HomeMy WebLinkAboutMINUTES - 09222009 - C.01RECOMMENDATION(S):
APPROVE the Proposition 1B revised project list identifying the projects for funding with
Proposition 1B funds, as recommended by the Public Works Director, Countywide.
FISCAL IMPACT:
No impact to the General Fund. The County has already received approximately $11.8
million in Proposition 1B funds and is expected to receive an additional $12.3 million in the
coming years.
BACKGROUND:
In 2006, Governor Schwarzenegger signed a $37.3 billion package of bonds for highways,
schools, levees and affordable housing. The package contained several components
including Senate Bill 1266 (SB 1266), the Highway Safety, Traffic Reduction, Air Quality
and Port Security Bond Act of 2006. The act, approved by the voters as Proposition 1B at
the November 7, 2006 general election, authorizes the issuance of $19.9 billion of general
obligation bonds to fund a variety of transportation priorities including reducing emissions
and improving air quality in trade corridors,
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On: 09/22/2009 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:John Gioia, District I Supervisor
Gayle B. Uilkema, District II
Supervisor
Mary N. Piepho, District III
Supervisor
Susan A. Bonilla, District IV
Supervisor
Federal D. Glover, District V
Supervisor
Contact: Adelina Huerta, (925)
313-2305
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the
Board of Supervisors on the date shown.
ATTESTED: September 22, 2009
David J. Twa, County Administrator and Clerk of the Board of Supervisors
By: EMY L. SHARP, Deputy
cc:
C. 1
To:Board of Supervisors
From:Julia R. Bueren, Public Works Director/Chief Engineer
Date:September 22, 2009
Contra
Costa
County
Subject:Proposition 1B revised project list, Countywide. (Proposition 1B Funds)
BACKGROUND: (CONT'D)
highway-railroad grade separation and crossing improvement projects, state highway safety
and rehabilitation projects, and local street and road improvements, congestion relief, and
traffic safety projects. In addition to Proposition 1B, four other bond measures known as
Proposition 1A (Proposition 42 protection), Proposition 1C (housing), Proposition 1D
(education) and Proposition 1E (levees and flood protection) were included on the ballot.
Of the $19.9 billion, $2 billion is designated for cities and counties to fund the maintenance
and improvement of local transportation facilities. The specific allocation for each agency is
based on the number of registered vehicles and the number of miles of road. Based on that
formula, Contra Costa County (unincorporated) is expected to receive $24.1 million over
the life of the program.
In order to receive funds, counties and cities must submit a plan to the State Department of
Finance for use of the amount of funds available.
The following revised project list demonstrates how Proposition 1B funds will be allocated:
Projects for Proposition 1B allocation
District 1
San Pablo Dam Road Safety Improvements $ 1,500,000
San Pablo Dam Road Downtown Improvements $ 500,000
District 2
Alhambra Valley Road Safety Improvements-East of Castro Ranch Road $ 1,100,000
Alhambra Valley Road Safety Improvements-East of Bear Creek Road $ 728,000
Alhambra Valley Road Pedestrian Path $ 400,000
District 3
Vasco Road Safety Improvements $ 4,000,000
Vasco Road/Camino Diablo Intersection Improvements $ 1,000,000
Deer Valley Road Safety Improvements- Marsh Creek Road to Briones Valley Road $
1,200,000
Deer Valley Road Safety Improvements- South of Chadbourne Road $ 667,000
Marsh Creek Road Safety Improvements- Round Valley Park to Lydia Lane $ 1,600,000
Marsh Creek Road Safety Improvements- 2.0 miles west of Deer Valley Road $ 772,000
Camino Tassajara Shoulder Improvements $ 900,000
Byron Highway Shoulder Improvements $ 1,800,000
Byron Highway Overlay $ 200,000
State Route 4 Bypass $ 3,000,000
District 4
Marsh Creek Road Safety Improvements- Russelmann Park Road $ 1,577,700
Deer Valley Road Safety Improvements- South of Chadbourne Road
District 5
Willow Pass Safety Improvements-Phase 1 $ 564,000
Willow Pass Safety Improvements –Phase 2 $ 500,000
Bethel Island Bridge Replacement -Dutch Slough $ 2,000,000
Marsh Creek Road Safety Improvements- 2.0 miles west of Deer Valley Road
Total $ 24, 008,700
CONSEQUENCE OF NEGATIVE ACTION:
The revised project list for the Proposition 1B allocation will not be approved and the
Bethel Island Bridge Replacement project will not be included on the project list.