HomeMy WebLinkAboutMINUTES - 02032009 - C.01RECOMMENDATION(S): APPROVE the Alhambra Valley Road Pedestrian Bridge project contingency fund increase of $10,000.00 for a new contingency fund amount of $30,140.92 effective February 3, 2009, and APPROVE and AUTHORIZE the Public Works Director, or designee, to execute Contract Change Order No. 2 with E.E. Gilbert Construction, Inc., effective February 3, 2009, in an amount not to exceed $20,000.00, to a new payment limit of $231,550.09 for increased cost of drilled piers and concrete bridge abutments, Martinez area. (Alhambra Valley Specific Plan funds)(District II) Project No. 0662-6R4059-08. FISCAL IMPACT: The project contingency funds are currently insufficient to cover the increased cost. The increase in contingency funds will be funded by Alhambra Valley Specific Plan funds. BACKGROUND: Additional funding is required to increase the contract contingency amount to pay the contractor for additional costs incurred during the construction of the pedestrian bridge drilled piers and concrete bridge abutments. Approval of the contingency fund increase is required to compensate the contractor for the additional work. APPROVE OTHER RECOMMENDATION OF CNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE Action of Board On: 02/03/2009 APPROVED AS RECOMMENDED OTHER Clerks Notes: VOTE OF SUPERVISORS AYE:John Gioia, District I Supervisor Gayle B. Uilkema, District II Supervisor Mary N. Piepho, District III Supervisor Susan A. Bonilla, District IV Supervisor Federal D. Glover, District V Supervisor Contact: Kevin Emigh, 313-2233 I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board of Supervisors on the date shown. ATTESTED: February 3, 2009 David J. Twa, County Administrator and Clerk of the Board of Supervisors By: , Deputy cc: Janet Dowling, Paulette Denison C.1 To:Board of Supervisors From:Julia R. Bueren, Public Works Director/Chief Engineer Date:February 3, 2009 Contra Costa County Subject:APPROVE Project Contingency Fund Increase and execute Contract Change Order No. 2 for Project No. 0662-6R4059-08, Martinez area CONSEQUENCE OF NEGATIVE ACTION: The lack of approval would prevent successful completion of this contract and preclude payment to the contractor for the required work.