HomeMy WebLinkAboutMINUTES - 04052011 - C.06RECOMMENDATION(S):
ADOPT Resolution No. 2011/125 accepting as complete the contracted work performed by W.C. Maloney, for
abatement and demolition of structures for the Upper Sand Creek Basin Expansion Project, as recommended by the
Public Works Director/Chief Engineer, Antioch area.
FISCAL IMPACT:
The fiscal impact of the Demolition portion of this project is estimated at $25,000, which includes the Contract with
WC Maloney for $18,850 and PWD Labor related.
BACKGROUND:
The Public Works Director/Chief Engineer reports that said work has been inspected and complies with the special
provisions and standard specifications and recommends its acceptance as complete as of February 10, 2011, for
Assessor’s Parcel No. 057-050-008 in Antioch.
CONSEQUENCE OF NEGATIVE ACTION:
The Contractor will not be paid and the acceptance notification will not be recorded.
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD
COMMITTEE
Action of Board On: 04/05/2011 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYES 5 NOES ____
ABSENT ____ ABSTAIN ____
RECUSE ____
Contact: Angela Bell, (925)
313-2337
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of
the Board of Supervisors on the date shown.
ATTESTED: April 5, 2011
David J. Twa, County Administrator and Clerk of the Board of Supervisors
By: June McHuen, Deputy
cc: Real Property Division; Fina Prak
C. 6
To:Board of Supervisors
From:Julia R. Bueren, Public Works Director/Chief Engineer
Date:April 5, 2011
Contra
Costa
County
Subject:Accepting and Giving Notice of Completion of Contract for Demolition of property, Antioch area. Project No. 7562-6D8518
CHILDREN'S IMPACT STATEMENT:
Not applicable.