HomeMy WebLinkAboutMINUTES - 01192010 - C.61RECOMMENDATION(S):
Authorize the County Librarian to temporarily close the Martinez Library for approximately 6 months to complete a
remodel.
Authorize the County Librarian to spend the operational savings resulting from the closure to benefit library service in
Martinez.
FISCAL IMPACT:
None.
BACKGROUND:
Measure H, a $30 million bond measure in the City of Martinez to improve a number of community facilities, was
passed by 68% of the voters in November 2008. Library staff have been working with staff from the City of
Martinez, the Friends of the Martinez Library, the Martinez Parks, Recreation, Marina and Cultural Commission, and
the City Council as well as architects and consultants and members of the public to plan the improvements to the
Martinez Library. Major improvements include a program area and renovated staff area on the lower level,
installation of an elevator
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD
COMMITTEE
Action of Board On: 01/19/2010 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYES 4 NOES ____
ABSENT 1 ABSTAIN ____
RECUSE ____
Contact: Anne Cain, (925) 927-3201
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of
the Board of Supervisors on the date shown.
ATTESTED: January 19, 2010
David J. Twa, County Administrator and Clerk of the Board of Supervisors
By: June McHuen, Deputy
cc:
C.61
To:Board of Supervisors
From:Anne Cain, Librarian
Date:January 19, 2010
Contra
Costa
County
Subject:Martinez Library
Renovation
BACKGROUND: (CONT'D)
and other accessibility improvements, new accessible restrooms, and renovations to the public spaces on the main
level to accomodate the latest library technology.
In order to complete the project, the Library will need to close for approximately 6 months. Although the schedule
could change as the project moves through design development and construction documents, the current timeline
anticipates that the library will be closed from August 2010 to December 2010.
During the closure, Martinez Library staff will be deployed to cover vacant positions at other community libraries,
resulting in a salary savings of approximately $174,000. The operational savings will be spent to benefit library
service in Martinez in a way agreed to by the County Librarian and the City of Martinez. Possibilities include
funding additional open hours once the library reopens, enhancing the collection or purchasing furniture or equipment
for the Martinez Library.
In the past, operational savings resulting from closed libraries have been used to benefit library service in that