HomeMy WebLinkAboutMINUTES - 10062009 - C.01RECOMMENDATION(S):
APPROVE the Camino Tassajara Road Shoulder Widening project, south of Highland
Road, (San Ramon) and FIND the project is a California Environmental Quality Act
(CEQA), Class 1c Categorical Exemption, pursuant to Article 19, Section 15301(c) of the
CEQA Guidelines, and
DIRECT the Director of Conservation and Development to file a Notice of Exemption with
the County Clerk, and
AUTHORIZE the Public Works Director to arrange for payment of a $25 fee to the
Department of Conservation and Development for processing, and a $50 fee to the County
Clerk for filing the Notice of Exemption, and
AUTHORIZE the Public Works Director, or designee, to advertise the project.
FISCAL IMPACT:
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On: 10/06/2009 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:John Gioia, District I Supervisor
Gayle B. Uilkema, District II
Supervisor
Mary N. Piepho, District III
Supervisor
Susan A. Bonilla, District IV
Supervisor
Federal D. Glover, District V
Supervisor
Contact: Kimani Birden (925)
313-2190
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the
Board of Supervisors on the date shown.
ATTESTED: October 6, 2009
David J. Twa, County Administrator and Clerk of the Board of Supervisors
By: EMY L. SHARP, Deputy
cc: Emma Kuevor, Affirmative Action Officer, Karen Fernandez, Finance, Bill Fernandez, Design, Marlon Epps, Engineering Services
C. 1
To:Board of Supervisors
From:Julia R. Bueren, Public Works Director/Chief Engineer
Date:October 6, 2009
Contra
Costa
County
Subject:APPROVE the Camino Tassajara Road Shoulder Widening project South of Highland Road and make
related findings under CEQA (CP#08-14) Project No.:6P4023
The estimated project cost is $933,000. This project is funded by Prop 1B (40%) and South
County AOB (60%).
BACKGROUND:
Contra Costa County Public Works Department (CCCPWD) is planning to implement the
Camino Tassajara Shoulder Widening South of Highland Road Project to provide a new
shoulder recovery area for drivers along Camino Tassajara Road and to bring the
shoulders up to current design standards. The project will begin approximately 520 feet
south of Highland Road and will extend 3,900 feet to the south of Highland. The existing
pavement section is approximately 24 feet wide with two 12 foot lanes. The new
pavement section will be widened to 34 feet with two 12 foot wide lanes, 5 foot wide
shoulders, and 3 foot wide shoulder backing on both sides of the roadway. In addition,
approximately 1,400 feet of the roadway will be realigned to the west to avoid further
undercutting associated with Tassajara Creek to the east. In most locations, areas that
currently sheet flow to adjacent properties will continue to do so after the project is
completed. In those areas where the roadway is flanked on both sides by drainage ditches
(approximately 1500 linear feet), it will be necessary to create new ditches or relocate
existing ditches further from the road to accommodate the widening. Once the ditches are
relocated they will be reconnected to existing ditches. The project will address the
following erosion related damage associated with Tassajara Creek and the drainage
ditches that run parallel to Camino Tassajara Road:
• At a location midway along the project area, the roadway embankment adjacent to
Tassajara Creek on the east side of the project is experiencing erosion damage. A hot
mixed asphalt (HMA) dike will be installed along the edge of the pavement to redirect
runoff away from the damage and towards a shallow depression area a short distance
away. Redirection of the drainage to this stable area will correct the erosion problem. No
work will occur within Tassajara Creek.
• A rock and/or concrete spillway will be constructed between an existing roadside ditch
and a small unnamed drainage. The spillway will stop the erosion that is occurring
between the edge of the roadway and the small drainage, which if left unimproved could
erode into the road. Additionally, a small gabion weir structure will be installed just
upstream of the new spillway to dissipate the energy that is creating substantial erosion in
this small drainage, which could also endanger the road if not addressed.
Approximately 50,000 square feet of new right-of-way will be required (between 5 to 20
feet on either side of the roadway) in order to accommodate the widening, provide room
for joint utility pole relocation, accommodate the spillway and drainage modifications,
and the new ditches. Existing home owner fencing will be relocated where right-of-way
is acquired for widening. A gate will be installed in the existing fence adjacent to the
spillway for maintenance access.
A driveway culvert will be installed under an existing driveway. Another driveway
culvert which has been crushed and is not functioning properly will be replaced. Six
existing mailboxes that conflict with the proposed widening will be relocated further
from the road. Once the widening is complete, the road will be slurry sealed and striped.
Approximately 18 trees lining the roadway that conflict with the proposed widening will
need to be removed. None of the trees are riparian as they are separated from Tassajara
Creek by Camino Tassajara Road. Tree removal will not cause a significant aesthetic
impact, as there are large numbers of trees in the surrounding area and lining Tassajara
Creek and the trees do not constitute a stand. Approximately 3 single trunk Southern
California black walnut trees (approximately 25” dbh), 9 multi-trunk Southern California
black walnut trees (<48” dbh), 6 valley oak (<24” dbh) will be removed to accommodate
realignments to the western side of the roadway. In order to ensure compliance with the
Federal Migratory Bird Treaty Act, the trees will be removed outside of the nesting
season (March 1 through August 31), or if that is not feasible, a nesting bird survey will
be conducted by a qualified biologist to ensure no active nests. If active nests are
identified, construction will be delayed until the young have fledged. The project area
contains potential red-legged frog (RLF) habitat. CCCPWD staff met with staff from the
U.S. Fish and Wildlife Service (USFWS) at the project site. USFWS staff indicates that
the project qualifies for coverage under the programmatic consultation for RLF between
USFWS and the U.S. Army Corps of Engineers. Based on this preliminary consultation,
the CCCPWD will implement avoidance and minimization measures outlined in the
programmatic consultation that includes conducting a preconstruction survey within two
weeks of the start of construction, presenting an education program to the contractor’s
crews, and contracting with a qualified biologist to monitor all habitat disturbances
during construction to ensure impacts to RLF are avoided. In order to minimize impacts
to surrounding environmentally sensitive areas, the project has been designed to include
Best Management Practices (BMPs) such as:
1. Implementation of permanent BMPs for long-term erosion prevention and sediment
control, including minimizing the amount of disturbed area and preserving existing
vegetation to the maximum extent possible.
2. Daily trash removal from the site will ensure the area is maintained in a clean
condition.
3. Fueling and maintenance of equipment at designated areas outside the creek channel,
and assurance that machinery is properly maintained so as to not allow deleterious fluids
to enter the creek.
4. Following completion of the project; any exposed areas will be seeded with a mix
including native grasses prior to winter rains.
In addition, the project area was also reviewed via detailed records search and pedestrian
survey by a qualified archeological consultant (Condor Country Consulting Inc.). Based
on the records search and field work, no archeological resources or architectural
structures will be directly or indirectly impacted by the project. No work that interferes
with traffic flow will be performed during commute hours between 6:30 am to 8:30 am
Monday through Friday with no p.m. or weekend limitations. During non-commute times
only, one lane of traffic will be closed for construction with flagmen controlling traffic
during construction activities. At least one lane of traffic will be open at all times during
construction activities and emergency vehicles will have access at all times.
Real property transactions, including right-of-way acquisition may be necessary in
support of this project. Utility relocations may be necessary in support of the project.
CONSEQUENCE OF NEGATIVE ACTION:
Delay in approving the project will result in delay of design and construction and may
jeopardize funding.
ATTACHMENTS
S:\ENG Services\BO Camino Tassajara Shoulder Widening Proj..pdf
S:\ENG Services\Camino Tassajara Notice of Exemption.pdf