HomeMy WebLinkAboutMINUTES - 09282010 - C.02RECOMMENDATION(S):
APPROVE the Right of Way Contract-Temporary Easement and ACCEPT the Grant of
Easement from East Bay Municipal Utility District (EBMUD) for property rights needed in
connection with the Montalvin Manor Pedestrian and Transportation Access Improvement
Project. (4660-6X4109)
AUTHORIZE the Public Works Director, or designee, to execute said Right of Way
Contract-Temporary Easement on behalf of the County.
DIRECT the Real Property Division to have said Grant of Easement recorded in the Office
of the County Recorder.
FISCAL IMPACT:
There is no impact to the County General Fund. The activity is funded by Redevelopment
Agency (RDA) Funds 74.9%, State Transportation Improvement Program-Transportation
Enhancement (STIP-TE) Funds 18.9%, Transportation Development Act (TDA) Grants
3.6%, Community Development Block Grant Program (CDBG) 2.6%.
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On: 09/28/2010 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:John Gioia, District I
Supervisor
Gayle B. Uilkema, District II
Supervisor
Mary N. Piepho, District III
Supervisor
Federal D. Glover, District V
Supervisor
ABSENT:Susan A. Bonilla, District IV
Supervisor
Contact: Cheryl Sousa
(313-2252)
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the
Board of Supervisors on the date shown.
ATTESTED: September 28, 2010
David J. Twa, County Administrator and Clerk of the Board of Supervisors
By: EMY L. SHARP, Deputy
cc:
C. 2
To:Board of Supervisors
From:Julia R. Bueren, Public Works Director/Chief Engineer
Date:September 28, 2010
Contra
Costa
County
Subject:Montalvin Manor Pedestrian and Transportation Access Improvements
BACKGROUND:
The purpose of the project is to improve mobility in the Montalvin Manor area by closing
sidewalk gaps on San Pablo Avenue between Shamrock Drive to Kay Road and on Kay
Road from San Pablo Avenue to Rachel Road, providing Class II bike lanes and bus
shelters along the west side of San Pablo Avenue. This project will improve pedestrian
circulation along the heavily traveled San Pablo Avenue by providing a dedicated
sidewalk for pedestrians. This project will also provide additional pavement width needed
for a Class II bike facility along the west side of San Pablo Avenue. In addition, new
drainage facilities will be constructed to collect and convey storm water within the
project limits, which include storm drains, inlets, concrete valley gutters and outfall
structures. As a condition of the easement EBMUD has required the County to indemnify
EBMUD.
CONSEQUENCE OF NEGATIVE ACTION:
The County will not have sufficient land rights to complete the drainage improvements
with approved plans and specifications.
CHILDREN'S IMPACT STATEMENT:
Not Applicable.
ATTACHMENTS
Grant of Easement
Right of Way Contract