HomeMy WebLinkAboutMINUTES - 08102010 - C.66RECOMMENDATION(S):
APPROVE and AUTHORIZE the Public Works Director, or designee, to execute a contract
amendment with Jeff Alvarez, dba “The Wildlife Project” (Contractor), effective August 1,
2010, to increase the payment limit by $75,000 from $100,000 to a new payment limit of
$175,000, to continue to provide biological monitoring for the Bethel Island Road Bridge
Replacement Project.
FISCAL IMPACT:
There is no impact to the County General Fund. This project is funded by Road Funds
(100%), Project No. 0662-6R4043.
BACKGROUND:
This contract amendment is needed to increase the payment limit increase by $75,000 from
$100,000 to a new payment limit of $175,000 to continue biological monitoring of the
Bethel Island Road Bridge project. All other terms and conditions in the contract entered
into on June 8, 2009, between Contra Costa County Public Works Department and the
Contractor shall remain in full force and effect.
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On: 08/10/2010 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:John Gioia, District I Supervisor
Gayle B. Uilkema, District II
Supervisor
Mary N. Piepho, District III
Supervisor
Susan A. Bonilla, District IV
Supervisor
Federal D. Glover, District V
Supervisor
Contact: Trina Torres, (925)
313-2176
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board
of Supervisors on the date shown.
ATTESTED: August 10, 2010
David J. Twa, County Administrator and Clerk of the Board of Supervisors
By: KATHERINE SINCLAIR, Deputy
cc: T. Torres, P. Denison, L. Chavez, C. Gemberling, N. Chuhak
C.66
To:Board of Supervisors
From:Julia R. Bueren, Public Works Director/Chief Engineer
Date:August 10, 2010
Contra
Costa
County
Subject:Contract Amendment with Jeff Alvarez, dba "The Wildlife Project" for Bethel Island Road Bridge
Replacement Project (biological monitoring)
CONSEQUENCE OF NEGATIVE ACTION:
Without Board approval, necessary biological monitoring may not continue, which will
be non-compliant with State and Federal regulations, which may delay the construction
of the project and may jeopardize funding.
CHILDREN'S IMPACT STATEMENT: