HomeMy WebLinkAboutMINUTES - 08072001 - C.8 TO: BOARD OF SUPERVISORS FROM: MAURICE M. SHIU, PUBLIC WORKS DIRECTOR DATE: August 7, 2001 SUBJECT: Determine the Need to Continue the Emergency Action Regarding the Repair of Briones Valley Rd Bridge, Brentwood area Project No.: 0662-6U4094-01, CP# 01-42 SPECIFIC REQUEST(S)OR RECOMMENDATION(S)&BACKGROUND AND JUSTIFICATION I. Recommended Action: DETERMINE that there is a need to continue the emergency action taken by the Board of Supervisors on July 24, 2001, pursuant to Public Contract Code Sections 22035 and 22050, to repair the Briones Valley Road Bridge, Brentwood area Continued on Attachment: X SIGNATURE: / _RECOMMENDATION OF COUNTY ADMINISTRATOR _RECOMMENDATION OF BOARD COMMITTEE APPROVE OTHER SIGNATURE(S): ACTION OF BOARD ON Augus t 7 , 2001 APPROVED AS RECOMMENDED xx OTHER VOTE OF SUPERVISORS xx UNANIMOUS (ABSENT ) AYES: NOES: I hereby certify that this is a true and correct copy of an ABSENT: ABSTAIN: action taken and entered on the minutes of the Board of Supervisors on the date shown. BF:mp G:\GrpData\Design\Board Orders\BO 2001\ Briones Valley Road Cont..doc. Orig.Div: Public Works(Design) ATTESTED: Augus t07 , 2001 Contact: B.Fernandez-313-2294 JOHN SWEETEN, Clerk of the Board of Supervisors and County Administrator c: M. Hollingsworth,Design Public Works Accounting By , Deputy r SUBJECT: Determine the Need to Continue the Emergency Action Regarding the Repair of Briones Valley Rd Bridge, Brentwood area Project No.: 0662-6U4094-01, CP# 01-42 DATE: August 7, 2001 PAGE 2 II. Financial Impact: Total cost of repairs cannot be fully determined at this time, but staff is developing an estimate for completion of the repair. III. Reasons for Recommendations and Background: A. On July 24, 2001, the Board of Supervisors declared an emergency and authorized the Public Works Director to proceed in the most expeditious manner to repair the Bridge. B. Repair status: Plans and specifications are being developed. IV. Consequences of Negative Action: A negative action would slow the process of the replacement structure and would cause the project to be delayed to 2002