HomeMy WebLinkAboutMINUTES - 03222011 - C.33RECOMMENDATION(S):
1. APPROVE the plans, specifications, and design for Trade Bid Package 1C consisting of
general requirements work (construction fencing, portable toilets, dumpsters, etc.); and
DELEGATE to the Deputy General Services Director, or designee, or to any licensed
architect or engineer employed by the County, the authority to approve any design
modifications prepared for the above project.
2. AWARD a trade contract in the amount of $723,644 to Vila Construction Company
(“Vila”), the lowest responsive and responsible bidder for Trade Bid Package 1C consisting
of general requirements work for the subject project; and DIRECT the Deputy General
Services Director, or designee, to prepare the trade contract.
3. DETERMINE that Turner Construction Company (“Turner”), as the Construction
Manager At-Risk, has documented an adequate good faith effort to comply with the
specifications and the requirements of the County’s Outreach Program in connection with
the above trade contract and WAIVE any irregularities in such compliance.
4. FURTHER DETERMINE that Vila, as the lowest responsive and responsible bidder for
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On: 03/22/2011 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:John Gioia, District I
Supervisor
Gayle B. Uilkema, District II
Supervisor
Mary N. Piepho, District III
Supervisor
Karen Mitchoff, District IV
Supervisor
Federal D. Glover, District V
Supervisor
Contact: Rob Lim (925)
313-7242
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board
of Supervisors on the date shown.
ATTESTED: March 22, 2011
David J. Twa, County Administrator and Clerk of the Board of Supervisors
By: June McHuen, Deputy
cc:
C.33
To:Board of Supervisors
From:Steve Silveira, Deputy General Services Director
Date:March 22, 2011
Contra
Costa
County
Subject:Award of Construction Trade Contract for Trade Bid Package 1C for the West County Health Center Project,
13601 San Pablo Avenue, San Pablo (WH554B)
the above trade contract, and
RECOMMENDATION(S): (CONT'D)
Turner, as Project Manager, have entered into a Project Labor Agreement with the Contra
Costa Building and Construction Trades Council to comply with the requirements of the
County’s Project Labor Agreement policy.
5. DIRECT that Vila shall submit two good and sufficient surety bonds (performance
bond and payment bond) in the amount of $723,644 and that Vila and its subcontractors
shall sign a Project Labor Agreement for the project; and ORDER that, after Vila has
signed the trade contract and returned it, together with the bonds, the signed Project
Labor Agreement, evidence of insurance, and other required documents, and the Deputy
General Services Director has reviewed and found them to be sufficient, the Deputy
General Services Director, or designee, is authorized to sign the trade contract for this
Board.
6. AUTHORIZE the Deputy General Services Director, or designee, to exonerate any bid
bonds posted by the bidders after execution of the above trade contract.
7. AUTHORIZE the Deputy General Services Director, or designee, to sign any escrow
agreements prepared for this project to permit the direct payment of retentions into
escrow or the substitution of securities for monies withheld by the County to ensure
performance under the trade contract, pursuant to Public Contract Code Section 22300.
8. AUTHORIZE the Deputy General Services Director, or designee, to order changes or
additions to the trade contract work pursuant to Public Contract Code Section 20142.
9. DELEGATE, pursuant to Public Contract Code Section 4114, the Board's function
under Public Contract Code Sections 4107 and 4110, with regards to subletting and
subcontracting, to the Deputy General Services Director, or designee.
10. DELEGATE, pursuant to Labor Code Section 6705, to the Deputy General Services
Director or to any registered civil or structural engineer employed by the County the
authority to accept detailed plans showing the design of shoring, bracing, sloping or other
provisions to be made for worker protection during trench excavation covered by that
section.
11. DECLARE that, should the award of the trade contract to Vila be invalidated for any
reason, the Board would not in any event have awarded the contracts to any other bidder,
but instead would have exercised its discretion to reject all of the bids received. Nothing
herein shall prevent the Board from re-awarding a trade contract to another bidder in
cases where the successful bidder establishes a mistake, refuses to sign the trade contract,
or fails to furnish required bonds or insurance in accordance with Public Contract Code
Sections 5100-5107.
FISCAL IMPACT:
The estimated total project cost is $45 million. Funding in the amount of $12 million is
from a federal Health Resources and Services Administration (“HRSA”) grant, provided
under the American Recovery and Reinvestment Act of 2009. The remaining balance of
$33 million will be provided through bond financing and dedicated revenue within the
Hospital Enterprise Fund.
BACKGROUND:
The project involves constructing a new 2-story, 53,000-square-foot health center in San
Pablo. The new WCHC will serve the region by providing outpatient and ancillary
services in a modern and efficient facility. In addition, a new 315-stall, 3-level parking
structure will be built adjacent to the WCHC. The “Construction Manager At-Risk” (“CM
At-Risk”) project delivery method is being utilized on the project. Utilizing this method
involves overlapping multiple design and construction phases in order to fast-track the
project. With the CM At-Risk project delivery method, multiple trade bid packages (e.g.,
earthwork, piles, concrete, framing, mechanical, and electrical) will be developed and
issued for bidding. Two trade contracts (for earthwork and pile foundations) were
recently awarded by the Board. A third trade bid package (“1C” consisting of general
requirements work) was developed and issued for bidding.
Three bids were received for Trade Bid Package 1C. The bids were opened by the
General Services Department on March 8, 2011, and the bid results are as follows:
Bidder Base Bid
Vila Construction Company,
Richmond
$723,644
Turner Group Construction,
Oakland
$791,380
Roebbelen Construction, El Dorado
Hills
$795,995
For Trade Bid Package 1C, all three bids were above the CM At-Risk's estimate of
$720,000. Vila submitted the lowest responsive and responsible bid of $723,644, which
is $67,736 less than the next lowest bid submitted by Turner Group Construction. (Note:
“Turner Group Construction” is not related or connected with the County’s CM At-Risk
firm, “Turner Construction Company.”) Staff recommends that the trade contract for
Trade Bid Package 1C, consisting of general requirements work (construction fencing,
portable toilets, dumpsters, etc.), be awarded to Vila.
With the CM At-Risk project delivery method, the County contracts directly with the
various trade contractors, and Turner, as CM At-Risk, manages the trade contracts with a
Guaranteed Fixed Price and Guaranteed Completion Date. With award of the above trade
contract for general requirements work, the total amount of trade contracts to date is
$1,925,023. Recommendations for the award of other trade contracts will come before
$1,925,023. Recommendations for the award of other trade contracts will come before
the Board at future dates.
The County’s CM At-Risk, Turner, has submitted its documentation of good faith efforts
to comply with the specifications and requirements of the County's Outreach Program for
Trade Bid Package 1C (see memo attached to this Board Order). Staff recommends the
Board determine that Turner, as the CM At-Risk, has documented an adequate good faith
effort to comply with the requirements of the Outreach Program and that the Board waive
minor irregularities relating to the various Outreach steps and Terner's documentation.
When specific quantities are determined for the items included in Trade Bid Package 1C,
Vila or Turner will be required to perform and document additional Outreach to potential
subcontractors and suppliers for those items. This is similar to the process used by
general contractors under County's JOC (Job Order Contracting) Program.
Pursuant to the County’s Project Labor Agreement (PLA) policy, a PLA is required for
all trade contracts on this project. Vila has signed a PLA, which contains a local hire
provision consistent with the Disposition and Development Agreement between the City
of San Pablo Redevelopment Agency and the County. As a condition of trade contract
award, Vila’s subcontractors will also be required to sign the PLA.
The general prevailing rates of wages, which shall be the minimum rates paid on this
project, are on file with the Clerk of the Board, and copies are available to any party
upon request.
CONSEQUENCE OF NEGATIVE ACTION:
Failure to award the trade contract would delay the project and could potentially result in
the WCHC not being built and the loss of $12 million in federal stimulus money.
CHILDREN'S IMPACT STATEMENT:
Not applicable.
ATTACHMENTS
GFE Docs