Loading...
HomeMy WebLinkAboutMINUTES - 03152011 - C.03RECOMMENDATION(S): APPROVE and AUTHORIZE the Chair, Board of Supervisors, to execute Memorandum of Understanding between Contra Costa County, the Redevelopment Agency of the County of Contra Costa and the City of Pittsburg for the Bailey Road Improvement Project, Bay Point area. (District V) FISCAL IMPACT: There is no fiscal impact to the General Fund. The Bailey Road Improvement Disposal Surcharge collected from Keller Canyon Landfill pursuant to Condition of Approval 29.6 of Keller Canyon Landfill Land Use Permit 2020-89 of $1,193,000 will be used towards this project. BACKGROUND: The Bailey Road Improvement Project (Project) is a joint project between Contra Costa County, the Redevelopment Agency, and the City of Pittsburg. The City of Pittsburg has been the lead agency for the project. The City of Pittsburg and the Contra Costa County APPROVE OTHER RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE Action of Board On: 03/15/2011 APPROVED AS RECOMMENDED OTHER Clerks Notes: VOTE OF SUPERVISORS AYE:John Gioia, District I Supervisor Gayle B. Uilkema, District II Supervisor Mary N. Piepho, District III Supervisor Karen Mitchoff, District IV Supervisor ABSENT:Federal D. Glover, District V Supervisor Contact: Billilee Balangan, (925) 313-2188 I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board of Supervisors on the date shown. ATTESTED: March 15, 2011 David J. Twa, County Administrator and Clerk of the Board of Supervisors By: EMY L. SHARP, Deputy cc: Maureen Toms, RDA C. 3 To:Board of Supervisors From:Julia R. Bueren, Public Works Director/Chief Engineer Date:March 15, 2011 Contra Costa County Subject:APPROVE the Memorandum of Understanding between Contra Costa County, the Redevelopment Agency of the County of Contra Costa, and the City of Pittsburg Redevelopment BACKGROUND: (CONT'D) Agency have applied for and been granted funds through the Safe Routes to Transit Program in the amount of $650,000, Transportation Development Act funds in the amount of $160,000, and Transportation for Livable Communities funds in the amount of $989,000, for use towards the Project. Approximately $1.193 million in Bailey Road Maintenance Disposal Surcharge funds will also be used for the Project. The City of Pittsburg and the Redevelopment Agency will contribute towards the remaining amount of the project cost. The project limits is within the Pittsburg/Bay Point BART Station Area Specific Plan boundaries in east Contra Costa County. The project involves capital improvements along Bailey Road and adjacent roads, and pedestrian/bike trails between SR4 on/off ramps and West Leland Road. The project includes pedestrian crossing improvements at the Bailey Road/BART entrance intersection and the Bailey Road/Maylard Road/Shopping Center intersections. Other improvements include widening the sidewalk and landscaping along Bailey Road and Maylard Avenue, security lighting and landscaping improvements adjacent to the Delta De Anza Trail, reconstruction and landscaping of the Bailey Road median islands, and road widening to accommodate Class II bicycle facilities along both sides of Bailey Road between SR4 and West Leland Road. The County adopted the Mitigated Negative Declaration for the project on January 11, 2011. CONSEQUENCE OF NEGATIVE ACTION: The receipt of grant funds would be jeopardized and improvements to Bailey Road would not occur. CHILDREN'S IMPACT STATEMENT: Not Applicable. ATTACHMENTS MOU