HomeMy WebLinkAboutMINUTES - 09222009 - C.03RECOMMENDATION(S):
APPROVE and AUTHORIZE the Chair, Board of Supervisors, to execute the Temporary
Permit for biological, topographical and archaeological surveys with East Bay Municipal
Utility District (EBMUD), effective September 1, 2009 through December 31, 2010, for the
Alhambra Valley Road Safety Improvements at Bear Creek Road Project, as recommended
by the Public Works Director.
FISCAL IMPACT:
There is no impact to the County General Fund. All funding comes from the project, 50%
High Risk Rural Road Grant and 50% Local Road Funds.
BACKGROUND:
The Public Works Department is in the initial phase of the Alhambra Valley Road Safety
Improvements at Bear Creek Road Project. It is necessary to conduct archaeological,
topographical and environmental testing and surveys to determine the impact in the
surrounding area before the project can move forward. As a condition of the permit,
EBMUD has required the County to indemnify EBMUD.
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On: 09/22/2009 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:John Gioia, District I
Supervisor
Gayle B. Uilkema, District II
Supervisor
Mary N. Piepho, District III
Supervisor
Susan A. Bonilla, District IV
Supervisor
Federal D. Glover, District V
Supervisor
Contact: Lisa Dalziel,
313-2223
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board
of Supervisors on the date shown.
ATTESTED: September 22, 2009
David J. Twa, County Administrator and Clerk of the Board of Supervisors
By: EMY L. SHARP, Deputy
cc:
C. 3
To:Board of Supervisors
From:Julia R. Bueren, Public Works Director/Chief Engineer
Date:September 22, 2009
Contra
Costa
County
Subject:Alhambra Valley Road Safety Improvements at Bear Creek Road Project, Martinez area. Project No.
0662-6R4101
CONSEQUENCE OF NEGATIVE ACTION:
The project would not be able to move forward.