Loading...
HomeMy WebLinkAboutMINUTES - 09221998 - C1-C5 CONTRA COSTA Co Recorder's office STEPHEN L. WEIR, County Recorder Recording Requested By: Contra Costa County Public Works Dept. DOC - Sit-W-0a:3 744 i --oo Construction Division Wednesday, SEP 23, 1998 14424,-42 255 Glacier Chive FRE $0.0011, Martinez,CA 94553 Tt 1 Pd $0.00 Nbr-0000267909 Return to: i rc /R9 WHEN RECORDED,RETURN TO CLERK BOARD OF SUPERVISORS BOARD OF SUPERVISORS, CONTRA COSTA COUNTY, CALIFORNIA In the Matter of Accepting and Giving } RESOLUTION OF ACCEPTANCE Notice of Completion of Contract for and NOTICE OF COMPLETION (C.C. § 3086, 3093) El Portal Overlay ) RESOLUTION NO. 98/477 Proiect No. 0662.6R4121-96 ) The Board of Supervisors of Contra Costa County RESOLVES that: The County of Contra Costa on August 27, 1997 contracted with Bay Cities Paving & Grading, Inc. for constructing curb ramps, minor road widening, shoulder work, AC dike, asphalt concrete grinding, overlay and signal modification in the San Pablo/El Sobrante area, with Liberty Mutual, as surety, for work to be performed on the grounds of the County; and The Public Works Director reports that said work has been inspected and complies with the approved plans, special provisions and standard specifications and recommends its acceptance as complete as of August 31, 1098. Therefore, said work is ACCEPTED as completed on said date, and the Clerk shall file with the County Recorder a copy of this Resolution and Notice as a Notice of Completion for said contract. PASSED BY THE BOARD on September 22, 1998 by the following vote: AYES: Supervisors Uilketna, Gerber, DeSaulnier, Canciamilla., and Rogers NOES: Mane ABSENT: Nene CERTIFICATION AND VERIFICATION I hereby certify that this is a true and correct copy of an action taken and entered on the Contact: Joseph P.Murphy, (925)313-2321 minutes of the Board of Supervisors on the Orig. Dept.:Pubiic Works(Const.) date shown. o cc: Record and return ,ATTESTED: Auditor PHIL BP i Cii g IiLcrd Public Works - Accounting of supervisors anis County Admir istrutor - Construction,R. Bruno : Deputy Traffic, S. Kersevan Bys Contractor JPM:SI.Elt G:1GrpData\Const\BOO EPO-22-t9.doc TO.'- BOARD OF SUPERVISORS FROM: J. MICHAEL WALFORD,PUBLIC WORKS DIRECTOR DATE: September 22, 1998 SUBJECT: Approve Dimm Way Slide Repair Project, Richmond Area. Project No. 0672-6R6359 CDD-CP #98-60 Specific Request(s) or Recommendation(s) & Background & Justification 1. RECOMMENDED ACTION: APPROVE Project, and DETERMINE that the project is a California Environmental Quality Act'(CEQA) Class 1c Categorical Exemption, and DIRECT the Public Works Director to prepare contract plans and specifications for construction. DIRECT the Director of Community Development to file a Notice of Exemption with the County Clerk, l A06�//Ae Continued on Attachment: X SIGNATURE RECOMMENDAT15N OF COUNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE —APPROVE —OTHER SIGNATURE(S): ACTION OF BOARD ON September 22, 1998 APPROVED AS RECOMMENDED VOTE OF SUPERVISORS X UNANIMOUS(ABSENT None ) AYES: _ __ NOES: I hereby certify that this is a true and correct ABSENT: ABSTAIN:_ _ copy of an action taken and entered on the minutes of the Board of Supervisors on the date shown. g:%dssign%boNdimmway sgde9.22.doc ATTESTED � f Orig.Div: Public Works(Design Division) PHIL BATOHE OR, Clerk of th,,- 130.ird Contact: J.Fishy,Maintenance of Supervisors and C unty Administrator i cc! County Administrator Attn: EKuevor DeputyAutl for-Controller By PW Acccunting Construction Community Development-A.Woods J.Frattini,Design SUBJECT: Approve Dimm Way Slide Project, Richmond area. Project No.0572-585359, CDD-CP #98-60 BATE: September 22, 1998 PAGE: 2 DIRECT the Public Works Director to arrange for payment of the $25.00 handling fee to the County Clerk for filing of the Notice of Exemption. 11. FINANCIAL IMPACT: The estimated project cost is $10,000, funded by FEMA (20%), Local Road funds (80%) Ili. REASONS FOR RECOMMENDATION/BACKGROUNDS The project includes repairing a bank erosion/bridge scour. It is needed-to restore structural integrity of the roadway. IV. CON'SEQU'ENCES OF NEGATIVE ACTION: Delay in approving the project will result in a delay of design and construction and may jeopardize funding. _.......... _. _ __ _ ....._ ........ ..... ........ _._. _....._. .. ...._ ..........._.... TO: BOARD OF SUPERVISORS AS THE GOVERNING BODY OF THE CONTRA COSTA COUNTY FLOOD CONTROL AND WATER CONSERVATION DISTRICT FROM: J. MICHAEL WALFORD, CHIEF ENGINEER DATE: September 22, 1998 SUBJECT: Approve-Wildcat Creek Desilting Project, Richmond Area. Project No. 7527-6D9PO3 CDD-CP #98-63 Specific Request(s) or Recommendation(s) & Background & Justification 1. RECOMMENDED ACTION: APPROVE Project, and DETERMINE that the project is a California Environmental Quality Act (CEQA) Class 4g Categorical Exemption, and DIRECT the Chief Engineer to prepare contract plans and specifications for construction. DIRECT the Director of Community Development to file a Notice of Exemption with the County Clerk. Continued on Attachment: X SIGNATURE: G� RECOMMENDATION 3F COUNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE —APPROVE OTHER SIGNATURE(S): ACTION OF BOARD ON September 22, 1998 APPROVED AS RECOMMENDED _ VOTE OF SUPERVISORS UNANIMOUS{ABSENT None ) AYES: NOES: ABSENT: ABSTAIN: I hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board of Supervisors on the g1design%botwcdesift9-22.98.doc date shown. 0r1g.biv Public Works(Design Division) ATTESTED. Contact: T.Jensen,Flood Control (313-2276) PHIL BA CCH E , (iG'14 i)f cc: County Administrator Atte: E.Kuevor of Supervisors ana' C unty Administrator Auditor-Controller PW Accounting Construction By < ,�.t Deputy Construction Community Development-A.Woods J.Frattim,Design SUBJECT: Approve Wildcat Desilting Project, Richmond area. Project No. 7527-6D9P03, CDD-CP #98-63 DATE: September 22, 1998 PAGE: 2 DIRECT the Chief Engineer to arrange for payment of the $25.010 handling fee to the County Clerk for filing of the Notice of Exemption. H. FINANCIAL IMPACT: The estimated project cost is $105,000, funded by Flood Control Zone 7 (58'%) and FEMA funding (42%) III. REASON'S FOR RECOMMENDATION/BACKGROUND: The project includes excavating approximately 15,000 cy of material from basin. It is needed-to increase basin retention capacity. IV. CONSEQUENCES OF NEGATIVE ACTION: Delay in approving the project will result in a delay of design and construction and may jeopardize funding. rC : BOARD OF SUPERVISORS FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR DATE: September 22, 1998 SUBJECT: Determine the Need to Continue the Emergency Action Regarding the Repair of the Alhambra Valley Road Bank Erosion at Pinole Creek, and the Alhambra Valley Road slide 2.7 miles east of Bear Creek Road, Pinole Area Project No: 0672-6R6356.98and 0672-686355.98, respectively 1. Recommended Action: DETERMINE that there is a need to continue the emergency action taken by the Board of Supervisors on April 14, 1998 pursuant to Public Contract Code Sections 22035 and 22050, to repair the Alhambra Valley Road Bank Erosion at Pinole Creek, and the Alhambra Valley Road Slide 2.7 miles east of Bear Creek Road, Pinole Area. 11. Financiallmpact: There is no impact to the general fund. Plans, specifications and engineer's estimate are complete. The preliminary cost estimates for the projects indicatea construction cost of $110,000, and $90,000 respectively. The projects cannot be constructed as designed this year due to environmental permitting constraints. However, efforts to stabilize the slides are under design and are scheduled to be completed by late September. Continued on Attachment: X SIGNATURE. A44 RECOMMENDATION OF COUNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE —APPROVE OTHER SIGNATURE(S): ACTION OF BOARD ON ep r 7 APPROVED AS RECOMMENDED_X_ VOTE OF SUPERVISORS I hereby certify that this is a true and correct X UNANIMOUS{ABSENT None ) copy of an action taken and entered on the AYES: NOES: minutes of the Board of Supervisors on the ABSENT: ABSTAIN: date shown, ATTESTED: MM:iig PHIL_BATCH t.OR, Clerk of vie r.,oard g:ldesignlbo\AlVatPinoles-22.58.doe of Supervisors and County Administrator Orig.Div: Public Works(Design) B Deputy Contact: Melissa Morton(313-2225) y cc: Auditor/Controller County Counsel Construction Div.-R.Bruno Maintenance Div. Transp. Engineering 12otermine the Need to Continue the Emergency Action Regarding the Repair of the Alhambra Valley Road Bank erosion at Pinola Creek, Pinola Area September 22, 1998 Page 'Two Ill. Reasons F2r Regommendations And Background: The excessive rains of February 2, 1998 and debris in an unmaintained creek, caused storm waters from Pinole Creek to flow over Alhambra Valley Road, washing out the embankment on the far side of the crossing. In addition, high flows in Vaca Creek caused a slide to undercut Alhambra Valley Road at a point approximately 2.7 miles east of the intersection with Bear Creek Road. Alhambra Valley Road accommodates more than 4,200 vehicles per day. If the slide is allowed to progress and a road closure becomes necessary, east/west traffic between Central and West County along this corridor would no longer be possible. Immediate repair of this washout is necessary to assure the road=s stability. Since Alhambra Valley Road is included in the federal highway system and with the federal designation of Contra Costa County as a disaster area, it qualifies for Federal Highway Administration funds to make the repairs. If we were to follow our normal construction contract advertisement and approval process, the slide stabilization could not begin until early October. Pursuant to provisions of Sections 22035 and 22050 of the Public Contract Code, when the appropriate findings of an emergency are made by the Board of Supervisors, the normal bidding procedures are waived and stabilization can begin immediately. We are, therefore, recommending that the Board continue the emergency action and direct the Public Works Director to proceed with the project and enter into any necessary contracts to ensure completion of slide stabilization in the most expeditious manner. IV. Conseguences-of Negative Action: Non-concurrence of the above recommendation will significantly delay stabilization of the slides which would result in potential road failure and road closure. _..... .11.11 __ ....... .... .. TO: BOARD OF SUPERVISORS 1..6 FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR DATE: September 22, 1998 SUBJECT: Determine the Need to Continue the Emergency Action Regarding the Repair of the Fish Ranch Road Slide, Orinda area. Project No: 0672-6R6346 1. Recommended Action: DETERMINE that there is a need to continue the emergency actiontaken by the Board of Supervisors on March 24, 1998, pursuant to Public Contract Code Sections 22035 and 22050, to repair the Fish Ranch Road Slide, Orinda area. if. Financial lmpact: There is no impact to the general fund. Plans, specifications and engineer's estimate are complete. The project is currently under construction, and the upper slide is complete. The lower slide has been delayed due to utility conflicts. However, the entire project should be completed by mid-October. The expected contract cost based on the low bid is $684,651. 1 Continued on Attachment: X SIGNATURE: _RECOMMENDATION OF COUNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE —APPROVE OTHER SIGNATURE(S): ACTION OF 130ARD ON , TM APPROVED AS RECMAMENDED VOTE OF SUPERVISORS i hereby certify that this is a true and correct X UNANIMOUS (ABSENT NaIF- ) copy of an action taken and entered on the AYES: NOES: ABSENT: ABSTAIN. minutes of the Board of Supervisors an the date shown. ATTESTED: f ' MM:jfg PHIL BATCHLOR, Clerk of the Board G:\GRPDATA\DESIGN\B0TlSH RANCH EMt RG 9-22.98.DOC of Supervisors and County Administrator Orig.div: Public Works{Design} r ,ty� Deputy Contact: Melissa Morton{313-2225) By p y cc: Auditor/Controller County Counsel Construction Div.-R. Bruno Maintenance Div. Transp.Engineering -Determine the Need to Continue the Emergency Actlon Regarding the Repair of the Fish Ranch Road Slide, Orinda ArF-a September 22, 1998 Page Two Ill. Reasons For Recommendations And Background: Fish Ranch Road has been damaged by a landslide which affected the uphill, north bound lane and approximately three feet of the downhill, south bound lane. The slide scarp has dropped approximately one foot below road surface, creating a dangerous condition which necessitated closing the road February 21, 1998. The Public Works Department was able to make temporary repairs to the slide damaged roadway which facilitated opening the south bound lane on March 9. Slide movement has slowed, but further movement and increased pavement damage is expected over the next few weeks as groundwater continues to accumulate at the slide site. A small slide along the edge of the north bound lane approximately half a mile from the larger site will also be repaired as part of this project. Fish Ranch Road carries 6,009 vehicles per day and this traffic has been severely hampered by the closure of the road from February 21 to March 9, and the subsequent closure of the north bound lane to date. Since Fish Ranch Road is included in the federal highway system and with the federal designation of Contra Costa County as a disaster area, it qualifies for Federal Highway Administration funds to make the repairs. To receive 100% funding for this repair, the work must be completed within 180 days of the February 2, 1998 emergency declaration. After that time, only 88.5% financing is available and the County will have to pay the 11.5% matching funds. If we were to follow our normal construction contract advertisement and approval process, the slide repair would not have begun until early September. 4n March 24, 1998, pursuant to provisions of Sections 22035 and 22050 of the Public Contract Code, the Board of Supervisors declared an emergency for the slide repair, allowing the normal bidding procedures to be waived and repairs to begin immediately. We recommend that the Board continue the emergency action to ensure;completion of the repair in the most expeditious manner. IV. Consequences of Negative Action: Non-concurrence of the above recommendation will significantly delay completion of the repair of the roadway, prolonging impacts to traffic flow.