HomeMy WebLinkAboutMINUTES - 12142010 - C.09RECOMMENDATION(S):
ACCEPT the License Agreements from the Contra Costa Water District (CCWD) and East
Bay Regional Park District (EBRPD) and AUTHORIZE the Public Works Director, or
designee, to execute the Agreements on behalf of the County. (District III)
FISCAL IMPACT:
There is no impact to the County General Fund. This project is funded 56% American
Recovery and Investment Act and 44% Proposition 1B.
BACKGROUND:
In preparation for construction of the Vasco Road Safety Improvement project, the Public
Works Department (Department) has been working with CCWD and EBRPD to obtain
permission to use a portion of Assessor’s Parcel No. 005-170-006, which they share a 50%
ownership, for the reconstruction of their existing driveway and the installation and
maintenance of the Environmental Improvements along Vasco Road. This work is required
for the project in accordance with the approved plans and specifications. Construction is
scheduled to begin January 2011.
APPROVE OTHER
RECOMMENDATION OF CNTY
ADMINISTRATOR
RECOMMENDATION OF BOARD
COMMITTEE
Action of Board On: 12/14/2010 APPROVED AS RECOMMENDED OTHER
Clerks Notes:DISTRICT IV - SEAT VACANT
VOTE OF SUPERVISORS
AYE:John Gioia, District I
Supervisor
Gayle B. Uilkema, District
II Supervisor
Mary N. Piepho, District III
Supervisor
Federal D. Glover, District
V Supervisor
Contact: Lucy Owens
925-313-2229
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes
of the Board of Supervisors on the date shown.
ATTESTED: December 14, 2010
David J. Twa, County Administrator and Clerk of the Board of Supervisors
By: EMY L. SHARP, Deputy
cc: J. Carlson, Real Property, Auditor-Controller, Recorder
C. 9
To:Board of Supervisors
From:Julia R. Bueren, Public Works Director/Chief Engineer
Date:December 14, 2010
Contra
Costa
County
Subject:Vasco Road Safety Improvement Project, Byron area. Project No. 0662-6R4254
As a condition of the License Agreements, the Districts
BACKGROUND: (CONT'D)
have required the County to indemnify them.
CONSEQUENCE OF NEGATIVE ACTION:
The project will not have sufficient land rights to allow construction in accordance with
the approved plans and specifications.
CHILDREN'S IMPACT STATEMENT:
Not Applicable.
ATTACHMENTS
License Ageement CCWD
License Agreement EBRPD