HomeMy WebLinkAboutMINUTES - 12152009 - C.04RECOMMENDATION(S):
ADOPT Resolution No. 2009/572 accepting completion of private improvements, for MS
90-00141, for project being developed by Charles M. Farr and Lorraine A. Farr, as
recommended by the Public Works Director, San Ramon area.
FISCAL IMPACT:
No fiscal impact.
BACKGROUND:
The developer completed the private improvements required of the minor subdivision.
CONSEQUENCE OF NEGATIVE ACTION:
The private improvements will not be accepted as complete, the developer will not receive a
refund of their cash deposit, the Subdivision Agreement and performance/maintenance
surety (letter of credit) will not be exonerated.
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On:
12/15/2009 APPROVED AS RECOMMENDED OTHER
Clerks Notes:Seven Speakers, Matt Trost, Michael Warholic, James A. Warholic, Patrick WarholicCharles Farr,
Michael L. Rains, and Lori Farr,
VOTE OF SUPERVISORS
AYE:John Gioia, District I
Supervisor
Gayle B. Uilkema, District II
Supervisor
Mary N. Piepho, District III
Supervisor
Susan A. Bonilla, District IV
Supervisor
Federal D. Glover, District V
Supervisor
Contact: J. LaRocque - 3-2315
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board
of Supervisors on the date shown.
ATTESTED: December 15, 2009
David J. Twa, County Administrator and Clerk of the Board of Supervisors
By: EMY L. SHARP, Deputy
cc: D. Favero, Engineering Services,, A. Bell, Construction,, E. Sanders, M & T Lab,, P. Edwards, Engineering Services,
C. 4
To:Board of Supervisors
From:Julia R. Bueren, Public Works Director/Chief Engineer
Date:December 15, 2009
Contra
Costa
County
Subject:Accepting completion of improvements, MS 90-00141, San Ramon area.
ATTACHMENTS
Resolution No.
2009/572