HomeMy WebLinkAboutMINUTES - 08052008 - C.90 TO: REDEVELOPMENT AGENCY a 'sE 'A' Contra
COS
FROM: JOHN CULLEN, EXECUTIVE DIRECTOR nil
to
DATE: August 5, 2008 7a =' County
SUBJECT: Hookston Station Hazardous Materials Remediation revl
SPECIFIC REQUEST(S)OR RECOMMENDATION(S)&BACKGROUND AND JUSTIFICATION
RECOMMENDATION: C?a
1). AUTHORIZE the Redevelopment Director to reimburse Union Pacific Railroad Company,
on behalf of the County and the Redevelopment Agency, the amount of $213,719.69 for
costs incurred to date on behalf of the County and Agency in the remediation of hazardous
materials in the Hookston Station area pursuant to a November 5, 1997 settlement
agreement between the Union Pacific Railroad Company, the Hookston Group, the County
and the County Redevelopment Agency and an October 1, 1998 Settlement Agreement
between the County, the County Redevelopment Agency and the Hookston Group
(Budgeted Agency Funds); and
2). AUTHORIZE the Redevelopment Director to deposit into the Helix/Union Pacific
Remediation Account with Bank of America an amount not to exceed $750,000 in
fulfillment of obligations set forth in the aforementioned November 5, 1997 and October 1,
1998 settlement agreements.
FISCAL IMPACT: No General Fund revenues are involved. The Redevelopment Agency has
budgeted funds for the current requirement.
BACKGROUND- In 1992, the County using the Redevelopment Agency funds acquired a
portion of a former railroad right-of-way in the Hookston Station area of Pleasant Hill. The right-
of-way was being acquired to preserve the former rail corridor for a future fixed guideway/transit
use-, for the Iron Horse Trail; and for a roadway connection between the Contra Costa Centre
area and Monument Blvd. The Redevelopment Agency was to fund the roadway project;
therefore the Agency funded the property acquisition of behalf of the County, the legal owner of
the subject property. The roadway element has since been dropped from consideration as a
planned roadway. The Agency has funded the construction of the Iron Horse Trail in the subject
corridor and the County continues to preserve the corridor for future fixed guideway/transit.
01
CONTINUED ON ATTACHMENT: ® YES SIGNATURE: 1'/�^ /
ECOMMENDATION OF COUNTY ADMINISTRATOR ❑ RECOM EN ATION OF O RD COMMITTEE
APPROVE ❑ OTHER
SIGNATURE(S):
ACTION OF BOARD ON aIy5y
APPROVED AS RECOMMENDED ® OTHER ❑
VOTE OF SUPERVISORS: I HEREBY CERTIFY THAT THIS IS A TRUE AND
CORRECT COPY OF AN ACTION TAKEN AND
X UNANIMOUS (ABSENT V)0y'Ve ) ENTERED ON THE MINUTES OF THE BOARD OF
SUPERVISORS/AGENCY ON THE DATE SHOWN.
AYES: NOES:
ABSENT: ABSTAIN: ATTESTED
Contact: Jim Kennedy JOHN CULLEN, CLERK OF THE BOARD OF
335-7225 SUPERVISORS/AGENCY SECRETARY
orig: Redevelopment Agency
cc: County Administrator By: a-� Deputy
Auditor-Controller
County Counsel
Via Redevelopment:
Union Pacific Railroad Company
Hookston Group
Goldfarb & Lipman
G:\CDBG-REDEV\redev\Hookston Remediation\Hookston.Remediation.RDA.Order.8.5.08.doc
The seller of the property, a group of individual investors (Dan & Mary Lou Helix, John Hook,
Steven Purcell, and Nancy Ellicock) is referred to as the Hookston Group. The Hookston Group
had acquired the right-of-way between Hookston Road and Mayhew Way as part of a
reversionary transaction from the Southern Pacific Railroad Company. In the County's
acquisition of the right-of-way steps were taken to protect the County from liability related to the
removal of identified surface and sub-surface contaminants.
Subsequent to the County's acquisition of the right-of-way chlorinated solvents
(trichloroethylene) were determined to exist in the groundwater. Prior testing had not revealed
their presence. Some of the contamination is suspected to have come from a prior tenant of
the property during the tenure of Southern Pacific's ownership. The County/Agency joined the
Hookston Group in filing suit against Southern Pacific related to the groundwater
contamination. Effective in November, 1997, the County, the Agency, the Hookston Group,
and Union Pacific Railroad Company (now the successor to Southern Pacific) entered into a
Settlement Agreement to resolve the federal lawsuit. In general, the Settlement Agreement
assigned financial responsibility for remediation to the parties as shown in Table 1 below:
Table I
Remediation Cost Amount/Party
1 The first $3 Million $1.5 Million — Union Pacific
$1 .5 Million — Hookston Group
2 The next $1 million $500,000 — County/RDA
(total $4 million) $500,000 - Union Pacific
3 The next $1 million $500,000 — County/RDA
(total $5 million) $500,000 — Union Pacific
4 The next $1 million $250,000 — County/RDA
(total $6 million) $250,000 - Hookston Group
$500,000 - Union Pacific
5 The next $1 million $250,000 — County/RDA
(total) $7 million $250,000 - Hookston Group
$500,000 - Union Pacific
6 The next $1 million $250,000 — County/RDA
(total $8 million) $250,000 - Hookston Group
$500,000 - Union Pacific
7 The next $1 million $250,000 — County/RDA
(total $9 million) $250,000 - Hookston Group
$500,000 - Union Pacific
8 The next $1 million $250,000 — County/RDA
(total $10 million) $250,000 - Hookston Group
$500,000 - Union Pacific
G:\CDBG-REDEVVedev\Hookston Remediation\Hookston.Rem ediation.RDA.Order.8.5.08.doc
The parties owning the property during the time period contaminants are suspected to
have been introduced to the groundwater were given the primary role in funding
remediation. The County was assigned a subordinate role in funding remediation. The
County, the County Redevelopment Agency, and the Hookston Group also entered into an
additional October 1, 1998 Settlement Agreement to further clarify remediation
funding responsibilities as outlined above.
The parties have engaged in a process to develop and obtain regulatory agency approval
of a remediation plan. The remediation plan has been approved by the Regional Water
Quality Control Board, and is being implemented.
Based on records available to County staff, as of June 28, 2008, a total of $4,209,364.96
has been expended for hazardous materials remediation related to Hookston Station.
Costs incurred to date have been paid from an escrow fund jointly established and funded
by contributions from Union Pacific and the Hookston Group as described in Table 1
above. That amount referenced in recommendation No. 1 will reimburse Union Pacific for
an amount advanced into the remediation escrow account on behalf of the County to cover
current/ongoing cost up to an aggregate of $4 million. As remediation work proceeds the
County/Redevelopment Agency will have a continuing obligation to contribute an additional
$750,000 (obligation line item #3 and #4 from Table 1). Recommendation No. 2 will permit
staff to respond to anticipated cash calls over the next 12 months to deposit funds required
by the Settlement Agreement into the joint escrow funds. The work completed to-date has
permitted the parties to achieve approval from the State Water Resources Control Board,
and to complete initial remediation work. The remediation work will be ongoing for the next
several years. Completion of the remediation work will be determined when specified
threshold levels of contamination have been achieved. Once installed, the remediation
work will largely consist of monitoring and reporting, with some equipment maintenance.
Current estimates suggest total remediation cost will be upwards of $10 million total. Costs
paid to date are summarized in the table below:
Table 2
TO AMOUNT FOR
Center Technology
Environmental Health $414,516.58 Human Health Risk Assessment
Environmental Resource
Management (ERM) $2,733,080.24 Primary Project Consultant
Environmental West Exploration $42,885.30 Soil and Groundwater sampling
Soil and Groundwater
Severen Trent Labs $180,280.48 sampling analyses
State Water Resources Control Board $359,919.41 Primary Oversight Agency
Vironex $252,399.71 Sampling
Other Misc. Consultants $222,604.24 Misc. Consultants
Payments to local property owners $3,679.00 Vapor intrusion electrical
cost reimbursement
G:\CDBG-REDEV\redev\Hookston Rem ediation\Hookston.Rem ediation.RDA.Order.8.5.08.doc