HomeMy WebLinkAboutMINUTES - 12072010 - C.33RECOMMENDATION(S):
1. APPROVE and ADOPT plans, specifications, and design (piles, foundation, and site
work) for the West County Health Center (“WCHC”) Project, San Pablo.
2. AUTHORIZE the General Services Director, or designee, to solicit bids from various
trade contractors to be received during the period from approximately December 2010 to
December 2011, and to issue bid Addenda as needed for clarification of the contract bid
documents, provided the involved changes do not significantly increase the construction
cost estimate.
3. DIRECT the Clerk of the Board to publish Notices to Contractors in accordance with
Public Contract Code Section 22037, inviting bids for the various trades required for this
project.
4. DIRECT the General Services Director, or designee, to mail notices to the construction
trade journals specified in Public Contract Code Section 22036 at least thirty calendar days
before the bid-opening date for each trade.
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On: 12/07/2010 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:Gayle B. Uilkema, District II
Supervisor
Mary N. Piepho, District III
Supervisor
Federal D. Glover, District V
Supervisor
ABSENT:John Gioia, District I
Supervisor
Contact: Mike Lango (925)
313-7100
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the
Board of Supervisors on the date shown.
ATTESTED: December 7, 2010
David J. Twa, County Administrator and Clerk of the Board of Supervisors
By: June McHuen, Deputy
cc: GSD Administration, GSD Accounting, GSD CPM Manager, GSD CPM Clerical, Auditor's Office, County Counsel's Office, County Administrator's
Office, County Administrator's Office
C.33
To:Board of Supervisors
From:Michael J. Lango, General Services Director
Date:December 7, 2010
Contra
Costa
County
Subject:APPROVE BID DOCUMENTS AND AUTHORIZE THE SOLICITATION OF BIDS FOR THE WEST
COUNTY HEALTH CENTER PROJECT, SAN PABLO
FISCAL IMPACT:
The estimated total project cost is $45 million. Funding in the amount of $12 million is from
a federal Health Resources and Services Administration (“HRSA”) grant, provided under
the American Recovery and Reinvestment Act of 2009. The remaining balance of $33
million will be provided through bond financing and dedicated revenue within the Hospital
Enterprise Fund.
BACKGROUND:
The project involves constructing a new 2-story, 53,000-square foot health center in San
Pablo. The new WCHC will serve the region by providing outpatient and ancillary services
in a modern and efficient facility. In addition, a new 320-stall, 3-level parking structure will
be built adjacent to the WCHC.
On October 12, 2010, the Board approved a Negative Declaration for the project pursuant
to the California Environmental Quality Act (CEQA). A Notice of Determination was
subsequently filed with the County Clerk by the Director of Community Development, or
designee.
The “Construction Manager At-Risk” (“CM At-Risk”) project delivery method is being
utilized on the project. Utilizing this method involves overlapping multiple design and
construction phases in order to fast-track the project. Typically, the CM At-Risk method
provides improved cost control, better allocation of risk, and enhanced project collaboration.
With the CM At-Risk project delivery method, multiple trade bid packages (e.g., site work,
concrete, framing, mechanical, and electrical) will be developed and issued for bidding.
The design documents are currently being prepared by Hawley Peterson Snyder Architects,
the architect hired for the project. To date, the plans and specifications for the piles,
foundation, and site work (grading, etc.) have been completed and have been submitted to
the Clerk of the Board. As the design documents for additional trades are completed, they
will similarly be filed with the Clerk of the Board for approval and adoption by the Board.
Staff recommends that the Board approve and adopt the plans, specifications, and design
for the piles, foundation, and site work. Staff also recommends that the Board authorize the
General Services Director, or designee, to solicit bids from trade contractors for the various
trades involved in this project. The trade bids will be solicited from December 2010 through
December 2011, starting with trade bids for piles, foundation, and site work. As bids are
received for the various trades, the bids will be presented to the Board for award of trade
contracts (i.e., construction contracts for each trade).
The total construction cost estimate is approximately $29 million. The prevailing rates of per
diem wages, which are stipulated by federal law and the federal grant terms, are on file with
the Clerk of the Board of Supervisors and will be the minimum rates required on this
project.
CONSEQUENCE OF NEGATIVE ACTION:
If the authorization to bid is not approved, the project cannot progress into the Construction
Phase and the project may not be built.
CHILDREN'S IMPACT STATEMENT:
Not applicable.