HomeMy WebLinkAboutMINUTES - 12161986 - 1.95 TO: REDEVELOP14ENT AGENCY
FROM: PHIL BATCHELOR, EXECUTIVE DIRECTOR
DATE: December 16, 1986
SUBJECT: Approve Contract Change Order No. 2 for the Pleasant Hill BART Station Area
Street Improvements Project, Phase 113, Project No. 7891-6X5591-85
Specific Request(s) or Recommendation(s) & Background & Justification
RECOMMENDED ACTION:
AUTHORIZE the Chief Engineer to execute Contract Change Order No. 2 to Gallagher and Burk,
Inc. of Oakland (estimated increase of $61 ,273) to provide for miscellaneous changes in the
planned work for the Pleasant Hill BART Street Improvements Project, Phase IIB, Project No.
7891-6X5591-85.
FINANCIAL IMPACT:
Funds are available from Assessment District 1983-1.
REASONS FOR RECOMMENDATION/BACKGROUND:
The Agency is constructing major street improvements for, the Pleasant Hill BART Specific
Pian area. This contract change order provides for changes which are required because of
unanticipated conflicts with various utilities and/or adjacent projects. It also provides
for work not included in the contract. This change order provides for compensation to the
contractor for modifications which are required to complete the project.
Because this change order and the previously approved change order collectively exceed
$25,000, Agency approval is required.
CONSEQUENCES OF NEGATIVE ACTION:
Failure to approve the change order will significantly delay construction of the improvements
as well as impact public access to the Pleasant Hill BART Station.
Continued on attachment: _ yes Signature:
Recommendation of Executive Director Recommendation of Agency Cgdmittee
Approve Other:
Signature(s): /
Action of Agency on: DEC 16 1986 Approved as Recommended Z Other
Vote of Commissioners I HEREBY CERTIFY THAT THIS IS A TRUE
/ AND CORRECT COPY OF AN ACTION TAKEN
t/ Unanimous (Absent ) AND ENTERED ON THE MINUTES OF THE
Ayes: Noes: REDEVELOPMENT AGEACY ON DATE SHOWN.
Absent: Abstain:
Attested DEC 16 1986
Urig. Div.: Redevelopment Agency (Construction) Phil Batchelor
cc: Redevelopment Director Agency Secretary
Auditor-Controller
Chief Engineer
Lonstruction
Public 'Works AccounLiny
By , DEPUTY
L7iuu
UU :ria16. ti2