HomeMy WebLinkAboutRESOLUTIONS - 08132013 - 2013/340EXHIBIT A
LAND DEVELOPMENT FEE SCHEDULE
APPROVED AUGUST 13, 2013
EFFECTIVE OCTOBER 12, 2013
Page 1 of 24
S-001 Permit Processing and Issuance Program
A. Plan Review 65% of Building Permit Fee. Applicable when plans are
required beyond a plot or site plan.
B. Permit Review and Processing 25% of Building Permit Fee. Applicable when review for
compliance can be determined through a plot or site plan,
or references to a master plan previously reviewed and
approved by the department.
C. Additional Processing Applicable when additional plan review is required due
to: 1) incomplete or unacceptable follow-through by
applicant on deficiencies found in the initial plan review;
2) significant revisions submitted after plan review is well
underway; or 3) revisions submitted during construction
to reflect field changes. Fees for such reviews shall be at
the hourly rates in effect at the time of plan review.
D. Refinery and Chemical Plant Fee
1. Yearly Building/
Grading Permit
10% of the actual annual valuation of building
construction and grading activity. Excluded from this
category are all expenditures for which individual
building or grading permits are applicable.
2. Individual Building/
Grading Permit
For new construction, additions, or major alterations of
buildings, the fees charged will be consistent with other
sections of this fee schedule. For all other construction
work the valuation will be based upon the actual cost of
materials and labor associated with the installation of
foundations and other structural items only. The permit
will be calculated as per Table No. 1-A.
3. Yearly Electrical Permit 1% of the actual valuation of electrical construction
activity.
S-002 Construction Inspection Program
A. Building Inspection
1. Building Permit The Building Permit fee shall be as set forth in the Fee
Schedule (Table No. 1-A) or $75.00 whichever is greater.
2. Energy Compliance 25% of Building Permit and Plan Review or processing
fees. Applicable on all structures with heated or air-
conditioned space.
EXHIBIT A
LAND DEVELOPMENT FEE SCHEDULE
APPROVED AUGUST 13, 2013
EFFECTIVE OCTOBER 12, 2013
Page 2 of 24
3. Access Compliance 25% of Building Permit and Plan Review or processing
fees. Applicable on all buildings except residential use
buildings with fewer than 4 dwelling units. Additions and
alterations to an exempt building, and accessory structures
on the same parcel with an exempt building, also are
exempt from this fee.
B. Earthquake Fee Residential: $10 per each $100,000 of building valuation.
Commercial: $20 per each $100,000 of building valuation.
Valuation. The determination of value or valuation under any provisions of the County Building
Code shall be made by the Director of Conservation and Development. The total valuation to be
used with the Fee Schedule shall be determined using the Building Valuation Data contained in the
Building Safety Journal, published by the International Code Council (ICC) or in the Successor
magazine published by the ICC or its Successor organization. The data in the March -April issue of
each year shall be used for the ensuing fiscal year. Work not listed in the Building Valuation Data
shall be valued per the Building Valuation Data Supplement below, which may be modified
administratively by the Director of Conservation and Development to clarify or cover additional
types of work and situations.
The valuation to be used in computing the building permit fee shall be the total valuation of all
construction work for which the permit is issued, as well as all finish work, painting, roofing,
mechanical, electrical, plumbing, heating, air conditioning, elevators, fire extinguishing systems,
and any other permanently installed equipment. For industrial facilities, the value of process
equipment and heavy machinery supported by the structure or by its own foundation shall be
included. Contractor overhead and profit shall be included.
The valuation of grading, retaining walls, paving and other site work, and any demolition work,
shall be included unless such work was included in other permits issued by the Department of
Conservation and Development.
The valuation data is used to establish consistent criteria for calculating permit fees, and the
calculated total valuation does not necessarily reflect actual costs. The County Assessor does not
rely on this cost, but performs independent assessments of the permitted work.
EXHIBIT A
LAND DEVELOPMENT FEE SCHEDULE
APPROVED AUGUST 13, 2013
EFFECTIVE OCTOBER 12, 2013
Page 3 of 24
BUILDING VALUATION DATA SUPPLEMENT
The work listed in this supplement shall be valued based on the gross square footage of the work, or where noted,
as a lump sum. Where actual costs are higher, those costs shall be used for the valuation.
$/Sq.Ft.
1. Residential addition
-Good Quality
-Average Quality
94.80
69.04
2. Residential remodel (to existing floor areas)
If bathrooms are added or remodeled, for each one, add lump sum of:
If kitchen is remodeled, add lump sum of:
47.40
5,000.00
15,000.00
3. Residential use conversion from garage, basement or unfinished area
-Good Quality
-Average Quality
If bathrooms or kitchen added, include lump sum(s) as for residential remodel.
56.50
33.90
4. Sun room with >60% glazing, cabanas, other similar structures
If conditioned space and integrated with main structure, add:
37.10
58.30
5. Patio cover (includes pre-fab types, usually with ICBO research listing)
If enclosed with walls or glazing, add:
16.27
31.80
6. Deck 15.90
7. Retaining wall (projected sq.ft. areas of wall and footing)
-concrete or CMU
-wood
10.60
5.30
8. Freestanding fence (projected area)
-concrete or CMU
-wood, chainlink
5.30
3.18
9. Swimming pool, lump sum of: 25,000.00
10. Remodel or tenant improvement work in commercial buildings
Type I and II Construction
Type III, IV and V Construction
If restrooms are added or relocated - add lump sum for each:
If commercial kitchen is added - add lump sum of:
31.80
26.50
10,000.00
30.000.00
11. Reroofing
-Built up, composition shingles, foam
-Treated wood, metal and proprietary products
-Tile - masonry, clay, concrete
3.18
3.71
4.77
EXHIBIT A
LAND DEVELOPMENT FEE SCHEDULE
APPROVED AUGUST 13, 2013
EFFECTIVE OCTOBER 12, 2013
Page 4 of 24
12. Mobile home on permanent foundation (based on square footage of mobile home) 10.60
13. Moved building (for existing s.f. any added s.f. shall be at "average quality" valuation) 31.80
14. Agricultural/husbandary buildings
-Pole construction
-Wood construction
-Steel construction
9.00
14.00
16.00
B. Electrical Inspection Fees
1. New dwelling 15% of the Building Permit Fee.
2. Addition or alteration to dwelling unit 20% of the Building Permit Fee, $75.00 minimum.
3. New commercial building 25% of the Building Permit Fee, $75.00 minimum.
4. Shell building 5% of the Building Permit Fee, $75.00 minimum.
5. Commercial alterations & tenant
improvements
20% of the Building Permit Fee, $75.00 minimum.
6. Electrical Permit $75.00 minimum. *See note below.
* An electrical permit is required for all electrical work regulated by the Electrical Code. Fees for
work not included in Items 1 - 5 above shall be calculated using Table 1-A and based on the contract
amount of the electrical work. Where such electrical work is performed in conjunction with a
building permit, the fee may be added to that permit, and a separate electrical permit is not required.
C. Mechanical Inspection Fees
1. New dwelling 10% of the Building Permit Fee.
2. Addition or alteration to dwelling unit. 15% of the Building Permit Fee, $75.00 minimum.
3. New commercial building 15% of the Building Permit Fee, $75.00 minimum.
4. Shell building 5% of the Building Permit Fee, $75.00 minimum.
5. Commercial alterations & tenant
improvements
10% of the Building Permit Fee, $75.00 minimum.
6. Mechanical Permit $75.00 minimum.*See note below.
EXHIBIT A
LAND DEVELOPMENT FEE SCHEDULE
APPROVED AUGUST 13, 2013
EFFECTIVE OCTOBER 12, 2013
Page 5 of 24
* A mechanical permit is required for all mechanical work regulated by the Mechanical Code. Fees
for work not included in Items 1 - 5 above shall be calculated using Table 1-A and based on the
contract amount of the mechanical work. Where such mechanical work is performed in conjunction
with a building permit, the fee may be added to that permit, and a separate mechanical permit is not
required.
D. Plumbing Inspection Fees
1. New dwelling 15% of the Building Permit Fee.
2. Addition or alteration to dwelling unit 20% of the Building Permit Fee, $75.00 minimum.
3. New commercial building 20% of the Building Permit Fee, $75.00 minimum.
4. Shell building 5% of the Building Permit Fee, $75.00 minimum.
5. Commercial alterations & tenant
improvements
15% of the Building Permit Fee, $75.00 minimum.
6. Plumbing Permit $75.00 minimum. *See note below.
* A plumbing permit is required for all plumbing work regulated by the Plumbing Code. Fees for
work not included in Items 1 - 5 above shall be calculated using Table 1-A and based on the contract
amount of the work. Where such plumbing work is performed in conjunction with a building permit,
the fee may be added to that permit, and a separate plumbing permit is not required.
E. Miscellaneous Fees
1. Reinspections. When return trips to the site by an inspector are necessary as specified below, a
reinspection fee shall be charged as follows:
a. For building permits with total valuations not exceeding $5,000, $50 per trip.
b. For building permits with total valuations of more than $5,000, $100 per trip.
c. For electrical, mechanical and plumbing permits on residential buildings, $50 per trip.
d. For electrical, mechanical and plumbing permits on non-residential buildings, $100 per trip.
Situations where reinspection fees shall be applicable include the following:
a. When the work for a called inspection is not ready or not accessible to the inspector.
EXHIBIT A
LAND DEVELOPMENT FEE SCHEDULE
APPROVED AUGUST 13, 2013
EFFECTIVE OCTOBER 12, 2013
Page 6 of 24
b. When extra inspections are necessary due to deficient or defective work through fault or error of
the owner or contractor. One such extra inspection will be made for each phase of work that
requires inspection (i.e. foundation, rough electric, etc.) under the regular fees prescribed in this
section. A reinspection fee shall be charged for each additional visit or inspection thereafter.
c. When more than one inspection is made on a phase of work (i.e., "partial inspections") that
normally is inspected in one trip. The fee may be waived when partial inspections are necessary
due to the large size of the project, or when the inspections do not adversely affect the efficiency
of the inspector.
2. Owner-requested inspection of an existing building. The fee shall be based on an hourly rate @ $90
per hour, with 1 hour minimum. If overtime is required the rate shall be $180 per hour with a 1-hour
minimum.
3. Inspection for Change of Occupancy. The fee shall be based on an hourly rate @ $90 per hour, with
1-hour minimum.
4. Investigation of work without permit. When a Stop Work Notice is issued for work being performed
without permits or performed beyond the scope of existing permits, a special investigation and
inspection shall be made before permits may be issued for such work. An investigation fee shall be
charged equal to two times the amount of all permit fees required by this ordinance, with a
minimum of $250. The fee is additive to the permit fees. This provision shall not apply to
emergency work when it can be proven to the satisfaction of the Director of Building Inspection that
such work was urgently necessary, that it was not practical to obtain a permit before the work was
commenced, and that a permit was applied for as soon as practical.
5. Abatement of Code Violations.
Building: Abatement costs: When an RF (Report Form) is issued as a result of an inspection of a
property, and compliance is required to correct violations found, or permits are required
to legalize work previously performed without building permits, a code enforcement cost
shall be charged equal to two times the amount of all permit fees required by this
ordinance, with a minimum of $250. Where repeat visits are required before the owner
complies or obtains the required permits, a reinspection cost of $100 per trip shall be
charged after the second trip. Where repeat visits are necessary after compliance or
permit issuance to enforce the abatement work, a reinspection cost of $100 per trip shall
be charged after the second trip. The costs in this section are additive to the permit fees.
EXHIBIT A
LAND DEVELOPMENT FEE SCHEDULE
APPROVED AUGUST 13, 2013
EFFECTIVE OCTOBER 12, 2013
Page 7 of 24
Zoning: When Code Enforcement activities are required as a result of an inspection of a property
and compliance is required to correct violations found, or permits are required for
compliance, a code enforcement cost shall be charged equal to the amount of all permit
fees required by this ordinance, with a minimum of $250. Where repeat visits are
required before the owner complies or obtains the required permits, a reinspection cost of
$100 per trip shall be charged. Where repeat visits are necessary after compliance or
permit issuance to enforce the abatement work, a reinspection cost of $100 per trip shall
be charged. The costs in this section are additive to the permit fees.
6. Renewal fee for an expired permit:
For Final Inspection: 10% of the current building valuation will be used as the basis for the
calculation of the building permit fee.
For permits that have expired within one year after issuance date: the permit fee will be 50% of
the sum of the original building, electrical, mechanical and plumbing fees.
For permits that have expired more than 180 days after the last inspection occurred: full fee is
applicable.
S-003 Grading Plan Check/Inspection
Improvement Value:
$100,000 or less
$100,001 to $1,000,000
Over $1,000,000
Additional fee if:
Work goes over 1 year
Work goes over 2 years
Fee:
The greater of 5% or $100.
$5,000 plus 4% of amount in excess of: $100,000.
$41,000 plus 3% of amount in excess of: 1,000,000.
1% of uncompleted work + $100.
2% of uncompleted work + $100.
S-004 Building Demolition Review $100 permit.
S-005 Mobile Home Park Annual Inspection $25 plus $2 per lot for licensing, plus $4 per mobile
home lot for annual inspection.
S-006 Mobile Home Permit Inspection Application: $20.
Inspection: $100 plus $30 for each half hour over one
hour.
Reinspection: $60 plus $30 for each half hour over one
hour.
S-007 Permanent Mobile Home Inspection Same as construction inspection. (S-002)
EXHIBIT A
LAND DEVELOPMENT FEE SCHEDULE
APPROVED AUGUST 13, 2013
EFFECTIVE OCTOBER 12, 2013
Page 8 of 24
S-008 R-Form Complaint Investigation Costs are offset by a portion of the 40% surcharge
collected on building permit fees. To the extent surcharge
revenues are insufficient, costs are absorbed by the
operations reserve.
S-009 R-Form Site Investigation $200 per investigation plus County's fully burdened
hourly rates for travel time outside the County.
S-010 County Code Compliance $200 per report.
S-011 Records Information Research Retrieval/research fee: $60 per hour, $15 minimum.
Photocopy charges at published rates.
Documents requested to be certified have an additional
charge:
First page: $4.50
Add'l pages: $1.00 each
S-012 Subpoena Services Evidence reproduction: $60 per hour, $15 minimum
Witness summons: Time and materials plus mileage,
$150 deposit.
S-013 Certificate of Compliance Review/
Determination of Legal Lot
$1,000 minimum deposit, time and materials.
S-014 Development Plan Review
(Multiple-family/Commercial/
Office/ Industrial)
$6,000 minimum deposit plus
Multiple-family: $195 per unit.
Commercial, Office, Industrial: $.20 sq.ft.
Time and materials.
S-015 Development Plan Review
(Exterior Change)
$2,900 minimum deposit. Time and materials.
S-016 Development Plan Review
(No Exterior Change)
$2,000 minimum deposit. Time and materials.
S-017 Time Extension (Administrative) $200 fee.
S-018 Time Extension (Public Hearing) $600 fee.
S-019 General Plan Amendment Review $5,000 plus $100 per acre minimum deposit.
Time and materials. $3,500 nonrefundable fee for
General Plan Maintenance.
S-019A Specific Plan Amendment $5,000 minimum deposit. Time and materials.
EXHIBIT A
LAND DEVELOPMENT FEE SCHEDULE
APPROVED AUGUST 13, 2013
EFFECTIVE OCTOBER 12, 2013
Page 9 of 24
S-019B General Plan Amendment Feasibility
Request
$750 fee credited towards subsequent General Plan
Amendment application.
S-020 General Plan Maintenance Costs are offset by the 40% surcharge on building permit
fees. To the extent such fees are insufficient, costs will
be absorbed by the operations reserve.
S-021 Land Use Permit (Quarry) $5,600 minimum deposit plus $75 per acre.
Time and materials.
S-022 Land Use Permit
(Quarry Reclamation Plan)
$1,780 minimum deposit plus $75 per acre.
Time and materials.
S-023 Land Use Permit
(Caretaker Mobile Home)
$2,000 minimum deposit. Time and materials.
S-024 Land Use Permit
(Family Member Mobile Home)
$750 minimum deposit. Time and materials.
$150 with proof of financial hardship of property owner.
S-025 Land Use Permit
(Residential Care Facility)
$3,000 minimum deposit. Time and materials.
S-026 Land Use Permit (Home Occupation) $500 minimum deposit. Time and materials.
S-027 Land Use Permit (Take Out Food) $2,700 minimum deposit. Time and materials.
S-027A Land Use Permit (Second Unit) $1,000 minimum deposit. Time and materials.
S-027B Land Use Permit
(Additional Residence)
$2,000 minimum deposit. Time and materials.
S-028A Land Use Permit
(Development Plan Combination)
$2,000 minimum deposit plus Development Plan deposit.
Time and materials.
S-028B Land Use Permit (Development Plan
Combo, Minor Revisions/Amendments)
$500 minimum deposit. Time and materials.
S-029 Land Use Permit (Other) $2,700 minimum deposit plus ½ % of value of project
over $100,000. Time and materials.
S-029A Land Use Permit
(Solid Waste Disposal Review)
$10,000 minimum deposit. Time and materials.
S-030 Land Use Permit
(Administrative Permit - Gas Well)
$570 minimum deposit. Time and materials.
S-031 Land Use Permit
(Gas Well Ordinance)
$2,060 minimum deposit. Time and materials.
EXHIBIT A
LAND DEVELOPMENT FEE SCHEDULE
APPROVED AUGUST 13, 2013
EFFECTIVE OCTOBER 12, 2013
Page 10 of 24
S-032 Lot Line Adjustment Review $50 per adjusted parcel. $500 minimum.
S-033 Tentative Subdivision Map Review -
Major
5-30 lots/units $5,490 minimum deposit plus $185
per lot/unit 5-30. Time and materials.
31-100 lots/units $11,500 minimum deposit plus $96
per lot/unit 31-100. Time and
materials.
101 or more
lots/units
$18,200 minimum deposit plus $64
per lot/unit 101 and up. Time and
materials.
S-033A Development Agreement $1,000 minimum deposit. Time and materials.
S-033B Development Impact Fee Deferral $500 – Agreement must be executed and recorded as lien
on property for deferral of Area of Benefit, Child Care,
Inclusionary Housing, Park Impact, Police Services, and
Traffic Impact Fees. Sunsets December 31, 2011.
S-034 Tentative Subdivision Map Review -
Minor
$4,800 minimum deposit plus $300 per lot/unit.
Time and materials.
S-034A Reversion to Acreage $1,500 minimum deposit. Time and materials.
S-035 Condo Conversion
Tentative Map
1 - 30 lots/units $1,910 minimum deposit plus $140 per lot/unit 1 - 30.
31 - 100 lots/units $6,104 minimum deposit plus $105 per lot/unit 31 - 100.
101/or more lots/units $13,454 minimum deposit plus $70 per lot/unit 101 and
up. Time and materials.
S-036 Lot Split $2,000 minimum deposit. Time and materials.
S-036A Undersized Lot Review $150 fee. If public hearing is requested, $500 minimum
deposit in addition to review fee. Time and materials.
S-037 Planned Unit Development
Rezoning Review - Residential
1-30 units $4,185 minimum deposit plus $128 per unit.
1-100 units $8,025 minimum deposit plus $96 per unit 31 - 100.
1-101/up $14,745 minimum deposit plus $64 per unit 101 and up.
Time and materials.
EXHIBIT A
LAND DEVELOPMENT FEE SCHEDULE
APPROVED AUGUST 13, 2013
EFFECTIVE OCTOBER 12, 2013
Page 11 of 24
S-038 Planned Unit Development
Rezoning Review -
Commercial/Industrial
$6,200 minimum deposit plus $.15 per sq.ft. of floor area
over 25,000 sq. ft. Time and materials.
S-039A Planned Unit Development
Final Development Plan
Review/New
$3,500 minimum deposit. Time and materials.
S-039B Planned Unit Development
Final Development Plan
Review/Non-Substantial
Modification
$1,000 minimum deposit. Time and materials.
S-039C Planned Unit Development
Final Development Plan Review/
Substantial Modification
$3,000 minimum deposit. Time and materials.
S-040 Planned Unit Development
Tentative Subdivision Map Review
$2,850 minimum deposit. Time and materials.
S-041 Rezoning Review -
Commercial/Industrial
$6,500 minimum deposit. Time and materials.
S-042 Rezoning Review - Other $2,500 minimum deposit. Time and materials.
S-043 Police Services District Formation $800 fee.
S-044 Zone Variance $1,000 minimum deposit. Time and materials.
S-045 Sign Review Minor modification: $550 fee.
Public hearing: Additional $800 deposit towards time
and materials.
S-045A Address Change/Private Road
Name Change
$500 fee plus $100 per address over 10.
S-046 Request for Determination $200 fee.
S-046A Accelerated Review Non-refundable deposit equal to 30% of amount of
consultant contract plus time and materials.
S-047A Zoning Administrator Appeal
- Land Use Permit
$125 filing fee.
Time and materials charged to applicant.
S-047B Zoning Administrator Appeal
- Minor Subdivision
$125 filing fee.
Time and materials charged to applicant.
EXHIBIT A
LAND DEVELOPMENT FEE SCHEDULE
APPROVED AUGUST 13, 2013
EFFECTIVE OCTOBER 12, 2013
Page 12 of 24
S-047C Zoning Administrator Appeal
- Major Subdivision
$125 filing fee.
Time and materials charged to applicant.
S-047D Zoning Administrator Appeal
- Other
$125 filing fee.
Time and materials charged to applicant.
S-047E Planning Commission Agenda
Mailing Service
$25 per year plus $5 per year for each additional agenda.
S-048 Fish and Game - Posting Fee
Administrative Fee
$50 fee.
$25 fee.
S-048A Appeal to the Board
- Land Use Permit
$125 filing fee.
Time and materials charged to applicant.
S-048B Appeal to the Board
- Minor Subdivision
$125 filing fee.
Time and materials charged to applicant.
S-048C Appeal to the Board
- Major Subdivision
$125 filing fee.
Time and materials charged to applicant.
S-048D Appeal to the Board
- Other
$125 filing fee.
Time and materials charged to applicant.
S-049 Reconsideration Review $125 filing fee. Time and materials.
S-049A Condition of Approval
Modification Review
$500 fee. Time and materials with $1,000 deposit if
modification goes to public hearing.
S-049B Modification of Official Document $250 fee.
S-050 Agricultural Preserve Rezoning Review $1,000 minimum deposit. Time and materials.
S-050A Agricultural Preserve Contract $500 deposit. Time and materials.
S-051 Agricultural Preserve
Cancellation Review
$5,400 minimum deposit. Time and materials.
EXHIBIT A
LAND DEVELOPMENT FEE SCHEDULE
APPROVED AUGUST 13, 2013
EFFECTIVE OCTOBER 12, 2013
Page 13 of 24
S-051A Preapplication Review
Minor Subdivision, Minor Land
Use Permit, Development Permit
(not more than one building)
Major Subdivision
up to 100 lots
101 - 250 lots
Major Residential, Commercial or
Industrial Development (more than
one building)
$500 fee. All additional costs charged to future
application, credit given for fee paid.
$750 fee. All additional costs charged to future
application, credit given for fee paid.
$950 fee. All additional costs charged to future
application, credit given for fee paid.
$1,000 fee. All additional costs charged to future
application, credit given for fee paid.
S-051B Agricultural Preserve
Non-Renewal Notice
$300 minimum deposit. Time and materials.
S-051C Annual Review of Quarry Reclamation $1,000 fee plus $2 per acre.
S-051D Permit for Alteration of Protected Trees $500 minimum deposit. Time and materials.
S-051F Heritage Tree (appeal) $50 minimum deposit plus time and materials.
S-051G Heritage Tree (nomination) $100 fee per tree.
S-051H Heritage Tree (removal permit) $1,000 minimum deposit plus time and materials.
S-051J Heritage Tree (encroachment permit) $500 minimum deposit plus time and materials.
S-052 Planning Surcharge 40% surcharge on building permits.
S-052A Fee Services Clerical Costs to be offset by a portion of the Planning Surcharge.
To the extent such revenues are insufficient, costs will be
absorbed by the operations reserve.
S-052B Notification List Services $1.50 per address plus $30.
S-053 Mitigation/ Condition of Approval
Compliance Monitoring
$1,500 minimum deposit plus time and materials.
EXHIBIT A
LAND DEVELOPMENT FEE SCHEDULE
APPROVED AUGUST 13, 2013
EFFECTIVE OCTOBER 12, 2013
Page 14 of 24
S-056 Hazardous Waste Application Review
Determination
Monitoring 86/100
Mitigation Monitoring
(non 86/100)
$2,440 minimum deposit plus time and materials.
$2,900/year minimum deposit plus time and materials.
Time and materials.
S-057 Environmental Impact Review Contract amount plus 30% administrative surcharge.
Time and materials.
S-059 County Water Agency Wetland Review $500 minimum deposit. Time and materials.
S-060 Records Information Research Retrieval/research fee: $60 per hour, $15 minimum.
Photocopy charges at published rates.
Documents requested to be certified have an additional
charge:
First page: $4.50.
Add'l pages: $1.00 each.
S-060A Geologic Review Contract amount. Time and materials.
Major Subdivision: Deposit of $750
Minor Subdivision: Deposit of $1,500
Others: Deposit based on estimated
contract amount.
Deposit to be paid at submittal application or submittal of
soil report whichever is earlier.
S-060B Landscaping and Tree Protection
Agreement
Time and materials charged against $100 minimum
initial deposit.
S-060C COA Compliance Check for
Building Permit Issuance
Minor Developments -
Major Developments -
$500 minimum deposit.
Time and materials.
$1,000 minimum deposit.
Time and materials.
S-060D Liquor License Site Determination $525 fee
S-060E Gun Ordinance Annual License $250 fee.
S-060F Deemed Approved Annual Fee $400 yearly fee per ABC license
EXHIBIT A
LAND DEVELOPMENT FEE SCHEDULE
APPROVED AUGUST 13, 2013
EFFECTIVE OCTOBER 12, 2013
Page 15 of 24
S-060G Subpoena Services Evidence reproduction: $60 per hour, $15 minimum.
Witness summons: Time and materials plus mileage,
$150 deposit.
S-060H Temporary Events $150 deposit – Time and materials - $2,500 cap.
S-060I Home Occupation Permit (Admin.) $50 fee.
S-060J Meteorological Tower Permit
(Admin.)
$1,000 minimum deposit plus time and materials.
S-061 Growth Management Task Force
Review
Costs offset by portion of 40% surcharge on Building
Review Permit fees. To the extent such revenues are
insufficient, costs will be absorbed by the operations
reserve.
S-062 Growth Management Plan CCTA funds program annually, as long as County was in
compliance in prior year. Allocation of funding internally
is determined by the Board of Supervisors.
Excess costs over annual funding determined by Board
of Supervisors is offset by 40% surcharge on building
permit fees and the operations reserve.
S-063 California Environmental Quality Act
Review County Projects - Non EIR
Time and materials excluding general overhead.
S-064 California Environmental Quality Act
Review County Projects -EIR
Time and materials excluding general overhead.
S-065 Child Care Application Review $1,000 minimum deposit. Time and materials.
S-066 Code Enforcement Costs are offset by 40% surcharge on building permit
fees. To the extent such revenues are insufficient, costs
will be absorbed by the operations reserve.
S-066A Late Filing of Development Permit
Application
Nonrefundable penalty equal to 50% of application fee or
deposit amount.
S-067 Counter Information Costs are offset by 40% surcharge on building permit
fees. To the extent such revenues are insufficient, costs
will be absorbed by the operations reserve.
FEES FOR NORTH RICHMOND PLANNED UNIT DISTRICT AREA
S-NR01 Administrative Permits $150 fee $300 deposit, plus time and materials.
S-NR02 Land Use Permit – Automotive Uses $1,000 deposit, plus time and materials.
EXHIBIT A
LAND DEVELOPMENT FEE SCHEDULE
APPROVED AUGUST 13, 2013
EFFECTIVE OCTOBER 12, 2013
Page 16 of 24
S-NR03 Land Use Permit $500 deposit, plus time and materials.
S-NR04 Development Permit $1,000 deposit, plus time and materials.
S-NR05 Lot Line Adjustment $150 fee per parcel, plus time and materials.
S-NR06 Annual Monitoring Fee $50 fee, plus time and materials.
S-NR07 Home Occupation $50 fee, plus time and materials.
FEES FOR RODEO PLANNED UNIT DISTRICT AREA
S-RD01 Administrative Permits $150 fee $300 deposit, plus time and materials.
S-RD02 Land Use Permit – Automotive Uses $1,000 deposit, plus time and materials.
S-RD03 Land Use Permit $500 deposit, plus time and materials.
S-RD04 Development Permit $1,000 deposit, plus time and materials.
S-RD05 Lot Line Adjustment $150 fee per parcel, plus time and materials.
S-RD06 Annual Monitoring Fee $50 fee, plus time and materials.
S-RD07 Home Occupation $50 fee, plus time and materials.
FEES FOR BAY POINT PLANNED UNIT DISTRICT AREA
S-BP01 Administrative Permits $150 fee $300 deposit, plus time and materials.
S-BP02 Land Use Permit - Automotive Uses $1,000 deposit, plus time and materials.
S-BP03 Land Use Permit $500 deposit, plus time and materials.
S-BP04 Development Permit $1,000 deposit, plus time and materials.
S-BP05 Lot Line Adjustment $150 fee per parcel, plus time and materials.
S-BP06 Annual Monitoring Fee $50 fee, plus time and materials.
S-BP07 Home Occupation $50 fee, plus time and materials.
FEES FOR MONTALVIN MANOR PLANNED UNIT DISTRICT AREA
S-MM01 Administrative Permits $150 fee $300 deposit, plus time and materials.
S-MM02 Land Use Permit – Automotive Uses $1,000 deposit, plus time and materials.
EXHIBIT A
LAND DEVELOPMENT FEE SCHEDULE
APPROVED AUGUST 13, 2013
EFFECTIVE OCTOBER 12, 2013
Page 17 of 24
S-MM03 Land Use Permit $500 deposit, plus time and materials.
S-MM04 Development Permit $1,000 deposit, plus time and materials.
S-MM05 Lot Line Adjustment $150 fee per parcel, plus time and materials.
S-MM06 Annual Monitoring Fee $50 fee, plus time and materials.
S-MM07 Home Occupation $50 fee, plus time and materials.
FEES FOR EL SOBRANTE PLANNED UNIT DISTRICT AREA
S-ES01 Administrative Permits $300 deposit, plus time and materials.
AFFORDABLE HOUSING REFINANCING PROCESS FEES
S-HM01 Multi-Family Affordable Housing
Refinancing Fee
$1,000 deposit plus time and materials.
S-HS01 Single-Family Affordable Housing
Refinancing Fee
$350 deposit plus time and materials.
S-MCC01 Mortgage Credit Certificate Insurance $300 deposit plus time and materials.
S-RMCC1 Reissued Mortgage Credit Certificate $300 deposit plus time and materials.
S-MCC02 Replacement lost mortgage credit and
reissued mortgage credit certificate
$100 deposit plus time and materials.
S-MCC03 MCC Lender Participation $400 deposit plus time and materials.
S-MCC04 MCC Lender Participation
Annual Renewal
$200 deposit plus time and materials.
EXHIBIT A
LAND DEVELOPMENT FEE SCHEDULE
APPROVED AUGUST 13, 2013
EFFECTIVE OCTOBER 12, 2013
Page 18 of 24
IN-LIEU FEES FOR INCLUSIONARY HOUSING ORDINANCE – APPLIES TO PROJECTS WITH 5
THROUGH 125 UNITS ONLY. FEES ARE NOT ALLOWED ON PROJECTS WITH MORE THAN 125
UNITS EXCEPT FOR FRACTIONAL UNITS
Fees are one option for compliance. See Ordinance for requirements and options for an y project of five or more
units. Fees may be paid on a fraction of a unit if the calculation of the required number of inclusionary units in a
project results in a fraction of a unit.
Developments of 5 or more units must provide 15% of the units as affordable.
For-sale developments must have 80% of the inclusionary units (12% of total units) as affordable to moderate
income households and 20% of the inclusionary units (3% of total units) as affordable to lower income
households.
Rental developments must have 80% of the inclusionary units (12% of total units) as affordable to lower income
households and 20% of the inclusionary units (3% of total units) as affordable to very-low income households.
Refer to Ordinance for income definitions.
Fee amounts are based on the formula in Section 822.4404(b) of the ordinance.
S-IH1 FOR SALE HOUSING Fee equals 12% of total number of units in the
development times $0 plus 3% of total number of
units in the development times $129,163; i.e.,
[(0.12 x total units)($0) + (0.03 x total
units)($129,163) or $3,874.89 per market rate unit.]
S-IH2 RENTAL HOUSING *Rental Housing in-lieu fees are suspended effective
December 15, 2009
S-068 Final Map Check (Major) Deposit of $1,500 plus $25 per lot. 50% surcharge
for accelerated review if available.
Lot line revisions after the first check $25 per
affected lot. Time and materials.
S-069 Parcel Map Check Deposit of $1,500 plus $25 per lot. 50% surcharge
for accelerated review if available.
Lot line revisions after the first check are $25 per
affected lot. Time and materials.
S-070 Record of Survey Check The fee is actual time at the County's fully burdened
hourly rates charged against an initial deposit of
$500, and additional deposits as necessary. The
minimum fee is $200.
EXHIBIT A
LAND DEVELOPMENT FEE SCHEDULE
APPROVED AUGUST 13, 2013
EFFECTIVE OCTOBER 12, 2013
Page 19 of 24
S-072 Public Improvement Plan Check
(Major)
Based on Improvement Value:
$25,000 or less
$25,001-$50,000
More than $50,000
Deposit of:
$1,500 + 8% of improvement value.
$3,500 + 6% of amount over $25,000.
$5,000 + 2% of amount over $50,000.
Time and materials. 50% surcharge for accelerated
review if available.
S-073 Public Improvement Plan Check
(Minor)
Based on Improvement Value:
$25,000 or less
$25,001-$50,000
More than $50,000
Deposit of:
$1,500 + 8% of improvement value.
$3,500 + 6% of amount over $25,000.
$5,000 + 2% of amount over $50,000.
Time and materials. 50% surcharge for accelerated
review if available.
S-074A Public Improvement Plan Check
(LUP)
Based on Improvement Value:
$25,000 or less
$25,001-$50,000
More than $50,000
Deposit of:
$1,500 + 8% of improvement value.
$3,500 + 6% of amount over $25,000.
$5,000 + 2% of amount over $50,000.
Time and materials. 50% surcharge for accelerated
review if available.
S-075 Public Improvement Plan Check
(Development Plan)
Based on Improvement Value:
$25,000 or less
$25,001-$50,000
More than $50,000
Deposit of:
$1,500 + 8% of improvement value.
$3,500 + 6% of amount over $25,000.
$5,000 + 2% of amount over $50,000.
Time and materials. 50% surcharge for accelerated
review if available.
S-076 Drainage Review
(No Improvement Plan)
$700 deposit. Time and materials.
S-076A Condition of Approval Compliance Check (No
Improvement Plan)
$1,000 deposit. Time and materials.
S-076B Improvement Agreement Extension $250 if documents signed and submitted 21 days
before agreement expires, $400 thereafter.
EXHIBIT A
LAND DEVELOPMENT FEE SCHEDULE
APPROVED AUGUST 13, 2013
EFFECTIVE OCTOBER 12, 2013
Page 20 of 24
S-076C Public Improvement Plan
-Bridge/Major Structure
$2,000 + 6% of improvement value.
Time and materials.
S-077 Public Improvement Inspection
(Major)
Based on Improvement Value:
$100,000 or less
$100,001 or more
Deposit of:
$1,500 + 6.5% of improvement value.
$3,500 + 4.5% of amount over $101,000.
Time and materials.
M & T Lab retests at scheduled test prices.
S-077A Public Improvement Inspection -
Bridge/Major Structure
Deposit of:
$1,500 + 7% of improvement value.
Time and materials.
M & T Lab retests at scheduled test prices.
S-078 Public Improvement Inspection
(Minor)
Based on Improvement Value:
$100,000 or less
$100,001 or more
Deposit of:
$1,500 + 6.5% of improvement value.
$8,000 + 4.5% of amount over $100,000.
Time and materials.
M & T Lab retests at scheduled test prices.
S-079 Public Improvement Inspection
(Land Use Permit)
Based on Improvement Value:
$100,000 or less
$100,001 or more
Deposit of:
$1,500 + 6.5% of improvement value.
$8,000 + 4.5% of amount over $100,000.
Time and materials.
M & T Lab retests at scheduled test prices.
S-080A Public Improvement Inspection
(Development Plan)
Based on Improvement Value:
$100,000 or less
$100,001 or more
Deposit of:
$1,500 + 6.5% of improvement value.
$8,000 + 4.5% of amount over $100,000.
Time and materials.
M & T Lab retests at scheduled test prices.
S-081C Public Improvement Plan Review -
Landscaping
$500 deposit plus 2% of improvement value.
Time and materials.
EXHIBIT A
LAND DEVELOPMENT FEE SCHEDULE
APPROVED AUGUST 13, 2013
EFFECTIVE OCTOBER 12, 2013
Page 21 of 24
S-081D Subdivision Monument Check 1 -2 monuments $500.00
3 -5 monuments $750.00
6-9 monuments (per monument) $125.00
10 or more monuments (per monument) $120.00
Time and materials.
S-081E Application Review -
Encroachment Permit (small)
(driveway, sidewalk repairs, small
retaining walls, sewer laterals or water
service by property owner, etc.)
$35.00 fee plus $500 cash bond required for work in
the street.
S-081F Application Review -
Encroachment Permit (large)
Deposit determined by staff based on valuation with
a $300 initial deposit. One hour minimum. Time
and materials at fully burdened hourly rates. Bond
may be required.
S-081G Application Review -
Encroachment Permit (utilities)
Time and materials using fully burdened hourly
rates. One hour minimum.
"Blanket" permit style services are available upon
request for routine utility work within the right of
way.
S-082B Public Improvement Inspection -
Landscaping
$500 plus 8% of improvement value.
Time and materials.
S-082C Encroachment Permit Inspection
(small)
(driveways, sidewalk repairs, small
retaining walls, etc.)
$100 fee. Unpermitted inspection fee is double
inspection and permit fee.
Non-notification for inspection: $100 plus time and
materials.
S-082D Encroachment Permit Inspection
(large)
(If engineering plans required for street
excavation)
Time and materials. One hour minimum.
$300 + $1,000 initial deposit charged at time and
materials.
Non-notification for inspection: $100 plus time and
materials.
S-082E Encroachment Permit Inspection
(utilities)
Time and materials. One hour minimum.
$300 + $1,000 initial deposit charged at time and
materials.
Non-notification for inspection: $100 plus time and
materials.
EXHIBIT A
LAND DEVELOPMENT FEE SCHEDULE
APPROVED AUGUST 13, 2013
EFFECTIVE OCTOBER 12, 2013
Page 22 of 24
S-083 Flood Control District Encroachment Construction Permit Review - Time and materials.
$400 initial deposit.
Inspections - Time and materials. Initial deposit is
the larger of $1,000 or 10% of project valuation.
Temporary Right of Entry - Time and materials.
$400 initial deposit.
Non-inspection Notification for Permitted Work -
$100 plus actual cost of inspection.
S-084A Drainage Permit Application Time and materials against initial deposit
determined by staff.
$100 minimum.
S-084B Drainage Permit Inspection Time and materials against initial deposit
determined by staff.
$100 minimum.
S-085A Miscellaneous Road Permit Application
(house move)
Time and materials. $500 initial deposit.
S-085B Miscellaneous Road Permit Application
(house move inspection)
Time and materials. $500 initial deposit.
S-085C Miscellaneous Road Permit
Application (extra-legal load)
Permit fee set by State. Premium billing service
$100 per year plus $100 security deposit.
S-085D Miscellaneous Road Permit
Application (temporary road closure -
construction)
For-profit applicant $300.00
Not-for-profit applicant $35.00
S-085E Miscellaneous Road Permit
Application (temporary road closure -
special events)
For-profit applicant $300.00
Not-for-profit applicant $35.00
S-085F Miscellaneous Road Permit
Application (extension/modification)
$125 per extension/modification.
S-085G Road Acceptance Plan Review Same as S-072, S-073, S-074A, S-075 as applicable.
Time and materials.
S-085H Road Acceptance Inspection Same as S-077, S-078, or S-080A as applicable.
Time and materials.
EXHIBIT A
LAND DEVELOPMENT FEE SCHEDULE
APPROVED AUGUST 13, 2013
EFFECTIVE OCTOBER 12, 2013
Page 23 of 24
S-086 Street Vacation Review If an in-use area:
Actual time spent at County's fully burdened
hourly rates charged against a $1,700 deposit.
If an unused area:
Actual time spent at County's fully burdened
hourly rates charged against a $900 deposit.
Additional mapping fee if map is required, as
follows:
If map exists:
Actual time spent at County's fully burdened
hourly rates charged against a $1,000
deposit.
If no map exists:
Time and materials against a $2,700 deposit.
S-086A Floodplain Management Compliance $30 per parcel.
S-086B Flood Zone/Base Flood Elevation
Determination
Flood Zone Determination: $50 per lot, $300
maximum for a group of adjacent lots. If site visit
required: $250 plus $50 per lot; $550 maximum for
a group of adjacent lots.
Base Flood Elevation: Time and materials, initial
deposit determined by staff based upon complexity
of project.
S-086C Floodplain Management Permit Application $325 per application. Time and materials.
S-086D Floodplain Elevation Certification $200 per lot.
S-086E Floodplain Map Revision/Amendment Floodplain Map Amendment: $500.
Base map revision, $35 per lot.
Time and materials.
S-087 Assessment District Bond Segregation Segregation initiated by owner or County: $1,000 +
$30 per lot.
Segregation initiated by developer’s engineer: time
and materials. $200 initial deposit. $100 minimum.
S-088 Certificate of Correction Time and materials. $500.00 initial deposit.
S-088A Adopt-a-Road $500 per application.
EXHIBIT A
LAND DEVELOPMENT FEE SCHEDULE
APPROVED AUGUST 13, 2013
EFFECTIVE OCTOBER 12, 2013
Page 24 of 24
S-088B Adopt-a-Park $250 per application.
S-088C Road Name Change (public road) $200 plus $200 installation charge for first
intersection, $50 per intersection thereafter.
S-088D Corner Record Check Fee same as fee for recording a document at the
Recorder's Office.
S-088F Base Map Revision $25 per lot. This fee is waived if the parcel maps or
final maps are submitted on computer disk.
S-088H Amended Map Revision Time and materials plus base map revision fee of
$25 per lot for altered lots. $1,000 initial deposit.
S-088I Records Information Research/
Survey Assistance
Retrieval/Research fee:
$60 per hour, $15 minimum.
Photocopy charges at published rates.
Documents requested to be certified have an
additional charge:
First page: $4.50
Add'l pages: $1.00 each
S-088J Subpoena Services Evidence reproduction: $60 per hour, $15
minimum.
Witness summons: Time and materials plus
mileage, $150 deposit.
S-088L Computer Map and Data Requests Prices to be set using time and materials, including