THE BOARD OF SUPERVISORS OF CONTRA COSTA COUNTY, CALIFORNIA
Adopted this Order on November 6, 1984 by the following vote:
AYES: Supervisors Fanden, Schroder, McPeak and Torlakson
NOES: None
ABSENT: Supervisor Powers
ABSTAIN: None
SUBJECT: In the Matter of Awardof Contractor Ygnacio Val ley KoNd
Slide Repair, Project No. 0671-6R6714-83, Federal Project No. ER-1116(5) ,
Walnut Creek-Concord Area.
Bidder Total Amount Bond Amounts
Heide and Williams, Inc. $3689343.00 Payment $184,171.50
P. 0. Box 2007 Faith. Perf. $3689343.00
Napa, California 94558
Kiewit Pacific Co.
Fanfa-Mulloy, Inc.
Gabe Mendez, Inc.
Ferma Corporation
Joe Foster Excavating
C & G Contractors
Independent Construction
Crystal Creek
Huntington Bros. , Inc.
Oliver de Silva
Bay Cities Paving and Grading
MJM Engineering
The above-captioned project and the specifications therefor being
approved, bids being duly invited and received by the Public Works Director;
and
The bidder listed first above submitted with his bid DB and WBE
information stating that the required goals would be met. A review of
this information by the Public Works Department indicated that an additional
submittal of information was required from the contractor adding to his
WBE goal . This additional information was submitted and approved following
the procedure set forth in the contract specifications; and
The Public Works Director recommending that the bid listed first
above is the lowest responsible bid and this Board concurring and so
finding;
IT IS BY THE BOARD ORDERED, that the contract for the furnishing
of labor and materials for said work is awarded to said first listed
bidder at the listed amount and at the unit prices submitted in said
bid; and that said contractor shall present two good and sufficient surety
bonds as indicated above; and that the Public Works Department shall
prepare the contract therefor.
IT IS FURTHER ORDERED that, after the contractor has signed the
contract and returned it together with bonds as noted above and any required
certificates of insurance or other required documents, and the Public
Works Director has reviewed and 'round Lhem Lu be 5ui i iLieilt, Lha rubl 1s
Works Director is authorized to sign the contract for this Board.
IT IS FURTHER ORDERED that, in accordance with the project specifi-
cations and/or upon signature of the contract by the Public Works Director,
any bid bonds posted by the bidders are to be exonerated and any checks or
cash submitted for bid security shall be returned. 000243
Orig.Dept.: Public Works Department, Design/Const. Div.
cc: County AdministratorIhere!!ycertify S11Mthis[!atrue and correct COPY of
County Auditor-Controller an action taken and entered on the minutes of the
Public Works Director Board of Supervisors on the date shown.
Design and Construction Division ATTESTED: NOV 6 1984
Accounting Division PHIL BATCHELOR,Clerk of the Board
Contractor of Supervisors and County Administrator
DC:YGNACIOBO.T11
By � � , Deputy