HomeMy WebLinkAboutMINUTES - 03222011 - C.07RECOMMENDATION(S):
ADOPT Resolution No. 2011/107 approving the application to the California Department of
Water Resources to obtain Stormwater Flood Management grant funds totaling $2,000,000
under the Disaster Preparedness and Flood Prevention Bond Act of 2006 (Public Resources
Code Section 5096.800 et seq.) (Proposition 1E), Antioch area. (50% California Department
of Water Resources Proposition 1E Funds and 50% matching Flood Control District Funds)
FISCAL IMPACT:
The Contra Costa County Flood Control and Water Conservation District (FC District) will
be required to provide 50% matching funding for the project. The FC District is applying for
$2,000,000 of grant funding and has sufficient funds in Fund Number 256200 (Drainage
Area 130) to provide the 50% match.
BACKGROUND:
The purpose of the proposed grant application is to obtain Stormwater Flood Management
funding from the California Department of Water Resources for the construction of Upper
Sand Creek Basin.
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On: 03/22/2011 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:John Gioia, District I
Supervisor
Gayle B. Uilkema, District II
Supervisor
Mary N. Piepho, District III
Supervisor
Karen Mitchoff, District IV
Supervisor
Federal D. Glover, District V
Supervisor
Contact: Carl Roner (925)
313-2213
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board
of Supervisors on the date shown.
ATTESTED: March 22, 2011
David J. Twa, County Administrator and Clerk of the Board of Supervisors
By: JEANIE ROUNSAVILLE, Deputy
cc: R. M. Avalon, Deputy Chief Engineer, C. Roner, Flood Control, C. Windham, Flood Control
C. 7
To:Contra Costa County Flood Control District Board of Supervisors
From:Julia R. Bueren, Public Works Director/Chief Engineer
Date:March 22, 2011
Contra
Costa
County
Subject:Adopt Resolution Approving the Application for California Department of Water Resources Grant. Project
No. 7562-6D8518
CONSEQUENCE OF NEGATIVE ACTION:
Without the Board of Supervisors’ approval, the primary flood protection infrastructure
planned for the Marsh Creek Watershed will be not be fully funded and the project may
not be able to be built in its entirety.