HomeMy WebLinkAboutMINUTES - 09102002 - C1-C5 TO: BOARD OF SUPERVISORS
FROM: MAURICE M. SHIU, PUBLIC WORKS DIRECTOR
DATE: September 10, 2002
SUBJECT: Approve Project Contingency Fund Increase for the Livorna Road AC Overlay Project,
Project No. 0662-684236-02, Alamo area.
Specific Request(s)or i;tecommendation(s)&Background&Justification
I. Recommended Action:
APPROVE project contingency fund increase of $18,000 for a new total of $44,800 effective
September 10, 2002 in order to compensate the contractor, Top Grade Construction, Inc. for
unforeseen extra work associated with paving fabric installation and additional traffic control
services.
II. Financia! Impact:
The project contingency funds are currently insufficient to cover the inFreased cost.The increase in
contingency funds will be funded by Measure C.
Continued on attachment: X yes SIGNATURE:
RECOMMENDATION OF COUNTY ADMINISTRATOR
RECOMMENDATION OF BOARD COMMITTEE
= APPROVE OTHER J
SIGNATURE(S):
ACTION OF BOA ON: Sent _ in 20[)9. APPROVED AS RECOMMENDED xx OTHER
.r
VOTE OF SUPERVISORS
xx UNANIMOUS (ABSENTNone}
AYES: NOES: I hereby certify that this is a true and correct copy of an
ABSENT: ABSTAIN: action taken and entered on the minutes of the Board of
Supervisors on the date shown.
Contact: Mike Carlson,(925)313-23201
Orig.Div.: Pw(CATTESTED: Septernbe
cc: County Administratortor r 10, 200Auditor-Controller JOHN SWEETEN, Clerk of the Board of Supervisors and
Public works County Administrator
- Accounting
- Construction.R.Bruno
- Design
Contractor By_ Deputy
RB:tb
G:\GRPDATAICONST\BO\20C210-S EPTEMBER\APPROVECONTI NG EN CYLEVORNARDAC.DOC
SUBJECT: Approval of contract contingency fund increase for the Livorna Road AC Overlay Project. Project No.0662-
6R4236-02,Alamo area
DATE: September 10, 2002
PAGE 2 OF 2
1111!. Reasons for Recommendations and Background:
Additional funding is needed to pay the contractor for the extra work outside the original contractual
agreement and for the increased bid item quantities. At the request of Public Works Department,
the contractor installed pavement fabric on Livorna Road, which was not part of the original scope
of work. The work was done on an agreed price generating Change Order No. 3. Consequently,the
additional funding will cover the increase in bid item quantities for the pavement repair and the
additional crack filling performed within County limits.As of a result,the cost for the work exceeded
the allowable contingency fund amount. Approval of an increased contingency fund amount is
necessary to compensate the contractor for the work.
IV. Consequences of Negative Action:
The lack of approval would prevent successful completion of this contract and preclude payment to
the contractor for required work.
r'
� � I III III Ill l Ill II II I VIII iIl ill I Illi I Illi l Ii IIII II
3 Recording Requested By:
Centra Costa County Public Works Dept. CONTRA COSTA CO Recorder Office
Construction Division STEPHEN 1, WEIR Clerk-Recorder
255 Glacier Drive DOC— 200 -�0322709-00
Martinez, CA 34553 Wedmosday, SEP 11, 2002 13:54:11
FRE $0.00
Return to: Ttl Pd $0,00 Nbr-0001040204
Irc/R9/1-1
WHEN RECORDED, RETURN TO CLERK
BOARD OF SUPERVISORS
BOARD OF SUPERVISORS, CONTRA COSTA COUNTY, CALIFORNIA
In the Matter of Accepting and Giving ) RESOLUTION OF ACCEPTANCE
Notice of Completion of Contract for } and NOTICE OF COMPLETION
Livorna Road AC Overlay ) (C.C. § 3086, 3093)
Proiect No.0662-6R4236-02 } RESOLUTION NO. 2002/ 521
The Board of Supervisors of Contra Costa County RESOLVES that:
The County of Contra Costa on May 22, 2002 contracted with Top Grade Construction, Inc., for
pavement overlay over a portion of Livorna Road from Danville Blvd. to Acacia Lane in the Alamo area,
with St. Paul Fire and Marine Insurance Company as surety, for work to be performed on the grounds of
the County; and
The Public Warks Director reports that said work has been inspected and complies with the approved
plans, special'provisions and standard specifications and recommends its acceptance as complete as of
July 31, 2002.
Therefore, said work is ACCEPTED as completed on said date, and the Clerk shall file with the County
Recorder a copy of this Resolution and Notice as a Notice of Completion for said contract.
PASSED BY THE BOARD on September 10, 2002 by the following vote:
AYES: Supervisors Gerber, Uilkema, DeSaulnier, Glover, and Gioia
NOES: None
ABSENT: None
CERTIFICATION AND VERIFICATION
I hereby certify that this is a true and correct copy of an
Contact. Mike Carlson (925)313-2321 action taken and entered on the minutes of the Board of
Orig. Dept.:Public works(Const.) Supervisors on the date shown.
cc: Record and Return
Auditor
Public Works- Accounting ATTESTED: September 10-2002
- Construction, R. Bruno JOHN SWEETEN, Clerk of the Board of Supervisors and
- Env.,C. Sellgren County Administrator
- Traffic,S. Kersevan
Contractor
r
RB:kl By �,Deputy
G:\GrpData\Const\BOQ002\10-September\ACCEPTANCE-LivornaRDAC.doc
RESOLUTION NO. 2002/ 521
Y;
Recording Requested By: CONTRA COSTA Co Recorder Office
Contra Costa County Public works Dept.
Construction Division STEPHEN L� WEIR Clerk-Recorder
255 Glacier Drive DOC— 2@&-032271 @-00
Martinez, CA 94553 Wednesday, SEP 11, 2002 13:54:16
FRE $,0.00
Return to: Tt l Pd $0.00 Nbr-0001040205
WHEN RECORDED, RETURN TO CLERK I r c/R9/1-2.
BOARD OF SUPERVISORS
BOARD OF SUPERVISORS, CONTRA COSTA COUNTY, CALIFORNIA
In the Matter of Accepting and Giving } RESOLUTION OF ACCEPTANCE
Notice of Completion of Contract for } and NOTICE OF COMPLETION
Park Avenue Improvements } (C.C. § 3086, 3093)
Project No.0662-6R4226-02 ) RESOLUTION NO. 20021 522
The Board of Supervisors of Contra Costa County RESOLVES that:
The County of Contra Costa on June 19, 2002 contracted with B & B Grading & Paving, Inc., for
reconstruction of a portion of Park Avenue from Sussex Street to Kilburn Street in the Clyde area, with
Great American Insurance Company as surety, for work to be performed on the grounds of the County,
and
The Public Works Director reports that said work has been inspected and complies with the approved
plans, specialprovisions and standard specifications and recommends its acceptance as complete as of
August 15, 2002.
Therefore, said work is ACCEPTED as completed on said date, and the Clerk shall file with the County
Recorder a copy of this Resolution and Notice as a Notice of Completion for said contract.
PASSED BY THE BOARD on September 10, 2002 by the following vote:
AYES: Supervisors Gerber, Uilkema, DeSaulnier, Glover, and Gioia,
NOES: None
ABSENT: None
CERTIFICATION AND VERIFICATION
I hereby certify that this is a true and correct copy of an
Contact: Mike Carlson (925)313-2321 action taken and entered on the minutes of the Board of
Orig. Dept.:Public works(Const) Supervisors on the date shown.
cc: Record and Return
Auditor
Public works- Accounting ATTESTED: September 10, 2002
- Construction,R.Bruno JOHN SWEETEN, Clerk of the Board of Supervisors and
Env.,C. Se#!gran County Administrator- Traffic, S. Kersevan
Contractor
R8:kj By Deputy
G:tGrpData\Const\803 2002\10-September\ACCEPTA#NCE-ParkAve.doc
RESOLUTION NO. 20021 522
THE BOARD OF SUPERVISORS OF CONTRA COSTA COUNTY,CALIFORNIA
Adopted this Resolution on September 10, 2002 by the following vote: coy
AYES: Supervisors Gerber, Uilkema, DeSaulnier, Glover, and Gioia
NOES: None
ABSENT: Nene
ABSTAIN: None
RESOLUTION NO. 2002/ 5 2 3
SUBJECT: Approve and Authorize the Public Works Director to fully close a portion of San
Pablo Darn Road on September 15, 2002 from 7:00 a.m. through 7:00 p.m.,for the
purpose of the El Sobrante Stroll, El Sobrante area. (District I)
RC-02-07
IT IS BY THE BOARD RESOLVED that permission is granted to El Sobrante Chamber of
Commerce to fully close San Pablo Dam Road,except for emergency traffic,on September 15,2002
for the period of 7:00 a.m. through 7:00 p.m. subject to the following conditions:
1. Traffic will be detoured via traffic control plan approved by public works.
2. All signing to be in accordance with the State of California Manual of Traffic Controls.
3. El Sobrante Chamber of Commerce shall establish and maintain free of obstruction,a 20-foot
wide emergency lane through the entire length of the closure for use by emergency vehicles
and personnel during the closure.
4. El Sobrante Chamber of Commerce shall comply with the requirements of the Ordinance
Code of Contra Costa County.
5. Have on file with the County Public Works Department at the Application and Permit Center
a Certificate of Insurance in the amount of$1,000,000 for Comprehensive General Public
Liability, which names the County as an additional insured.
b. Obtain approval for the closure from the Sheriff's Department,the California Highway Patrol
and the.Fire District.
I hereby certify that this is a true and correct copy of an action
BH:ew taken and entered on the minutes of the Board of Supervisors on
G:�GrpDatalEnssv®\Bo\2002\9-10-02\RC-02-07 BOl.doc the date shown.
Originator:Public Works(APC)
Contact: Bob Hendry(335-1375) September o mb e r 10 2002
ATTESTED: p �
c" cxP
Sheriff-Patrol Div.Commander JOHN SWEETEN,Clerk of the Board of Supervisors and
County Administrator
By ,Deputy
RESOLUTION NO. 2002/ 5 2 3
TO: BOARD OF SUPERVISORS i
FROM: MAURICE M. SHIU, PUBLIC WORKS DIRECTOR
DATE: September 10, 2002
SUBJECT: APPROVE and AUTHORIZE the Public Works Director to Execute an Agreement for
Real Property Services between the County of Contra Costa and Dean Chapman &
Associates for the State Route 4 East, Railroad Avenue to Loveridge Road Project,
Pittsburg Area
Project No.:46601-6X4287
SPECIFIC REQUEST(S)OR RECOWENDATION(S)&BACKGROUND AND JUSTIFICATION
1. Recommended Action:
APPROVE and AUTHORIZE the Public Works Director to execute, on behalf of Contra Costa
County an Agreement for Real Property Services with Dean Chapman & Associates in the amount
of $50,000 effective from June 1, 2002 to June 1, 2003 for appraisal and expert witness services in
connection with the State Route 4 East, Railroad Avenue to Loveridge Road Project.
I1. Financial impact:
Payments under this contract are covered from funding by the Contra Costa Transportation
Authority(OCTA). Costs will be charged directly to the project.
Ili. Reasons for Recommendations and Background:
Dean Chapman & Associates has provided appraisal services for the State Route 4 East Project in
the past. County staff members wish to continue retaining the professional services of this firm
because of its current involvement, reliable performance and experience in appraisal of the type of
parcelsinvolved. Therefore, staff is requesting approval of a $50,000 contract for appraisal and
expert witness services. The Agreement extends through the completion of all assigned tasks.
IV. Consequences of Negative Action:
The County would be unable to retain the services necessary to complete the assigned project in a
timely manner.
Continued on Attachment: SIGNATURE:
,48COMMENDATION OF COUNTY ADMINISTRATOR
RECOMMENDATION OF BOARD COMMITTEE
- APPROVE T ER
SIGNATURE(S):
ACT16N OF BOA N_S a P-t e mb e r 10, 2 OQ 2 APPROVED AS RECOMMENDED OTHER
VOTE OF SUPT* SORS
xx UNANIMOUS(ABSENT None )
AYES: NOES: I hereby certify that this is a true and correct
ABSENT: ABSTAIN: copy of an action taken and entered on the
minutes of the Board of Supervisors on the
dm:eh date shown.
G:1GrpDaWRealPropl2002-Files\BOs&RES\BODeanChapman.doc
Orlg.Div: Public Works(R/P) ATTESTED:_ September 10, 2002
Contact: D.Murdock(313-2168) JOHN SWEETEN,Clerk of the Board of
cc: County Administrator Supervisors and County Administrator
Auditor-Controller(via R/P) t
P.W.Accounting By_ Deputy
Deputy
Board Orders Senior Clerk,Adm.