HomeMy WebLinkAboutMINUTES - 06222010 - C.01RECOMMENDATION(S):
APPROVE the Arlington Avenue Curb Ramp Project and AUTHORIZE the Public Works
Director, or designee, to advertise the project [DCD-CP#09-95] Project No.: 0662-6R4207,
and
FIND the project is a California Environmental Quality Act (CEQA), Class 1c Categorical
Exemption, pursuant to Article 19, Section 15301(c) of the CEQA Guidelines, and
DIRECT the Director of Conservation and Development to file a Notice of Exemption with
the County Clerk, and
AUTHORIZE the Public Works Director to arrange for payment of $25 fee to Conservation
and Development for processing, and a $50 fee to the County Clerk for filing the Notice of
Exemption.
FISCAL IMPACT:
There is no impact to the County General Fund. This project is funded by Measure C
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On: 06/22/2010 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:John Gioia, District I
Supervisor
Gayle B. Uilkema, District II
Supervisor
Mary N. Piepho, District III
Supervisor
Federal D. Glover, District V
Supervisor
ABSENT:Susan A. Bonilla, District IV
Supervisor
Contact: Ave Brown, 313-2311
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the
Board of Supervisors on the date shown.
ATTESTED: June 22, 2010
David J. Twa, County Administrator and Clerk of the Board of Supervisors
By: EMY L. SHARP, Deputy
cc: D. Favero, Special Districts,, P. Denison, Finance, P. Warden, Design, L. Chavez, Environmental
C. 1
To:Board of Supervisors
From:Julia R. Bueren, Public Works Director/Chief Engineer
Date:June 22, 2010
Contra
Costa
County
Subject:Approve the Arlington Avenue Curb Ramp Project; Authorize the Public Works Director or designee, to
advertise the project.
(100%).
BACKGROUND:
The project is necessary to replace 13 existing curb ramps with Americans with
Disabilities Act (ADA) compliant curb ramps. Installation of the ADA compliant curb
ramps will make Arlington Avenue more accessible and improve access to Kensington
Elementary School, Kensington Library, Arlington Community Church, and several
government buildings.
CONSEQUENCE OF NEGATIVE ACTION:
Delay in approving the project will result in a delay of curb ramp replacement, and may
jeopardize funding.
CHILDREN'S IMPACT STATEMENT:
ATTACHMENTS
Initial Study and Maps
Noe Arlington Avenue Curb Ramp Project