HomeMy WebLinkAboutMINUTES - 06082010 - C.02RECOMMENDATION(S):
APPROVE Marsh Creek Road Rubberized Asphalt Concrete Overlay Project; and
AUTHORIZE the Public Works Director, or designee, to advertise the project. [DCD-CP
10-26] Project No. 4660-6X4462.
FIND the project is a California Environmental Quality Act (CEQA), Class 1 (c)
Categorical Exemption, pursuant to Section 15301 (c) of the CEQA Guidelines, and
DIRECT the Director of Conservation and Development to file the Notice of Exemption
with the County Clerk, and
AUTHORIZE the Public Works Director to arrange for payment of a $25 fee to the
Department of Conservation and Development for processing, and a $50 fee to the County
Clerk for filing the Notice of Exemption.
FISCAL IMPACT:
There is no impact to the County General Fund. The project is funded with 85.3% East
Contra Costa Regional Fee and Financing Authority (ECCRFFA) funds and 14.7% Federal
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On: 06/08/2010 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:John Gioia, District I
Supervisor
Gayle B. Uilkema, District II
Supervisor
Mary N. Piepho, District III
Supervisor
Susan A. Bonilla, District IV
Supervisor
Federal D. Glover, District V
Supervisor
Contact: Nancy Wein,
313-2275
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board
of Supervisors on the date shown.
ATTESTED: June 8, 2010
David J. Twa, County Administrator and Clerk of the Board of Supervisors
By: EMY L. SHARP, Deputy
cc: Nancy Wein, Chris Lau, Emma Kuevor
C. 2
To:Board of Supervisors
From:Julia R. Bueren, Public Works Director/Chief Engineer
Date:June 8, 2010
Contra
Costa
County
Subject:Marsh Creek Road Rubberized Asphalt Concrete (RAC) Project
funding from the American Recovery and Reinvestment Act.
BACKGROUND:
The project work consists of placing a 0.15 foot overlay of Rubberized Asphalt Concrete
on existing pavement, adding backing material to the existing shoulder backing to meet
the new grade within the roadway limits, and restriping using the same current lane
configuration of two 12 foot wide lanes and 10 foot wide shoulders with thermoplastic
pavement delineations as well as a soft median barrier (rumble strips). A staging area at
the northeast corner of the intersection of the Bypass Road and Marsh Creek Road that
was used during the original construction will be reused during the proposed overlay
project. Two-way traffic will be maintained throughout construction and emergency
vehicle access will be allowed at all times.
The State Route 4 Bypass Authority will be assisting the County Public Works staff to
administer the construction project.
CONSEQUENCE OF NEGATIVE ACTION:
Delay in approving the project will result in a delay of design and construction and may
jeopardize funding.