HomeMy WebLinkAboutMINUTES - 04052011 - C.02RECOMMENDATION(S):
(1) APPROVE plans, specifications, and design for the above project.
(2) DETERMINE that the lowest apparent bidder, W. Bradley Electric, Inc. (“Bradley”), has failed to document an
adequate good faith effort to comply with the requirements of the County’s Outreach Program for this project, as
provided in the project specifications, and FURTHER DETERMINE that Bradley’s bid is non-responsive and
REJECT the bid on that basis.
(3) DETERMINE that the next lowest monetary bidder, Lister Construction, Inc. (“Lister”), has documented an
adequate good faith effort to comply with the requirements of the County’s Outreach Program and has exceeded the
MSM for this project, as provided in the project specifications, and FURTHER DETERMINE that Lister submitted
the lowest responsive and responsible bid for this project.
(4) AWARD the construction contract for the above project to Lister in the listed amount ($215,755.40) and the unit
prices submitted in the bid and DIRECT that Lister shall present two good and sufficient surety bonds as indicated
below, and that the Director of Public Works, or designee, shall prepare the contract.
(5) ORDER that, after the contractor has signed the contract and returned it, together with the bonds as noted below
and any required certificates of insurance
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD
COMMITTEE
Action of Board On: 04/05/2011 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYES 5 NOES ____
ABSENT ____ ABSTAIN ____
RECUSE ____
Contact: K. Emigh, (925) 313-2233
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of
the Board of Supervisors on the date shown.
ATTESTED: April 5, 2011
David J. Twa, County Administrator and Clerk of the Board of Supervisors
By: June McHuen, Deputy
cc: J. Dowling, Construction, P. Denison, Finance, M. Carlson, Transportation Engineering
C. 2
To:Board of Supervisors
From:Julia R. Bueren, Public Works Director/Chief Engineer
Date:April 5, 2011
Contra
Costa
County
Subject:AWARD and AUTHORIZE execution of a contract for the Willow Pass Road Safety Improvements Phase 1, Project #
0662-6U4031, Bay Point area
RECOMMENDATION(S): (CONT'D)
or other required documents, and the Director of Public Works has reviewed and found them to be sufficient, the
Director of Public Works, or designee, is authorized to sign the contract for this Board.
(6) ORDER that, in accordance with the project specifications and/or upon signature of the contract by the Director of
Public Works, or designee, any bid bonds posted by the bidders are to be exonerated and any checks or cash
submitted for security shall be returned.
(7) ORDER that, the Director of Public Works, or designee is authorized to sign any escrow agreements prepared for
this project to permit the direct payment of retentions into escrow or the substitution of securities for moneys
withheld by the County to ensure performance under the contract, pursuant to Public Contract Code Section 22300.
(8) DELEGATE, pursuant to Public Contract Code Section 4114, to the Director of Public Works, or designee, the
Board’s functions under Public Contract Code Sections 4107 and 4110.
(9) DELEGATE, pursuant to Labor Code Section 6705, to the Director of Public Works or to any registered civil or
structural engineer employed by the County the authority to accept detailed plans showing the design of shoring,
bracing, sloping, or other provisions to be made for worker protection during trench excavation covered by that
section.
(10) DECLARE that, should the award of the contract to Lister be invalidated for any reason, the Board would not in
any event have awarded the contract to any other bidder, but instead would have exercised its discretion to reject all
of the bids received. Nothing in this Board Order shall prevent the Board from re-awarding the contract to another
bidder in cases where the successful bidder establishes a mistake, refuses to sign the contract, or fails to furnish
required bonds or insurance (see Public Contract Code Sections 5100-5107).
FISCAL IMPACT:
The project construction contract in the amount of $215,755.40 will be funded by 100% Proposition 1B funds.
BACKGROUND:
The above project was previously approved by the Board of Supervisors, plans and specifications were filed with the
Board, bids were invited by the Director of Public Works, and Addendum No. 1 was issued. On March 1, 2010, the
Public Works Department received bids from the following contractors:
Lister Construction, Inc., TOTAL AMOUNT: $ 215,755.40
PAYMENT BOND AMOUNT: $ 215,755.40
PERFORMANCE BOND AMOUNT: $ 215,755.40
W. Bradley Electric, Inc.
Pleasanton Engineering Contractors, Inc.
Tennyson Electric, Inc.
St. Francis Electric, Inc.
Suarez & Munoz Construction, Inc.
A. J. Vasconi, Inc.
The Board of Supervisors previously determined that the project is exempt from the California Environmental Quality
Act as a Class 1(c) exemption, and a Notice of Exemption was filed with the County Clerk on March 23, 2010.
The Affirmative Action Officer has reported that the lowest apparent bidder, W. Bradley Electric, Inc. (“Bradley”),
failed to document an adequate good faith effort to comply with the requirements of the County’s Outreach Program,
as provided in the Project specifications, and the Affirmative Action Officer has recommended rejection of Bradley’s
bid.
Bradley has been notified in writing of the Affirmative Action Officer’s determination and has failed to appeal it to
the County Administrator, as provided in the project specifications.
The bidder listed first above, Lister, submitted the lowest responsive and responsible bid, which is $16,010.60 less
than the next lowest bid.
The Affirmative Action Officer has reported that Lister documented an adequate good faith effort to comply with the
requirements of the County’s Outreach Program and exceeded the MSM for this project, as provided in the project
specifications, and the Affirmative Action Officer has recommended that the contract be awarded to Lister.
The Director of Public Works recommends that the bid submitted by Lister is the lowest responsive and responsible
bid, and this Board concurs and so finds.
The general prevailing rates of wages, which shall be the minimum rates paid on this project, have been filed with
the Clerk of the Board, and copies will be made available to any party upon request.
CONSEQUENCE OF NEGATIVE ACTION:
Construction of the Willow Pass Road Safety Improvements Phase 1 project would be delayed, and the project might
not be built.
CHILDREN'S IMPACT STATEMENT:
Not applicable.