HomeMy WebLinkAboutMINUTES - 09112001 - C.1 TO: BOARD OF SUPERVISORS FROM: MAURICE M. SHIU, PUBLIC WORKS DIRECTOR DATE: September 11, 2001 SUBJECT: Approve Project Contingency Fund Increase and Contract Change Order No. 1 for the San Pablo Dam Road-Morrow Drive to 1-80 Bikeway project, Project No. 4660-6X4112- 01, San Pablo area Specific Request(s)or Recommendation(s)&Background&Justification I. Recommended Action: APPROVE project contingency fund increase of $1,500 for a new total of $5,595 and Contract Change Order No. 1 in the approximate amount of $5,400. II. Financial lmpact: The project contingency funds are currently insufficient to cover the incr ased cost. The increase in contingency funds will be funded by Transportation for Clea W1 Continued on attachment: X yes SIGNATURE: ✓ RECOMMENDATION OF COUNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE cf APPROVE OTHER SIGNATURE (S): ACTION OF BOA N:SeL t . 1 1 , goo] APPROVED AS RECOMMENDED xx OTHER_ VOTE OF SUPERVISORS xx UNANIMOUS (ABSENT ) I hereby certify that this is a true and correct copy of an AYES: NOES: action taken and entered on the minutes of the Board of ABSENT: ABSTAIN: Supervisors on the date shown. Contact: Mike Carlson,(925)313-2320 ATTESTED: September 11 , 2001 Orig.Div.: PW(Constr) JOHN SWEETEN, Clerk of the Board of Supervisors and cc: County Administrator Auditor-Controller County Administrator Public Works Accounting,R.Gilchrist Construction,R.Bruno By Deputy Design Contractor RB:jc G:\G RPDATA\CONST\BO\2001\9-SEPT\11-I80B-PCC&CC01.DOC lee 6 SUBJECT: Approval of Contract Contingency Fund Increase and Contract Change Order No. 1 for the 1-80 Bikeway on San Pablo Dam Road Project, Project No. 4660-6X4112-01, San Pablo area DATE: September 11, 2001 PAGE 2 OF 2 III. Reasons for Recommendations and Background: Additional funding is needed to pay the contractor for increases in contract work. The additional work reinforced weak areas of pavement. This change exceeded the project contingency fund. Approval of the Project Contingency Fund increase is required to compensate the contractor for the extra work. IV. Consequences of Negative Action: The lack of approval would prevent successful completion of this contract and preclude payment to the contractor for required work.