 9, 1986 APPROVEDAS RECOMMENDED X OTHER
VOTE OF SUPERVISORS
X UNANIMOUS (ABSENT ) I HEREBY CERTIFY THAT THIS IS A TRUE
AYES: NOES: AND CORRECT COPY OF AN ACTION TAKEN
ABSENT: ABSTAIN: AND ENTERED ON THE MINUTES OF THE BOARD-
OF SUPERVISORS ON THE DATE SHOWN.
CC: CAO - Justice System Programs ATTESTED
Sheriff-Coroner nil eor, L;Ierk of Me bam of
Members , WCJC Advisory Group &VeMm adCoNyAdmuli*dw,
` M3e2/7•ea BY � � ✓ DEPUTY
j: ..