HomeMy WebLinkAboutMINUTES - 04122011 - C.47RECOMMENDATION(S):
Approve and authorize the Purchasing Agent, on behalf of the Health Services Department,
to execute a Purchase Order with Direct Systems Support, in the amount of $361,283.32, for
the IBM server hardware necessary to support the EPIC electronic medical record
deployment within the Health Services Department.
FISCAL IMPACT:
100% Enterprise Fund I.
BACKGROUND:
This software will run nearly all aspects of clinical information flow, payment systems,
prescription ordering, and many other workflows. With the new EPIC application the
department is consolidating 14 lines of business applications into one application. Therefore
the uptime of this application is critical as nearly 3,000 employees will be working with it.
To meet that requirement we have selected 1(one) IBM Blade Center with two blades and 7
(seven) physical servers. These servers have the necessary redundancy to meet the
requirements of the application. Without this purchase, the EMR project could sustain
costly downtime, data loss, and loss of employee productivity.
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On: 04/12/2011 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:John Gioia, District I
Supervisor
Mary N. Piepho, District III
Supervisor
Karen Mitchoff, District IV
Supervisor
Federal D. Glover, District V
Supervisor
RECUSE:Gayle B. Uilkema, District II
Supervisor
Contact: David Runt, 313-6228
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the
Board of Supervisors on the date shown.
ATTESTED: April 12, 2011
David J. Twa, County Administrator and Clerk of the Board of Supervisors
By: Carrie Del Bonta, Deputy
cc: Tasha Scott, Demetria Gary, Karon Head
C.47
To:Board of Supervisors
From:William Walker, M.D., Health Services Director
Date:April 12, 2011
Contra
Costa
County
Subject:Purchase Order for EPIC – Window Servers
CONSEQUENCE OF NEGATIVE ACTION:
Without the aforementioned IBM servers, the EPIC software will have no systems to be
installed on. Purchasing with anything less than the configuration increases our risk and
vulnerability to a system outage. An outage of EPIC or delay of this purchase would
drastically affect our ability to deliver this project on time, and to sustain the required
redundancy and workload.
CHILDREN'S IMPACT STATEMENT:
Not applicable.