To: BOARD OF SUPERVISORS r � CONTRA COSTA
COUNTY
From: William B.Walker, M.D.
Health Services Director
Date: July 279 2004
Subject: EXTENSION OF EMERGENCY DECLARATION AND AUTHORIZATION OF THE COUNTY
HEALTH DEPARTMENT IN SUPPORT FOR NEEDLE EXCHANGE PROGRAMS
SPECIFIC REQUEST(S)OR RECOMMENDATION(S)cls BACKGROUND AND JUSTIFICATION
Recommendation:
CONTINUE with the emergency action originally taken by the Board on December 14, 1999 based on
the increasing/epidemic number of AIDS/HIV and Hepatitis C cases among injection drug users in.
Centra Costa County.
Backoroun+d:
Continued Needfor Emergency
The spread of disease, particularly HIV and Hepatitis C, through the sharing of needles continues to be
a grave concern in Contra Costa County. 30% of all people living with AIDS in Contra Costa were
infected by injection drug use with the highest number of AIDS cases in West County. As of December
1997, Richmond had the highest cumulative incidence of AIDS (4.8 per 1000 population) among
Contra Costa cities, with at least 50 cases. Injection drug use was the estimated mode of infection
among 40% of all individuals diagnosed with AIDS in Richmond. Among African Americans diagnosed
with AIDS in Richmond 1982-1998 53%were most likely infected through injection drug use.
Contra Costa Health Services does not currently provide needle exchange services (it is prohibited from
doing so absent a declared public health emergency). CCHS does provide services focused on injection
drug users including: I-HIVIAIDS Outreach and Education, 2-HIV antibody testing, 3-Substance
Abuse Treatment, 4-Health. on Wheels Van, and 5-Substance Abuse Counseling and Treatment for
HIV-infected clients.
CONITINUED ON ATTACHMENT: YIDS SIGNATURE: �• 1 '
<.---RECOMMENDATION OF COUNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
'PROVF OTHER
SIGNATURE(S): <,j
ACTION OF BO.A` N l APPROVED A5 RE.CONEAENDED ~- !;'�"'
VOTE OF SUPERVISORS
I HEREBY CERTIFY THAT THIS IS A TRUE
UNANIMOUS (ABSENT AND CORRECT COPY OF AN ACTION TAKEN
AYES: NOES: AND ENTERED ON THE MIN1:I MS OF THE BOARD
AYES: NOES: OF SUPERVISORS ON THE DATE SHOWN.
ABSENT: ABSTAIN:
. ATTESTED
JOHNS STEN, CLERK OF THE BOARD OF
SUPERVISORS AND COUNTY ADMINISTRATOR
Contact Person: Wendel.Brunner, MD. 313-6712
CC: Health Services Director
Public Health Administration
BY - - , DEPUTY
Board of Supervisors Page 2
Emergency Declarationfor Support of Needle Exchange Programs
Exchange Works, a community-based needle "change service currently in operation in Contra Costa
currently distributes clean needles on a one-to-one basis. Their volunteer staff currently exchange
5,000 needles per week at two sites. There are no established needle exchange program in East or
Central County.
PROGRESS SINCE EMEAGENCYDECLARA TION ON DECEMBER 14, .1999
At the Board of Supervisors December 14, 1999 meeting, CCHS was directed to take four actions. As
of January 7, 2000'the following has been completed:
CCHS has entered into discussions with Exchange Works in West County.
Supplies for the ongoing provision of*the services have been identified.
CCHS staff have been identified to assist with the provision of information and referrals.
• Documentation forms are being reviewed and revised as necessary to ensure that specific
information is available to the Board.
• Planning for an East County process will begin later this quarter after the preliminary process in
West County is completed.
Additional Background Text for Continuous Emergency Declaration
for Support of Needle Exchange Programs
Public Health Division,AIDS Program
Contact: Christine Leivermann, 5-6786
• February 11, 2003 —Board order submitted to recommend and accept"The Status of HIV
Prevention Efforts in Contra Costa County"report to the Board of Supervisors.
• February 26, 2003 —report submitted to the Family and Human Services Committee, "Options
for Continuing Needle Exchange for HIV Prevention" .
• March 3, 2003 —report submitted to the Family and Human Services Committee, "Needle
Exchange Follow-up Report—Strategies to Support the Non-Direct Costs of Needle
Exchange".
• April 16,2003 —report submitted to the Family and Human Services Committee, "Activities to
Maintain Threshold Needle Exchange Services in Contra Costa County" (4/21/03).
• July 28, 2003 —report submitted to the Family and Human Services Committee, "Further
Options for Continuing Needle Exchange for HIV Prevention".
• September 9, 2003 —Board of Supervisors accepted Health Services reports of April 16 and
July 28, and approved a one-year contract with Community Health Empowerment(CHE) to
provide needle exchange and HIV prevention services; Contract#22877 with Opportunity West
(fiscal agent for CHE); contract term 9/l/03 —8/31/04.
Bo:bos needle exchange update 304
To: BOARD OF SUPERVISORS CONTRA COSTA
. :_ :. COUNTY
From: William B.Walker, M.D. � .
Heath l s Director i
Services e
Date: August 10, 2004
Subject: Extension of Emergency Declaration Regarding Homelessness
SPECIFIC REQTIEST(S)OR RECOMMENDATIONS)& BACKGROUND AND JUSTIFICATION
Recommendation:
CONTINUE with the emergency action originally taken by the Board on November 16, 1999 regarding
the issue of homelessness in Contra Costa County.
Backsround:
Government Code Section 8634 required that, for a body that meets weekly that the need to continue
the emergency declaration be reviewed at least every 14 days until the local emergency is terminated. In
no event is the review to take place more than 21 days after the previous review.
With the continuing inclement weather and no additional resources having been able to be placed on he
to assist in sheltering homeless individuals and families, it is appropriate for the Board to continue the
declaration of a local emergency regarding homelessness.
On November 16, 1999, the Board of Supervisors declared a local emergency, pursuant to the
provisions of Government Code Section 8634, on homelessness in Contra Costa County. This local
emergency was extended on August 17, 2004.
CONTINUED ON ATTACHMENT: NO SIGNATURE
"'RECOMMENDATION OF COUNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
,,,-APPROVE OTHER
rte'"�,�,✓ .-�,%
SIGNATURE(S):
ACTION OF B DO � 7 ' APPROVED AS RECOMMENDED -0TttEK
VOTE OF SUPERVISORS
UNANIMOUS ABSENT ` i HEREBY CERTIFY THAT THIS IS A TRUE
( ) AND CORRECT COPY OF AN ACTION TAKEN
AND ENTERED ON THE MINUTES OF THE BOARD
AYES: NOES: OF SUPERVISORS ON THE DATE SHOWN.
ABSENT: ABSTAIN:
Contact Person: Wendel Brunner, M.D. 313-6712 OLJ4,&W
f
ATTESTED
CC: Health Services Administration JOHN OWEETEN, CLERK OF THE BOARD OF
Public Health Administration SUPERVISORS AND COUNTY ADMINISTRATOR
BY . I 'I ? , DEPUTY
TO: BOARD OF SUPERVISORS �. CONTRA
FROM: BARTON J. GILBERT, DIRECTOR OF GENERAL SERVICES COSTA
DATE: AUGUST 10, 2004 COUNTY
SUBJECT: CONTINUATION OF EMERGENCY ACTION TO FACILITATE
COMPLETION OF THE CONTRA COSTA COUNTY ANIMAL
SERVICES FACILITY PROJECT AT 4800 IMHOFF PLACE,
MARTINEZ (WH415F)
SPECIFIC REQUEST(S)OR RECOMMENDATION(S)&BACKGROUND AND JUSTIFICATION
RECOMMENDATION
DETERMINE that there is a need to continue the emergency action taken by the Board on April 6,
2004 pursuant to Public Contract Code Sections 22035 and 22050 to complete the Contra Costa
County Animal Services Facility at 4800 Imhoff Place, Martinez for the Animal Services Department.
FINANCIAL IMPACT
Costs will be covered by funds deducted from the contract balance for the remaining work. To the
extent that the contract funds are not sufficient to cover all expenses, the County presumably will be
able to recover the additional amount from the contractor, Dennis J. Amoroso Construction Co., Inc.
("DJA") and/or their surety, Travelers Casualty and Surety Company of America ("Travelers").
BACKGROUND
1. On July 9, 2002, the Board awarded the construction contract for the Contra Costa County
Animal Services Facility, located at 4800 Imhoff Place, Martinez, to DJA of San Rafael,
California. The contract required completion within 430 calendar days from the starting date.
On July 24, 2002 a notice to proceed was issued with a starting date of August 5, 2002 and a
contract completion date of October 9, 2003.
2. DJA has not performed in a timely manner and has failed to comply with the scheduling and
completion requirements of the contract. As a result of DJA's performance delays, the project
presently is over five months late and only about 77% complete.
3. The County repeatedly has notified DJA and Travelers orally and in writing about the lack of
progress and concerns with the project schedule. For an extended period of time, DJA and its
subcontractors have failed to supply sufficient materials and workers to complete the project,
and DJA has failed to comply with the scheduling and completion requirements of the contract,
as documented by the following:
CONTINUED ON ATTACHMENT: X YES SIGNATURE:
RECOMMENDATION OF COUNTY ADMINISTRATOR -RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF BOAR6 O # rrr•L[ APPROVED AS RECOMMENDED R"
iv
VOTE OF SUPERVISORS
UNANIMOUS(ABSENTd )
AYES: NOES:
ABSENTS: ABSTAIN:
MEDIA CONTACT:BARTON J.GILBERT(313-7100)
Originating Dept.:General Services Department
cc: General Services Department I HEREBY CERTIFY THAT THIS IS A TRUE Capital Projects Management Division AND CORRECT COPY OF AN ACTION TAKENAND ENTERED ON THE MINUTES OF THE BOARD
Accounting OF SUPER VI ORS ON THE DATE SHOWN.
CPM File: 250-0003/C.1.1
250-0003/A.5 ATTESTED .
County Administrator's Office JOHNf
TEN'CLER OF THE BOARD OF SUPERVISORS
County Counsel AND COUNTY ADMINISTRATOR
Auditor Controller I
Animal Services Department(via CPM) B1 K.-C V .,s(F i - DEPUTY
H:\2000\250000=01-003299b.doc LDR:tb Page 1 of 3 M382(10/88)
CONTINUATION OF EMERGENCY ACTION TO August 10, 2004
FACILITATE COMPLETION OF THE CONTRA COSTA
COUNTY ANIMAL SERVICES FACILITY PROJECT AT
4800 IMHOFF PLACE, MARTINEZ
September 16, 2003 letter to DJA: Letter requested that DJA take all measures (manpower,
scheduling, material procurement, etc.) necessary to prosecute the work in a diligent manner
and regain lost time.
October 9_2003 letter to DJA: Letter notified DJA that the project was substantially behind
schedule and that no firm completion date had been established by DJA, requested that DJA
provide a recovery plan, and warned DJA that the County reserved its right to assess liquidated
damages for delays.
November 3 2003 letter to DJA: Letter notified DJA that, due to financial, scheduling, and other
problems under DJA's control, the project was significantly behind schedule and that
subcontractors were not performing and reminded DJA of the continuing costs to County
operations, including existing lease payment obligations and administrative costs.
December 22 2003 letter to DJA: Letter informed DJA that the County had not received an
approved schedule from DJA.
Despite the above notices, DJA has failed to take appropriate action to supply sufficient labor
and materials to the project, to provide updated schedules, or to comply with the scheduling and
completion requirements of the contract. These defaults continue up to the present.
4. Since August 2003, DJA generally has failed to pay bills for labor and materials on the project.
As a result, over 26 stop notices totaling more than $1.7 million have been filed on the project.
Other subcontractors/suppliers have indicated that they also have not been paid and will be filing
stop notices. The numerous stop notices have interfered with the project funding and have
made it difficult for the County to arrange payment to necessary subcontractors and suppliers.
In addition, over the past six months, many subcontractors and suppliers have slowed or cut off
the supply of labor and materials to the project, causing the work on the project to progress
erratically and at a slow pace. DJA and Travelers have failed to take effective action to release
the stop notices or to deal with the serious financial problems.
5. On January 14, 2004, the County received a letter from Travelers demanding that the County
release no further contract funds, including retention, without Travelers' advance, written
consent. The notice had the effect of freezing all payments on the project, including those to
necessary subcontractors and suppliers. In addition, on February 27, 2004, the County received
a writ of attachment from Travelers attempting to take possession of all contract funds.
6. On January 21, January 30, February 6, February 25, and March 16, 2004, the County sent
letters or email messages to Travelers demanding that Travelers take prompt action to pay
critical subcontractors and suppliers, to restore funding to the project, and to provide a qualified
replacement contractor to complete the remaining contract work. On March 17, 2004, the
County received a letter from DJA advising that DJA had no objection to Travelers providing a
replacement contractor and had urged Travelers to take that action with the County's project.
Despite the numerous demands to Travelers, Travelers has failed to take any meaningful action
except the one-time issuance of checks to nine subcontractors and suppliers.
7. On March 15, 2004, the County gave a written, ten-day notice to DJA and Travelers pursuant to
the contract provisions. The notice listed five defaults, including the ones described above,
demanded that DJA correct the defaults by March 25, 2004, and warned that DJA was in
material default under the contract and that failure to timely correct the defaults would lead to
termination of DJA's contract rights. Despite the notice, DJA and Travelers failed to correct the
defaults by the March 25 deadline and continue in their failure to supply sufficient labor,
materials, and funding to complete the project.
HA2000\2500003\00L003299b.doc LDR:tb Page 2 of 3 M382(10188)
CONTINUATION OF EMERGENCY ACTION TO August 10, 2004
FACILITATE COMPLETION OF THE CONTRA COSTA
COUNTY ANIMAL SERVICES FACILITY PROJECT AT
4800 IMHOFF PLACE, MARTINEZ
8. The above-described defaults effect the entire project and present a potential threat to the
animals presently housed in the existing Martinez Animal Shelter. Given the seriousness of the
defaults and DJA's repeated failure to take timely action to deal with them, it was recommended
that the Board declare DJA in material breach under its construction contract and terminate
DJA's rights under the contract. It was also recommended that the Board authorize County
Counsel to pursue appropriate legal action, including the negotiation and execution of e takeover
agreement or similar agreement with Travelers and the filing and prosecution of lawsuits against
DJA, Travelers, and any other responsible parties.
9. The existing Martinez Animal Shelter is obsolete and subject to overcrowding, and it was
essential that the new facility be complete and occupied as soon as possible. To deal with this
imminent threat to public safety and welfare, and to minimize the adverse impact of extended
rent and possible rent increases for the existing Martinez Animal Shelter, it was recommended
that the Board delegate to the General Services Director or his designee the authority to respond
to the emergency by proceeding with the project in the most expeditious manner possible,
without the need to re-solicit competitive bids.
10. Consequently, on April 6, 2004 (Agenda item C.105), the Board 1) found that an emergency
exists, 2) delegated authority to the General Services Director to proceed in the most
expeditious manner to complete the project at 4800 Imhoff Place, Martinez for the Animal
Services Department and enter into one or more contracts therefore, and 3) directed the General
Services Director to make reports to enable the Board to review the emergency actions and to
determine that there is a need to continue the action.
11. The condition that the Board found to be an emergency on April 6, 2004 continues to exist.
Therefore, it is necessary to continue the emergency action previously taken by the Board so
that the work can be completed in the shortest time possible.
12. Contracts for the emergency work are being negotiated and will be reported to the Board after
the scope of work and schedules have been confirmed.
H:12000\2500003100L003299b.doc LDR:tb Page 3 of 3 M382(10/88)
TO: BOARD OF SUPERVISORS Contra
* pN'
FROM: JOHN SWEETEN, k
COUNTY ADMINISTRATOR Costa
DATE: August 10, 2004 County
SUBJECT: CONTINUATION OF EMERGENCY RELATIVE TO JUVENILE HALL
ADDITION PROJECT (WH228F)
TZ
SPECIFIC REQUEST(S)OR RECOMMENDATION(S)&BACKGROUND AND JUSTIFICATION
B=MMENDATIONS:
DETERMINE there is a need to continue with the emergency action originally taken by the Board on
November 18, 2003 on the Juvenile Hall Addition Project(WH228F).
FISCAL IMPACT:
The financial impact remains as stated to the Board on November 18, 2003.
BACKGffQUND:
On 11118103 the Board acknowledged that an emergency exists related to the completion of the
Juvenile Hall Addition Project (WH228F) and that the emergency will not permit a delay resulting
from competitive re-solicitation of bids, and delegated to the County Administrator, or designee,
the authority to proceed in the most expeditious manner to complete the project and to enter into
one or more contracts therefor, without the need to re-solicit competitive bids.
CONTINUED ON ATTACHMENT: ,,,,,YES SIGNATURE:
------,----»
�c�UTTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE RECOMMENDATION
APPROVE OTHER
---- ----.----ACTION OF BOARD
aN APPROVE AS RECOMMENDED
G C
f j
VOTE OF SUPERVISORS I HEREBY CERTIFY THAT THIS IS A TRUE
AND CORRECT COPY OF AN ACTION TAKEN
r UNANIMOUS(ABSENT 1) 1 AND ENTERED ON THE MINUTES OF THE
BOARD OF SUPERVISORS ON THE DATE
AYES:_ NOES: SHOWN.
T
ABSEN . ABSTAIN:
ATTESTED
CONTACT: JOHN SWEETE ,CLERK OF THEIBOA tD OF SUPERVISORS
AND COUNTY ADMINISTRATOR
CC: County AAministrator
County Probation Officer
County Counsel
URS-Mark Gaul(via CAO)
t
BY :L* A01~ DEPUTY
TO: BOARD OF SUPERVISORS
FROM: MAURICE M. SHIU, PUBLIC WORKS DIRECTOR
DATE: AUGUST 10, 2004
SUBJECT: CONTINUE the emergency action originally taken by the Board of
Supervisors on August 5, 2003 regarding the construction of the Asbury
Graphite Wastewater System as recommended by the Public Works
Director, Hercules area. [SCH No. 95043029 (Contra Costa Transportation
Authority Funds, 100%) (District II) Project No.: 4660-6X4152.
SPECIFIC REQUEST(S)OR RECOMMENDATION(S)&BACKGROUND AND JUSTIFICATION
1. Recommended Action:
DETERMINE that there is a need to continue the emergency action taken by the
Board of Supervisors on August 5,2003, pursuant to Public Contract Code Sections
22035 and 22050, to construct a wastewater system for Asbury Graphite, Hercules
area.
Continued on Attachment: X SIGNATURE: -)La
RECOMMENDATION OF COUNTY ADMINISTRATOR
T_RECOMMENDATION OF BOARD COMMITTEE
:'PROVE _OTHER
SIGNATURE(S):
ACTION OF BOA N 2APPROVED AS RECOMMENDED GTHElt—
r
P
I hereby certify that this is a true and correct copy of an
VOTE OF SUPERVISORS action taken and entered on the minutes of the Board
UNANIMOUS (ABSENTnone-- } of Supervisors on the date shown.
AYES: NOES:
ABSENT: ABSTAIN:
MC:PE:tb ATTESTED: �.
G:\GrpData\Const\6012004�AsburyLeachfield-Emergency.doc JOHN SWEETEN Clerk of th& Board of Supervisors
Orig.Div:Public works(Construction) and County Administrator
Contact: M.Carlson 313-2321
cc: M.Hollingsworth,Design
K.Laws,Real Property By Deputy
SUBJECT: CONTINUE the emergency action originally taken by the Board of
Supervisors on August 5, 2003 regarding the construction of the Asbury
Graphite Wastewater System as recommended by the Public Works
Director, Hercules area. [SCH No. 95043029] (Contra Costa Transportation
Authority Funds, 100%) (District 11) Project No.: 4550-6X4152.
DATE: AUGUST 10, 2004
PAGE: 2
I1. Fiscal Impact:
The total estimated contract cost is $400,000,which is 100% reimbursable from the
Contra Costa Transportation Authority.
Ill. Reasons for Recommendations and Background:
A. On August 5, 2003, the Board of Supervisors declared an emergency and
authorized the Public Works Director to proceed in the most expeditious manner
to construct the Asbury Graphite Wastewater System.
B. Repair status:
The project was awarded to Ceiik Engineering Corporation of Carmichael.
The construction began on June 14, 2004. It is expected the construction to
be completed by the middle of August. This project is approximately 70%
complete.
IV. Consequences of Negative Action:
Non-concurrence of the above recommendation will delay replacement of the
wastewater system until 2005 resulting in the increased potential for the failure of
the existing system, which would cause effluent contamination of the surrounding
area and off-hauling up to 750 gallons per day of effluent to an appropriate disposal
facility.