HomeMy WebLinkAboutMINUTES - 02022010 - C.1RECOMMENDATION(S):
ADOPT Resolution No. 2010/69 accepting as complete the contracted work performed by Steiny & Company, Inc.,
for the Delta De Anza Trail Gap Closure project, Project No.: 0662-6R4001-08, as recommended by the Public
Works Director.
FISCAL IMPACT:
This project was funded by 74.9% State Transportation Improvement Program funds and 25.1% Local Road funds.
BACKGROUND:
The Public Works Director reports that said work has been inspected and complies with the approved plans, special
provisions and standard specifications and recommends its acceptance as complete as of January 6, 2010.
CONSEQUENCE OF NEGATIVE ACTION:
The contractor will not be paid and acceptance notification will not be recorded.
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD
COMMITTEE
Action of Board On: 02/02/2010 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYES 5 NOES ____
ABSENT ____ ABSTAIN ____
RECUSE ____
Contact: K. Emigh, 313-2233
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of
the Board of Supervisors on the date shown.
ATTESTED: February 2, 2010
David J. Twa, County Administrator and Clerk of the Board of Supervisors
By: EMY L. SHARP, Deputy
cc: J. Dowling, Construction, A. Bell, Construction, P. Denison, Finance, C. Lau, Transportation Engineering, L. Costa, Design, M. Carlson, Transportation
Engineering
C. 1
To:Board of Supervisors
From:Julia R. Bueren, Public Works Director/Chief Engineer
Date:February 2, 2010
Contra
Costa
County
Subject:ACCEPTANCE and Giving Notice of Completion of Contract for the Delta De Anza Trail Gap Closure project, Project No.
0662-6R4001-08