HomeMy WebLinkAboutMINUTES - 02152011 - C.30 (2)RECOMMENDATION(S):
APPROVE and AUTHORIZE the Public Works Director, or designee, to execute a contract
amendment with LSA Associates, Inc. effective February 1, 2011, to increase the payment
limit by $75,000 from $400,000 to a new payment limit of $475,000, with no change to the
contract term, to continue to provide environmental services, Countywide.
FISCAL IMPACT:
There is no impact to the County General Fund. This project is funded by 48% Flood
Control & Water Conservation District Funds, 48% Local Road Funds, 4% Airport Project
Funds. Project No.: Various
BACKGROUND:
The amendment is needed to increase the contract payment limit by $75,000 form $400,000
to a new contract limit of $475,000 to continue to provide on-call environmental services for
Contra Costa County Public Works Department, Countywide.
CONSEQUENCE OF NEGATIVE ACTION:
Without Board approval, necessary on-call environmental assessments may not be
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On: 02/15/2011 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:John Gioia, District I
Supervisor
Gayle B. Uilkema, District II
Supervisor
Karen Mitchoff, District IV
Supervisor
Federal D. Glover, District V
Supervisor
ABSENT:Mary N. Piepho, District III
Supervisor
Contact: T. Torres, 313-2176
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the
Board of Supervisors on the date shown.
ATTESTED: February 15, 2011
David J. Twa, County Administrator and Clerk of the Board of Supervisors
By: June McHuen, Deputy
cc: V. Mejia, County Administrator, P. Denison, Accounting – , Auditor - Controller, L. Chavez, Environmental, T. Torres, Environmental
C.30
To:Board of Supervisors
From:Julia R. Bueren, Public Works Director/Chief Engineer
Date:February 15, 2011
Contra
Costa
County
Subject:APPROVE and AUTHORIZE the Public Works Director, or designee, to execute a contract amendment with
LSA Associates Inc., Countywide
completed in a timely manner. Therefore, necessary environmental clearances may not be
obtained, which may jeopardize funding and delay the design and construction of various
projects.
CHILDREN'S IMPACT STATEMENT:
Not Applicable.
ATTACHMENTS
LSA (On Call) Contract