Loading...
HomeMy WebLinkAboutMINUTES - 02022010 - C.1RECOMMENDATION(S): ADOPT Resolution No. 2010/69 accepting as complete the contracted work performed by Steiny & Company, Inc., for the Delta De Anza Trail Gap Closure project, Project No.: 0662-6R4001-08, as recommended by the Public Works Director. FISCAL IMPACT: This project was funded by 74.9% State Transportation Improvement Program funds and 25.1% Local Road funds. BACKGROUND: The Public Works Director reports that said work has been inspected and complies with the approved plans, special provisions and standard specifications and recommends its acceptance as complete as of January 6, 2010. CONSEQUENCE OF NEGATIVE ACTION: The contractor will not be paid and acceptance notification will not be recorded. APPROVE OTHER RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE Action of Board On: 02/02/2010 APPROVED AS RECOMMENDED OTHER Clerks Notes: VOTE OF SUPERVISORS AYES 5 NOES ____ ABSENT ____ ABSTAIN ____ RECUSE ____ Contact: K. Emigh, 313-2233 I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board of Supervisors on the date shown. ATTESTED: February 2, 2010 David J. Twa, County Administrator and Clerk of the Board of Supervisors By: EMY L. SHARP, Deputy cc: J. Dowling, Construction, A. Bell, Construction, P. Denison, Finance, C. Lau, Transportation Engineering, L. Costa, Design, M. Carlson, Transportation Engineering C. 1 To:Board of Supervisors From:Julia R. Bueren, Public Works Director/Chief Engineer Date:February 2, 2010 Contra Costa County Subject:ACCEPTANCE and Giving Notice of Completion of Contract for the Delta De Anza Trail Gap Closure project, Project No. 0662-6R4001-08