HomeMy WebLinkAboutMINUTES - 01311984 - 1.9 '1HE BOARD OF SUPERVISORS OF CONTRA COSTA COUNTY, CALIFORNIA
Adopted this Order on January 31, 1984 , by the following vote:
AYES: Supervisors Powers , Fanden, Schroder, McPeak, Torlakson
NOES: None
ABSENT: None
ABSTAIN: None
SUBJECT: Authorize Contract Change Order, Assessment District 1980-4, Work
Order No. 5472, San Ramon Area.
The Public Works Director having recommended the initiation of Contract
Change Order No. 17 for Assessment District 1980-4 in the amount of $59,427.56
to compensate the contractor, Gradeway Construction, to landscape the median
islands as required by the amended scope of project approved by the Board on
August 10, 1982, raise water valves in the Safeway project up to finish grade,
install two traffic loops and install additional ice plant along the freeway
off-ramp near Crow Canyon Road.
The Public Works Director having reported that said change order and previous
change orders collectively exceed $25,000.00.
IT IS BY THE BOARD ORDERED that the Public Works Director is AUTHORIZED
to execute the contract change order.
I hereby certify that this Is a true and cornet copy of
ars action taker inc.ertarcd on the minutes of the
Board of on 4h:.-date shown.
AT T E CZ T"'ED:
ant' e;: evk or the Board
Deputy
Orig.Dept.: Public Works Department
Design and Construction Division
cc: County Administrator
County Auditor-Controller
Public Works Director
Design and Construction Division
Accounting Division
Land Development Division
DC.AD19804BO.T1