HomeMy WebLinkAboutRESOLUTIONS - 01161990 - 90/30WHEN RECORDED, RETURN RECORDED AT REQUEST OF OWNER
TO CLERK, BOARD OF at o'clock M.
SUPERVISORS Contra Costa County Records
Stephen Weir, County Recorder
Fee Official
BOARD OF SUPERVISORS, CONTRA COSTA COUNTY, CALIFORNIA
In the Matter of Accepting and Giving) RESOLUTION OF ACCEPTANCE
Notice of Completion of Contract for ) and NOTACE OF COMPLETION
Drainage Area 56, Lindsey C.C. S 3086, 3093)
Detention Basin,
Proiect No. 7566-6D8462-86 RESOLUTION NO. 90/30
The Board of Supervisors of Contra Costa County, as the governing
body of the Contra Costa County Flood Control and Water Conservation
District, RESOLVES that:
The Flood Control District on December 15, 1987 contracted with
Oliver DeSilva, Inc. , P.O. Box 4437, Hayward, CA 94540, for
construction of the Lindsey Detention Basin Project, No. 7566-
6D8462-86 in the Oakley area, with Seaboard Surety Company as
surety, for work to be performed on the grounds of the County; and
The Chief Engineer reports that said work has been inspected and
complies with the approved plans, special provisions and standard I
specifications and recommends its acceptance as complete as of
December 15, 1989.
Therefore, said work is ACCEPTED as completed on said date, and the
Clerk shall file with the County Recorder a copy of this ,Resolution
and Notice as a Notice of Completion for said contract.
PASSED BY THE BOARD on January 16, 1990 by the following vote:
AYES:Supervisors Powers , Schroder, McPeak, Torlakson & Fanden
NOES:None
ABSENT: None
CERTIFICATION AND VERIFICATION
I certify that the foregoing is a true and correct copy of a
resolution and acceptance duly adopted and entered on the minutes
of this Board's meeting on the above date. I declare under penalty
of perjury that the foregoing is true and correct.
Dated: January 16 , 1990 PHIL BATCHELOR, Clerk of the
Board
at Martinez, California of Supervisors and County
Administrator
By Je
Deputy Clerk
Orig.Dept. : Public Works (Construction)
Cc: Record and return
Auditor
Public Works-Accounting
R. Bruno
Contractor
DG/tt
BODA5616.T1
RESOLUTION NO. 90 30