HomeMy WebLinkAboutMINUTES - 09142010 - C.08RECOMMENDATION(S):
ADOPT Resolution No. 2010/437 accepting completion of warranty period, for DG
06-00061 (cross-reference SD 8448), for project being developed by Lyon Vista Del Mar
553, LLC, as recommended by the Public Works Director, Bay Point area. (District V)
FISCAL IMPACT:
No Fiscal Impact.
BACKGROUND:
The drainage improvements have met the guarantee performance standards for the warranty
period following completion and acceptance of the improvements.
CONSEQUENCE OF NEGATIVE ACTION:
The developer will not receive a refund of their cash deposit, the Drainage Improvement
Agreement and performance surety bond will not be exonerated, and the billing account will
not be liquidated and closed.
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On: 09/14/2010 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:John Gioia, District I
Supervisor
Mary N. Piepho, District III
Supervisor
Susan A. Bonilla, District IV
Supervisor
Federal D. Glover, District V
Supervisor
ABSENT:Gayle B. Uilkema, District II
Supervisor
Contact: J. LaRocque, 313-2315
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the
Board of Supervisors on the date shown.
ATTESTED: September 14, 2010
David J. Twa, County Administrator and Clerk of the Board of Supervisors
By: EMY L. SHARP, Deputy
cc: T. Rhys, Mike Mann, John Capozzo, C. Sumpter
C. 8
To:Board of Supervisors
From:Julia R. Bueren, Public Works Director/Chief Engineer
Date:September 14, 2010
Contra
Costa
County
Subject:Accepting completion of warranty period and release of cash deposit under the Drainage Improvement
Agreement for DG 06-00061
ATTACHMENTS
Resolution No.
2010/437