HomeMy WebLinkAboutMINUTES - 09222009 - C.10RECOMMENDATION(S):
ADOPT Resolution No. 2009/450 ratifying the prior decision of the Public Works Director,
or designee, to partially close the east/north bound lane of Jones Road between Oak Road
and Treat Boulevard, on September 8, 2009 through April 30, 2010 for the period of 24
hours per day, 7 days a week for the purpose of Iron Horse Trail Pedestrian Overcrossing
Project No.: 0662-6R4078-05, Contra Costa Centre area.
FISCAL IMPACT:
No fiscal impact.
BACKGROUND:
Applicant shall follow guidelines set forth by the Public Works Department. The closure is
needed to improve pedestrian, bicyclist and vehicular traffic flows in the project area for the
duration of the construction project.
CONSEQUENCE OF NEGATIVE ACTION:
Applicant will not have Board approval for completed road closure. Traffic flows in the
project area will continue to be congested
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On: 09/22/2009 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:John Gioia, District I
Supervisor
Gayle B. Uilkema, District II
Supervisor
Mary N. Piepho, District III
Supervisor
Susan A. Bonilla, District IV
Supervisor
Federal D. Glover, District V
Supervisor
Contact: Bob Hendry,
335-1575
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board
of Supervisors on the date shown.
ATTESTED: September 22, 2009
David J. Twa, County Administrator and Clerk of the Board of Supervisors
By: EMY L. SHARP, Deputy
cc: Bob Hendry, Engineering Services
C.10
To:Board of Supervisors
From:Julia R. Bueren, Public Works Director/Chief Engineer
Date:September 22, 2009
Contra
Costa
County
Subject:Jones Road closure between Oak Road and Treat Boulevard.
ATTACHMENTS
Resolution No.
2009/450