HomeMy WebLinkAboutMINUTES - 03012011 - C.03RECOMMENDATION(S):
ADOPT Resolution No. 2011/67accepting as complete the contracted work performed by Graham Contractors, Inc.,
for the 2010 Discovery Bay Terminal Blend Cape Seal project, Project No. 0672-6U2152-10, as recommended by the
Public Works Director.
FISCAL IMPACT:
This project was funded by 85% Local Road funds and 15% California Integrated Waste Management Board funds.
BACKGROUND:
The Public Works Director reports that said work has been inspected and complies with the approved plans, special
provisions and standard specifications and recommends its acceptance as complete as of February 4, 2011.
CONSEQUENCE OF NEGATIVE ACTION:
The contractor will not be paid and acceptance notification will not be recorded.
CHILDREN'S IMPACT STATEMENT:
Not applicable.
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD
COMMITTEE
Action of Board On: 03/01/2011 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYES 5 NOES ____
ABSENT ____ ABSTAIN ____
RECUSE ____
Contact: Kevin Emigh, (925)
313-2233
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of
the Board of Supervisors on the date shown.
ATTESTED: March 1, 2011
David J. Twa, County Administrator and Clerk of the Board of Supervisors
By: EMY L. SHARP, Deputy
cc: J. Dowling, Construction, H. Finch, Maintenance, M. Carlson, TE, C. Lau, TE, P. Denison, Finance
C. 3
To:Board of Supervisors
From:Julia R. Bueren, Public Works Director/Chief Engineer
Date:March 1, 2011
Contra
Costa
County
Subject:ACCEPTANCE and Giving Notice of Completion of Contract for the 2010 Discovery Bay Terminal Blend Cape Seal project,
Project No. 0672-6U2152-10