HomeMy WebLinkAboutMINUTES - 05192009 - C.04RECOMMENDATION(S):
APPROVE and AUTHORIZE the Chief Engineer, or designee, to execute the Temporary
Permit for Soil Testing and Survey studies, with John and Margaret Camara and Hillside
Group, LLC, effective March 1, 2009 through August 31, 2009, for the Upper Sand Creek
Detention Basin Project.
FISCAL IMPACT:
There is no impact to the County General Fund.
BACKGROUND:
The Contra Costa County Flood Control and Water Conservation District is in the initial
phase of the Upper Sand Creek Detention Basin Project. It is necessary to conduct soil
testing and surveys to determine the impact in the surrounding area before the project can
move forward. As requested by the property owners, indemnification has been included in
the permit.
CONSEQUENCE OF NEGATIVE ACTION:
The project would not be able to move forward.
APPROVE OTHER
RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
Action of Board On: 05/19/2009 APPROVED AS RECOMMENDED OTHER
Clerks Notes:
VOTE OF SUPERVISORS
AYE:John Gioia, District I
Supervisor
Gayle B. Uilkema, District II
Supervisor
Mary N. Piepho, District III
Supervisor
Susan A. Bonilla, District IV
Supervisor
Federal D. Glover, District V
Supervisor
Contact: Lisa Dalziel,
313-2223
I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board
of Supervisors on the date shown.
ATTESTED: May 19, 2009
David J. Twa, County Administrator and Clerk of the Board of Supervisors
By: Jane Pennington, Deputy
cc:
C.4
To:Board of Supervisors
From:Julia R. Bueren, Public Works Director/Chief Engineer
Date:May 19, 2009
Contra
Costa
County
Subject:Temporary Permit for Soil Testing and Survey Studies, Antioch area. Project No. 7589-6D8518
ATTACHMENTS
Permit