TO: BOARD OF SUPERVISORS .: l.` o
County
FROM: Dennis M. Barry, AICP
Community Development Director '
DATE: September 26, 2006
SUBJECT: REQUEST FROM AMBROSE RECREATION AND PARK DISTRICT FOR PARK
DEDICATION FUNDS TO UPGRADE THE SWIMMING POOL AT AMBROSE PARK IN
BAY POINT
SPECIFIC REQUEST(S) OR RECOMMENDATIONS(S) & BACKGROUND AND JUSTIFICATION
RECOMMENDATION
AUTHORIZE the Auditor-Controller to issue a warrant in the amount of $25,000 to the
Ambrose Recreation and Park District from the Park Dedication Trust Fund account listed
below to upgrade the swimming pool at Ambrose Park in Bay Point.
Account Number Amount
8136370031411 $25,000
FISCAL IMPACT
None (100% Park Dedication Trust Account)
CONTINUED ON ATTACHMENT: X YES SIGNATURE:
✓RECOMMENDATION OF COUNTY ADMINISTRATOR RECOMMENDATION OF 71RD
COMMITTEE APPROVE OTHER
SIGNATURE(S):
ACTION OF BOA DON 9 2 APPROVED AS RECOMMENDED ✓ OTHER_
VOTE OF SUPE VISORS
I HEREBY CERTIFY THAT THIS ISA
V UNANIMOUS (ABSENT ) TRUE AND CORRECT COPY OF AN
AYES: NOES: ACTION TAKEN AND ENTERED ON THE
ABSENT: ABSTAIN: MINUTES OF THE BOARD OF
SUPERVISORS ON THE DATE SHOWN.
Source: Bob Calkins, CDBG Program Manager
(925) 335-7220
ATTESTED����ZW6
Orig. Dept. Community Development - CDBG JOHN CULLEN: CLERK OF
cc: County Administrator THE BOARD OF SUPERVISORS
Auditor - Controller AND COUNTY ADMINISTRATOR
Public Works - Whan
BY , DEPUTY
BACKGROUND /REASONS FOR RECOMMENDATIONS
The Ambrose Recreation and Park District (Ambrose) requests park dedication funds to
help finance the cost of upgrading the swimming pool at Ambrose Park located at 125
Memorial Way in Bay Point. It is the policy of the County to utilize park dedication funds to
meet local park needs. Staff has determined that this action is consistent with that policy
and is consistent with Ambrose's Park Master Plan.
Ambrose Park is designed as a community park and consists of open play fields, baseball
field, soccer field, two play structures, BBQ pits, multiple picnic areas, a pavilion for rentals,
swimming pool, and tennis courts. The swimming pool is in need of upgrading including
installing a new lining over the existing fiberglass to reduce the likelihood of leaks and
installing a new pump and filtration system to keep the pool sanitary and safe. According
to Ambrose, the proposed project will restore the swimming pool to its full functioning
potential. The total cost of the project is estimated at $65,000. Ambrose has been
awarded a grant from the Stewardship Council in the amount of $40,000 to help finance
the proposed project.
It is expected that the proposed project will be completed by the summer of 2007. There
are sufficient funds in the appropriate Park Dedication Trust account to approve this
request.