HomeMy WebLinkAboutMINUTES - 08042009 - C.05RECOMMENDATION(S):
ADOPT Resolution No. 2009/367 accepting as complete the contracted work performed by
Asbestos Management Group of CA, Inc., for Phase 7 asbestos abatement and demolition of
the Orbisonia Heights Redevelopment Project, as recommended by the Public Works
Director, Bay Point area.
FISCAL IMPACT:
There is no impact to the County General Fund. This project is fully funded by the Contra
Costa County Redevelopment Agency.
BACKGROUND:
The Public Works Director reports that said work has been inspected and complies with the
special provisions and standard specifications and recommends its acceptance as complete
as of June 30, 2009, for 605 Bailey Road and 611 Bailey Road in Bay Point.
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On: 08/04/2009 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:John Gioia, District I
Supervisor
Gayle B. Uilkema, District II
Supervisor
Mary N. Piepho, District III
Supervisor
Susan A. Bonilla, District IV
Supervisor
Federal D. Glover, District V
Supervisor
Contact: Lisa Dalziel,
313-2223
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board
of Supervisors on the date shown.
ATTESTED: August 4, 2009
David J. Twa, County Administrator and Clerk of the Board of Supervisors
By: EMY L. SHARP, Deputy
cc:
C. 5
To:Board of Supervisors
From:Julia R. Bueren, Public Works Director/Chief Engineer
Date:August 4, 2009
Contra
Costa
County
Subject:Accepting and Giving Notice of Completion of Contract for abatement and demolition of properties, Bay
Point area. Project No. 4500-6X5489
ATTACHMENTS
Resolution No. 2009/367