HomeMy WebLinkAboutMINUTES - 06232009 - C.09RECOMMENDATION(S):
APPROVE the Pomo Street Arch Culvert Repair (Bay Point) project and FIND the project
is a California Environmental Quality Act (CEQA), Class 1d Categorical Exemption,
pursuant to Article 19, Section 15301d of the CEQA Guidelines, and
DIRECT the Director of Conservation and Development to file a Notice of Exemption with
the County Clerk, and
AUTHORIZE the Public Works Director to arrange for payment of a $25 fee to
Conservation and Development for processing, and a $50 fee to the County Clerk for filing
the Notice of Exemption, and
AUTHORIZE the Public Works Director, or designee, to advertise the project.
[CDD-CP#09-34]
Project No.:0662-6U4090
FISCAL IMPACT:
The estimated project cost is $48,000. This project is funded by Local Road Funds (100%).
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On: 06/23/2009 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:John Gioia, District I
Supervisor
Gayle B. Uilkema, District II
Supervisor
Mary N. Piepho, District III
Supervisor
Susan A. Bonilla, District IV
Supervisor
Federal D. Glover, District V
Supervisor
Contact: Leigh Chavez,
313-2366
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board
of Supervisors on the date shown.
ATTESTED: June 23, 2009
David J. Twa, County Administrator and Clerk of the Board of Supervisors
By: EMY L. SHARP, Deputy
cc:
C. 9
To:Board of Supervisors
From:Julia R. Bueren, Public Works Director/Chief Engineer
Date:June 23, 2009
Contra
Costa
County
Subject:APPROVE the Pomo Street Arch Culvert Repair (Bay Point) project and FIND it is exempt from California
Environmental Quality Act Project No.0662-6U4090
BACKGROUND:
The project will stop the accelerated corrosion at the air-soil interface and the portion of
the culvert extending to 12-inches above the interface and prevent future corrosion, thus
extending the life of the culvert.
The project consists of controlled sandblasting and application of a bitumastic coating to
the culvert from the air-soil interface to approximately 36-inches above the air-soil
interface and installing a cathodic protection system rated at 10 amps DC to protect the
buried portion of the culvert. This project will require minor trench work within the Pomo
Street right of way and easement over the Canal to bring power from a nearby electrical
box to a new PG&E pedestal at the project site. The new pedestal, rectifier, anode
junction box and bond box, as well as the new conduit will be permanently located within
the easement. The cathodic protection system and the bitumastic coating will require
monitoring and minor maintenance during the life of the culvert.
The project is located in unincorporated community of Bay Point in East Contra Costa
County; where Pomo Street crosses the Contra Costa Canal.
The project consists the restoration of a deteriorated facility, pursuant to CEQA
Guidelines (15301 Class 1d). The project will not result in the removal of any scenic
resource.
CONSEQUENCE OF NEGATIVE ACTION:
Delay in approving the project will result in delay of design and construction and may
jeopardize funding.
ATTACHMENTS
CEQA Pomo St Arch Culvert Repair