HomeMy WebLinkAboutMINUTES - 12082009 - C.04RECOMMENDATION(S):
ADOPT Resolution No. 2009/564 accepting completion of the Construction Road
Maintenance Agreement for Point of Timber Road and portions of Byron Highway, State
Route 4, Sellers Avenue, Marsh Creek Road and Camino Diablo (Haul Route) and release
of cash deposit for faithful performance, SD 03-08710 project being developed by Western
Pacific Housing, Inc., a Delaware Corporation, as recommended by the Public Works
Director, Discovery Bay area.
FISCAL IMPACT:
No fiscal impact.
BACKGROUND:
The Haul Route has been maintained during the construction period and all repairs have
been completed.
CONSEQUENCE OF NEGATIVE ACTION:
The developer will not receive a refund of their cash deposit, and the Construction Road
Maintenance Agreement and surety bond will not be exonerated.
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On: 12/08/2009 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:John Gioia, District I
Supervisor
Gayle B. Uilkema, District II
Supervisor
Mary N. Piepho, District III
Supervisor
Susan A. Bonilla, District IV
Supervisor
Federal D. Glover, District V
Supervisor
Contact: J. LaRocque - 3-2315
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board
of Supervisors on the date shown.
ATTESTED: December 8, 2009
David J. Twa, County Administrator and Clerk of the Board of Supervisors
By: EMY L. SHARP, Deputy
cc: D. Favero, Engineering Services,, E. Sanders, M & T Lab,, A. Bell, Construction,, P. Edwards, Engineering Services , H. Finch, Maintenance , : Tom
Morrison
C. 4
To:Board of Supervisors
From:Julia R. Bueren, Public Works Director/Chief Engineer
Date:December 8, 2009
Contra
Costa
County
Subject:Accepting completion of the Construction Road Maintenance Agreement for Point of Timber Road, SD
03-08710
ATTACHMENTS
Resolution No.
2009/564