TERMINATE the emergency action orginally taken by the Board of Supervisors on June
23, 2009, regarding the repair of the Marsh Drive Bridge, as recommended by the Public
Works Director.
FISCAL IMPACT:
The total cost of the project was approximately $120,000. The project was funded by Local
Road Funds (100%).
BACKGROUND:
A. On June 23, 2009, the Board of Supervisors declared an emergency and authorized the
Public Works Director to proceed in the most expeditious manner to repair the Marsh Drive
Bridge.
B. Repair Status: A contract was awarded to Hess Concrete Construction Company by the
Public Works Director on August 26, 2009. The repair work was completed on September
30, 2009 and the work was accepted as complete by the Public Works Director on October
5, 2009.
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On: 10/20/2009 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:John Gioia, District I Supervisor
Gayle B. Uilkema, District II
Supervisor
Mary N. Piepho, District III
Supervisor
Susan A. Bonilla, District IV
Supervisor
Federal D. Glover, District V
Supervisor
Contact: Mike Hollingsworth,
313-2231
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the
Board of Supervisors on the date shown.
ATTESTED: October 20, 2009
David J. Twa, County Administrator and Clerk of the Board of Supervisors
By: EMY L. SHARP, Deputy
cc:
C.39
To:Board of Supervisors
From:Julia R. Bueren, Public Works Director/Chief Engineer
Date:October 20, 2009
Contra
Costa
County
Subject:TERMINATE emergency action for repair of Marsh Drive Bridge, Project No.:0662-6U4111-09