HomeMy WebLinkAboutMINUTES - 08162011 - C.06RECOMMENDATION(S):
ADOPT Resolution No. 2011/336 approving the seventh extension of the Subdivision
Agreement for minor subdivision MS 93-00021 for project being developed by Harold W.
Smith and Martha Lee Smith, Declaration of Trust dated May 4, 1979, as recommended by
the Public Works Director, Diablo area. (District III)
FISCAL IMPACT:
No fiscal impact.
BACKGROUND:
Approximately 0% of the work has been completed to date. The developer has been unable
to obtain a private drainage easement and requested additional time to complete
improvements. Granting an extension gives the developer an additional year to complete the
improvements while keeping the bond security current.
CONSEQUENCE OF NEGATIVE ACTION:
If the extension is not granted the subdivision agreement will not be renewed and the
County may need to consider initiating legal proceedings against the surety to enforce the
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On: 08/16/2011 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:John Gioia, District I
Supervisor
Gayle B. Uilkema, District II
Supervisor
Mary N. Piepho, District III
Supervisor
Karen Mitchoff, District IV
Supervisor
Federal D. Glover, District V
Supervisor
Contact: M. Sen, (925)
313-2187
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board
of Supervisors on the date shown.
ATTESTED: August 16, 2011
David Twa, County Administrator and Clerk of the Board of Supervisors
By: Carrie Del Bonta, Deputy
cc: T. Rhys, Construction, J. Capozzo,Eng. Services, C. Sumpter, DCD
C. 6
To:Board of Supervisors
From:Julia R. Bueren, Public Works Director/Chief Engineer
Date:August 16, 2011
Contra
Costa
County
Subject:Approving the seventh extension of the Subdivision Agreement for minor subdivision MS 93-00021
terms of the agreement.
CHILDREN'S IMPACT STATEMENT:
Not applicable.
ATTACHMENTS
Resolution No.
2011/336
ms 93-00021