HomeMy WebLinkAboutMINUTES - 10021984 - 1.11 THE BOARD OF SUPERVISORS OF CONTRA COSTA COUNTY, CALIFORNIA
Adopted this Order on October 2, 1984 by the following vote:
AYES: Supervisors Powers , Fanden, McPeak & Torlakson
NOES: None
ABSENT: Supervisor Schroder
ABSTAIN: None -
SUBJECT: Increase in Contract Contingency Fund and Authorization to
Execute Contract Change Order No. 2 for 1984 Slurry Seal Project, Project
No. 0672-6U2126-84, Central County.
The Public Works Director having recommended that he be authorized
to execute Contract Change Order No. 2 for the 1984 Slurry Seal Project
to compensate the contractor, Valley Slurry Seal Company, Inc., for additional
work as requested and funded by the city of Danville; and
The Public Works Director having further recommended that the
contract contingency fund be increased by $16,800 to provide funds for
said change order; and
The Public Works Director having reported that said change
order and previous change orders collectively exceed $25,000.00.
IT IS BY THE BOARD ORDERE=D that the recommendations of the
Public Works Director are APPROVED.
I hearoby certlty that this is d,rue and correct cony of
an action taken and enlered on the minutes of the
Board of Super0sors on the date shown.
ATTESTED: OCT 21984
Pi-i;L CATCHELCR, Cier% of the Board
of Ss^pervisors an,, CuLmty Adrr,;aisfrator
1
BY ,Deputy
Orig. Dept. Public Works Department