HomeMy WebLinkAboutMINUTES - 12012009 - C.01RECOMMENDATION(S):
ADOPT Resolution No. 2009/528 accepting as complete the contracted work performed by
Ghilotti Construction Company, Inc. for the 2009 Vasco Road Overlay project, as
recommended by the Public Works Director.
FISCAL IMPACT:
This project was funded by 85% American Recovery Reinvestment Act funds and 15%
Local Gas Tax funds.
BACKGROUND:
The Public Works Director reports that said work has been inspected and complies with the
approved plans, special provisions and standard specifications and recommends its
acceptance as complete as of October 28, 2009.
CONSEQUENCE OF NEGATIVE ACTION:
The contractor will not be paid and acceptance notification will not be recorded.
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On: 12/01/2009 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:John Gioia, District I
Supervisor
Gayle B. Uilkema, District II
Supervisor
Susan A. Bonilla, District IV
Supervisor
Federal D. Glover, District V
Supervisor
ABSENT:Mary N. Piepho, District III
Supervisor
Contact: Kevin Emigh, 313-2233
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the
Board of Supervisors on the date shown.
ATTESTED: December 1, 2009
David J. Twa, County Administrator and Clerk of the Board of Supervisors
By: EMY L. SHARP, Deputy
cc: L. Costa, M. Carlson, P. Denison, Finance
C. 1
To:Board of Supervisors
From:Julia R. Bueren, Public Works Director/Chief Engineer
Date:December 1, 2009
Contra
Costa
County
Subject:ACCEPTANCE and Giving Notice of Completion of Contract for the 2009 Vasco Road Overlay project,
Project No.: 0662-6R4069-09
ATTACHMENTS
Resolution No.
2009/528