HomeMy WebLinkAboutMINUTES - 04272010 - C.02RECOMMENDATION(S):
ADOPT Resolution No. 2010/218 accepting as complete the contracted work performed by
Malachi Construction, for the Montalvin Manor Sidewalk project, as recommended by the
Public Works Director.
FISCAL IMPACT:
This project was funded by 75% Redevelopment funds and 25% Property Owner funds.
BACKGROUND:
The Public Works Director reports that said work has been inspected and complies with the
approved plans, special provisions and standard specifications and recommends its
acceptance as complete as of April 5, 2010.
CONSEQUENCE OF NEGATIVE ACTION:
The contractor will not be paid and acceptance notification will not be recorded.
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On: 04/27/2010 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:John Gioia, District I
Supervisor
Gayle B. Uilkema, District II
Supervisor
Mary N. Piepho, District III
Supervisor
Susan A. Bonilla, District IV
Supervisor
Federal D. Glover, District V
Supervisor
Contact: Kevin Emigh, 313-2233
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board
of Supervisors on the date shown.
ATTESTED: April 27, 2010
David J. Twa, County Administrator and Clerk of the Board of Supervisors
By: EMY L. SHARP, Deputy
cc: A. Bell, Construction, J. Dowling, Construction, P. Denison, Finance, C. Lau, Transportation Engineering, A. Knapp, Maintenance, J. Suemnick,
Maintenance
C. 2
To:Board of Supervisors
From:Julia R. Bueren, Public Works Director/Chief Engineer
Date:April 27, 2010
Contra
Costa
County
Subject:ACCEPTANCE and Giving Notice of Completion of Contract for the Montalvin Manor Sidewalk
Improvement project, Project No. 4500-6X5470-09
ATTACHMENTS
Resolution No. 2010/218