SUBJECT: CONTRACT AWARD RECOMMENDATION: DEBRIS DRYING AREA PROJECT,
PROJECT NO. 7517-6W7208-99, MARTINEZ AREA.
SPECIFIC REQUEST(S)OR RECOMMENDATION(S)&BACKGROUND AND JUSTIFICATION
i. RECOMMENDED ACTION,:
AWARD the contract for furnishing labor and materials for the subject project to Maggiora &
Ghilotti, Inc. the low bidder, in the amount of$116,186.00 and at the unit prices submitted; and
REQUIRE the contractor to present surety bonds for Payment and Faithful Performance in the
amounts of$116,186.00 and $116,186.00, respectively.
DIRECT the Public Works Director to prepare the contract for the project.
AUTHORIZE the Public Works Director to sign the contract on behalf of the Board subject to the
Director having reviewed and found sufficient all required documents, including the contract
signed by the contractor, the aforementioned surety bonds, and a certificate of insurance.
DIRECT that, in accordance with the project specifications and/or upon the execution of the
contract by the Public Works Director, any bid bonds posted by the bidders be exonerated and
any checks or cash submitted for bid security be returned.
Continued on Attachment: X SIGNATURE:
mi'k-C
KtW9MtNUA I 1UN Ut- WUNTY AUMIN15 I KA I UK
RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON APPROVED AS RECOMMENDED X OTHER
September 21, 1999
VOTE OF SUPERVISORS I hereby certify that this is a true and correct copy
UNANIMOUS (ABSENT None of an action taken and entered on the minutes of
AYES: NOES: the Board of Supervisors on the date shown.
ABSENT: ABSTAIN:
RB:kj
G:\GRPDATA\C0NST\B4\1999109-SEPT\21-DDA.DOC ATTESTED: September 21, 1999
Orig.Div.: PW(Constr)
Contact: Mike Carlson(925)313-2320 PHIL BATCHELOR, Clerk of the Board of
cc: County Administrator
Auditor-Controller Supervisors and County Administrator
Public Works;
R.Bruno,Construction
R.Gilchrist,Accounting
Design
S.B.E. Transp.Engin. By
Deputy
703 Market St.
San Francisco,CA 94103-1000
Contractor
(1 of 2)
SUBJECT: Contract Award Recommendation:
Debris Drying Area Project,
Project No. 7517-6W7208-99, Martinez area.
BOARD DATE: September 21, 1999
I. RECOMMENDED ACTION; (continued)
Pursuant to Public Contract Code Section 4114, the Board DELEGATES its functions under
Public Contract Code Sections 4107 and 4110 to the Public Works Director or his designee.
Pursuant to Section 6705 of the Labor Code, the Board also DELEGATES to the Public Works
Director or to any registered civil or structural engineer designated by him the authority to accept
detailed plans showing the design of shoring, bracing, sloping or other provisions to be made for
worker protection during trench excavating covered by that section.
DECLARE that, should the award of the contract to Maggiora & Ghilotti, Inc. be invalidated for any
reason, the Board would not in any event have awarded the contract to the second listed bidder
or any other bidder, but instead would have exercised its discretion to reject all of the bids
received. Nothing herein shall prevent the Board from reawarding the contract to another bidder
in cases where the successful bidder establishes a mistake, refuses to sign the contract or fails
to furnish required bonds or insurance (see Public Contract Code Sections 5100-5107).
11. FINANCIAL IMPACT:
The project, including engineering and appropriate overhead charges, is funded by the Clean
Water Program (100%).
Ill. REASONS FOR RECOMMENDATIONS AND BACKGROUND:
The plans and specifications were approved and the project advertised for bids by the Board of
Supervisors on August 3, 1999. The bids were received and opened at 255 Glacier Drive,
Martinez, California, on Tuesday, September 14, 1999. The construction bids received were as
follows:
1. Maggiora & Ghilotti, Inc..........................................................................$116,186.00
2. William G. McCullough Company...........................................................$121,821.30
3. MCK Services, Inc..................................................................................$123,324.20
4. Fanfa, Inc. ..............................................................................................$126,500.00
5. Rios Grading, Inc. ..................................................................................$131,877.00
6. Gilbert Excavating, Inc. ..........................................................................$146,297.00
7. Carone & Company, Inc.........................................................................$149,100.00
8. Bruce Carone Grading & Paving, Inc. ....................................................$157,714.00
9. Gordon N. Ball, Inc.................................................................................$157,780.00
10. J. A. Gonsalves & Sons, Inc...................................................................$304,812.00
The Engineers estimated construction cost was $112,000.00.
(2 of 2)
TO: BOARD OF SUPERVISORS
FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR
DATE: SEPTEMBER 21, 1999
SUBJECT: APPROVE PROJECT CONTINGENCY FUND INCREASE OF $44,000.00 FOR THE 1999
SLURRY SEAL PROJECT, PROJECT NO. 0672-6U2178-99 AND 4660-6X2959-99,
VARIOUS COUNTY LOCATIONS
Specific equest(s)or Recommendation(s)&Sackgrouncl&Justification
1. Recommended Action:
APPROVE Project Contingency Fund increase of $44,000.00 in order to compensate the
contractor, California Pavement Maintenance Company, Inc. for unforeseen extra work.
11. Financial ImRact:
The increase in the contingency fund will be funded by City of Oakley Funds (100%).
Continued on attachment: X yes SIGNATURE:
04 1 lGle C404C—
RECOMMENDATION OF COUNTY ADMINISTRATOR
RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON: September 21.1999 APPROVED AS RECOMMENDED X OTHER
I hereby certify that this is a true and correct copy of an
action taken and entered on the minutes of the Board of
Supervisors on the date shown.
VOTE OF SUPERVISORS
X UNANIMOUS (ABSENT None) ATTESTED: September 21, 1999
AYES: NOES: PHIL BATCHELOR, Clerk of the Board of Supervisors and
ABSENT: ABSTAIN: County Administrator
Contact: Mike Carlson, (925)313-2320 By
Deputy
Orig. Div.: PW(Constr)
cc: County Administrator
Auditor-Controller
Public Works
- Accounting, R. Gilchrist
- Construction, R. Bruno
- Design
Contractor
RB:kj
\\PWS1\SHARDATA\GRPDATA\C0NS-RB0\1 999\09-SEPT\21-99SS-PCC.DOC
1-57-e7
SUBJECT: Approve Project Contingency Fund Increase
1999 Slurry Seal Project, Project No. 0662-6U2178-99&4660-6X2959-99,
Various County Locations
DATE: September 21, 1999
PAGE: 2 of 2
Ill. Reasons for Recommendations and Background:
Additional funding is needed to pay the contractor for the extra work performed. This work included
applying a slurry seal to numerous streets in the Oakley area that were not part of the original
contract.
IV. Consequences of Negative Action:
The lack of approval would preclude payment to the contractor for work required for the successful
completion of the contract.
TO: BOARD OF SUPERVISORS
FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR
DATE: SEPTEMBER 21, 1999
SUBJECT: APPROVE PROJECT CONTINGENCY FUND INCREASE AND APPROVE CONTRACT
CHANGE ORDER NO. 1 FOR THE TAYLOR BLVD. GUWRAIL UPGRADE PROJECT,
Project No. 0662-6R4053-99, IN THE LAFAYETTE AREA
peci is Request(s) or Recommendation(s)&Bac groun us i ica ion
I. Recommended Action:
APPROVE Project Contingency Fund increase of$40,000.00 and Contract Change Order No. 1
in the approximate amount of$38,000.00 and AUTHORIZE the Public Works Director to execute
it in order to compensate the contractor, McGuire and Hester, for unforeseen extra work.
II. Financial Impact:
The Project Contingency Funds are currently insufficient to cover the cost of extra work. The
increase in contingency funds will be funded by the Federal Hazard Elimination and Safety Funds
(100%).
Continued on attachment: X yes SIGNATURE: G--
RECOMMENDATION OF COUNTY ADMINISTRATOR
RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE (S):
ACTION OF BOARD ON: beptemper 211 iJJJ APPROVED AS RECOMMENDED X OTHER
I hereby certify that this is a true and correct copy of an
action taken and entered on the minutes of the Board of
VOTE OF SUPERVISORS Supervisors on the date shown.
X UNANIMOUS (ABSENT None)
AYES: NOES: September 21, 1999
ABSENT: ABSTAIN: ATTESTED:
PHIL BATCHELOR, Clerk of the Board of Supervisors and
Contact: Mike Carlson, (925)313-2321 County Administrator
Orig. Div.: PW(Construction)
cc: County Administrator By 2jkLAK , Deputy
Auditor-Controller
Public Works
- Accounting, R. Gilchrist
- Construction, R. Bruno
- Design
Contractor
RB:kj
G:\GRPDATA\CONST\BO\1999\09-S EPT\21-TP H-PCC-CCO.D OC
SUBJECT: APPROVAL of Contract Contingency Fund Increase and Contract Change Order No. 1
For the Taylor Blvd. Guard Rail Project
DATE: September 21, 1999
PAGE: 2 of 2
Ill. Reasons for Recommendations and Background:
The scope of work was increased to insaii a concrete barrier at the inside curve on Taylor Blvd. to
the bridge abutment. Changes made exceed the limits specified in Public Contract Code Section
20395 and exceeded the project contingency fund. APPROVAL of the Change Order and Project
Contringency Fund increase is REQUIRED
IV. Consequences of Negative Action:
The lack of APPROVAL would prevent successful completion of this contract and preclude
payment to the contractor for required work.