HomeMy WebLinkAboutMINUTES - 09242002 - C.86 TO: BOARD OF SUPERVISORS
FROM: MAURICE M. SHIU, PUBLIC WORKS DIRECTOR
DATE: September 24, 2002
SUBJECT: CONTINUE the emergency action originally taken by the Board of
Supervisors on June 4, 2002 regarding the repair of the erosion along
Carquinez Scenic Drive, as recommended by the Public Works Director,
Crockett area. [CDD-CP # 02-02] (District Il) Project No.: 0672-6U2526-02
SPECIFIC REQUEST(S)OR RECOMMENDATION(S)&BACKGROUND AND JUSTIFICATION
I. Recommended Action:
DETERMINE that there is a need to continue the emergency action taken by the
Board of Supervisors on June 4, 2002, pursuant to Public Contract Code Sections
22035 and 22050, to repair the erosion along Carquinez Scenic Drive, Crockett
area.
Continued on Attachment: X SIGNATURE: � �
_, tCOMMENDATION OF COUNTY ADMINISTRATOR
RECOMMENDATION OF BOARD COMMITTEE
�; APPROVE OTHER
t
SIGNATURE(S): '4 '
ACTION OF BOARON September 24, 2002 APPROVED AS RECOMMENDED X OTHER
VOTE OF SUPERVISORS
X UNANIMOUS (ABSENT NOM }
AYES: NOES: I hereby certify that this is a true and correct copy of an
ASSENT: ABSTAIN: action taken and entered on the minutes of the Board
of Supervisors on the date shown.
NL:mp
G:\GrpData\Const\BO\2002\iO-SeptembeACarquinez
Scenic Drive Slide Repair Emerg Cont 5.doc
Grig.Div:Public Works(Design) ATTESTED: SePtesnber 24> 2002
Contact: B.Louis-313-2245 JOHN SWEETEN, Clerk of the Board of Supervisors
c: M.Hollingsworth,Design and County Administrator
Public Works Accounting
By , L'0 s✓ , Deputy
SUBJECT: CONTINUE the emergency action originally taken by the Board of
Supervisors on June 4, 2002 regarding the repair of the erosion along
Carquinez Scenic Drive, as recommended by the Public Works Director,
Crockett area.
[CDD-CP # 02-021 (District ll) Project No.: 0672-6U2526-02
DATE: September 24, 2002
PACE 2
II. inancialIMpact:
The total estimated contract cost is$260,000,funded by Local Road Funds(100%).
III. Reasons for Recommendations and Background:
A. Can June 4, 2002, the Board of Supervisors declared an emergency and
authorized the Public Works Director to proceed in the most expeditious manner
to repair the erosion and failed pavement.
B. Repair status:
The project was awarded to Upgrade Construction of Danville; construction
began August 26, 2002.
This project is approximately 15% complete.
IV. Consequences of Negative Action:
Non-concurrence of the above recommendation will significantly delay repair of the
roadway, prolonging impacts to local access and could result in the loss of the entire
traveled way.