HomeMy WebLinkAboutMINUTES - 08252009 - C.98RECOMMENDATION(S):
CONTINUE the emergency action taken by the Board of Supervisors originally on June 23,
2009, pursuant to Public Contact Code Sections 22035 and 22050, to repair the Marsh Drive
Bridge, Concord Area. (Project No. 0662-6U4111)
FISCAL IMPACT:
The total cost of the project is unknown at this time, but is not expected to exceed $200,000.
The project will be funded by Local Road Funds (100%).
BACKGROUND:
A. On June 23, 2009, the Board of Supervisors declared an emergency and authorized the
Public Works Director to proceed in the most expeditious manner to repair the Marsh Drive
Bridge.
B. Repair Status:
The project was advertised for bid on August 4, 2009 and sealed bids will be opened on
August 25, 2009. It is expected that construction will begin early September 2009.
APPROVE OTHER
RECOMMENDATION OF CNTY
ADMINISTRATOR
RECOMMENDATION OF BOARD
COMMITTEE
Action of Board On: 08/25/2009 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:Gayle B. Uilkema, District II
Supervisor
Mary N. Piepho, District III
Supervisor
Susan A. Bonilla, District IV
Supervisor
Federal D. Glover, District V
Supervisor
Contact: Mike Hollingsworth,
313-2231
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes
of the Board of Supervisors on the date shown.
ATTESTED: August 25, 2009
David J. Twa, County Administrator and Clerk of the Board of Supervisors
By: Katherine Sinclair, Deputy
cc:
C. 98
To:Board of Supervisors
From:Angela Bell, Public Works
Date:August 25, 2009
Contra
Costa
County
Subject:CONTINUE the emergency action for the repair of the Marsh Drive Bridge Project No.:0662-6U4111
CONSEQUENCE OF NEGATIVE ACTION:
Non-concurrence of the above recommendation will delay repair of the columns of the
Marsh Drive Bridge until summer 2010, prolonging this structure's exposure to severe
damage. Further deterioration of this structure could require closure of the bridge, adversely
affecting traffic circulation in the area.